DAVID B POLLACK
**** ******* ******, ********, ** 11710-
E-mail: acegt1@r.postjobfree.com
www.linkedin.com/in/davepol
SUMMARY
I am a Mechanical Engineer with extensive experience in construction
project management. Emphasis on construction and installation of major
mechanical systems, HVAC, MEP, environmental, plumbing systems, fire
protection, hazardous material abatement, and safety compliance. Directing
and managing of project development from pre-bid to closeout, experienced
in field construction inspection, Quality Assurance/Quality Control and
coordination of all types of construction activities. Well acquainted with
New York City's: construction procedures, building codes, standards and
specifications.
WORK EXPERIENCE
Parsons Brinckerhoff/ISS, One Penn Plaza, New York, NY 10119
Sept 2013 - Present
Mechanical Engineer
Performed comprehensive Building Condition Assessment Survey of school
facilities throughout NYC either owned or leased by New York City
Department of Education (DoE). To meet state-mandated reporting
requirements and to support the DoE's Five Year Capital Plan, by assessing
the physical condition of the buildings mechanical systems. The project
involved a detailed visual inspection of each facility's physical
condition, identifying deficiencies, estimating costs and assessing
infrastructure issues. I wrote detailed reports of each DoE asset, which
contained the condition rating, life cycle rating of the buildings existing
mechanical equipment/components with their deficiencies, quantities and
ratings, including the building violation status, priority conditions, and
overall building comments. Then coordinated the data, and reported Quality
Assurance, Quality Control (QA/QC) findings with the School Construction
Authority. Generate priced deficiency data from the Deficiency Cost
Program, and identified/adjusted the pricing methodology contained in the
program. Looked for priority, hazardous, and unsafe conditions identified
during inspections, and notified the SCA immediately
New York City, Department of Environmental Protection
Dec 1983 - Sept 2013
Bureau of Engineering Design & Construction, 96-05 Horace Harding
Expressway, Corona, NY 11368
Associate Project Manager
Responsible for planning, coordinating and directing the effective and
timely implementation of the construction of complex capital projects.
Formally evaluate the performance of contractors, reporting on
discrepancies, and/or unsatisfactory performance. Monitor contractor
operations, Quality Assurance/Quality Control by inspecting to assure
compliance with the contract documents. Prepare comprehensive daily reports
indicting observations of work performed each day. Insure that the daily
safety standards are maintained. Conduct acceptance inspections and
generate punch lists to ensure contractor completion. Resolve problems that
arise during the construction process. Maintain a management information
system by providing data, for the planning and control of project
development. Investigate and advise concerning contract disputes and
appeals. Prepare contract and project documentation. Review and comment of
project schedule (CPM). Draft, approve and negotiate change orders. Assist
in conducting meetings and prepare agendas/minutes. Draft correspondence to
the contractors. Verify, then approve and process, contractor and
consultant payments.
Recent Projects and Achievements Include:
. Bowery Bay WWTP: Contracts 58G, 58H, & 58E - $34M & Meet requirements of
the State Pollution Discharge Elimination System, ensured plant
reliability, reduced operational manpower requirements, at a huge cost
savings to NYC. (2006 - 2013)
. Clearview & 24th Avenue Pumping Station and Force Main: Contract PS-82-
107, $24M. Is part of the NYC Green Infrastructure Plan, was able to
reduced CSO discharges by approximately 90%. (YR: 2001 - 2006)
. Shaft 21, Water Tunnel #1: C601, $17M. Inspected, and video tapped using
an underwater ROV, 800 feet below street level, the 12 foot diameter
shaft 21, dewatering valve where it punctuates the lowest point of NYC
water system. (YR: 2000 - 2001)
. Gowanus Canal Flushing Tunnel: Contracts 15G, 15E, 15D & 16 - $42M. The
Gowanus Canal is a Superfund site, designated by US EPA. Successfully
increased the dissolved oxygen levels in the Gowanus Canal, improved the
overall water quality, mitigated the effects of CSO and increased the
capacity of the pumping station from 20MGD to 30MGD. (YR: 1996 - 2000)
. Rikers Island Pumping Station and Force Main: Contract PS-112, $15M. Is
now in compliance with FEMA elevation requirements, and also reduced CSO
discharges. (YR: 1991-1996)
H. Sand & Co., Mechanical Contractors & Engineers - 215 Park Avenue
South, New York, NY Feb 1983 - Dec 1983
Office Engineer - Wrote detailed proposals for change order work and
negotiated settlements with general contractors. Made takeoffs and worked
on bids proposals for high rise commercial buildings and capital
improvement mechanical construction contracts.
Projects Include: Trump Tower, 180 Maiden Lane, and 7 Hanover Square
EDUCATION
BS - Mechanical Engineering, 1982: SUNY, University at Buffalo, School of
Engineering and Applied Science, Buffalo, NY 14260
COMPUTER SKILLS
. Microsoft Office Suite
CERTIFIED TRAINING COURSES
. NYC DEP EH&S Construction Superintendent's Course, OSHA 29 CFR 1926, &
NYC DOB Chapter 33 Section BC 3301
. OSHA 10 hour Construction Safety, According to 29 CFR 1926, 29 CFR
1910
. On-Site Project Management Course
. Scaffolding Competency User
. Confined Space Entry/Rescue
. Control of Hazardous Energy (Lock-Out/Tag Out)
. Emergency and Spill/Release Notification/Reporting
. Excavation and Trenching Competency Course.