SUMMARY:

I am a common sense, results-oriented problem solver with an old-fashioned work ethic who believes in company loyalty and customer satisfaction.

SKILLS:

• Communication

• Team Building

• Job Planning

• Drawing & Specification Review

• Bid Package/Scope Preparation

• Bid / Award Administration

• Contractor Coordination

• Cost Control

• Scheduling / Planning

• Site Logistics

• Change Order Administration

• Claim Analysis

• Job Site Inspections

• Site Safety Administration

o STS Certified

o OSHA 30 Hour

o Safety Inspections

• Punch Lists

• Contract Close-Out

• Public Speaking

• Computer & Office Applications

o MS Office

o Adobe

o Blue Beam

o Contract Manager

o Primavera

o MS Project

o BIM 360

PROJECTS AND EXPERIENCE:

AECOM / URS / Hunt Jan 2013 to October 2018

Flex-N-Gate, Grand Prairie, TX May 2018 to Oct 2018

• Construction Manager - Design/Build GC conversion of warehouse space to manufacturing facility. $18 M. General Motors, Spring Hill Assembly Aug 2016 to May 2018

• Project Manager - IMN Building Addition – 58,000 sf Addition to operating plant. $13.5 M.

• Project Manager - CSS PT Addition – 209,000 sf Building Addition and 200,000 sf renovation of operating plant. Blasted & excavated 400,000 cy of soil & rock. $38 M.

• Project Manager - West Haul Lot – 750 space paved & lighted lot for staging / loading vehicles on haulers. $ 4 M.

• Construction Manager - Cross Rail Dock Bldg – 125,000 sf Greenfield Building with truck docks and railroad. $16 M.

• Construction Manager - SGE Program – Demolition and Renovations to operating auto assembly plant, engine plant, and body stamping buildings. $50 M.

• Construction Manager - Haul-Away Program - Construction of docks, truck lots, and roadways for site logistics building. $10 M

General Motors, Wentzville Assembly Apr 2014 to Aug 2014

• Night Shift Coordinator - Press Building Addition demolition for tie-in to existing building. Sprinkler & lighting installations. $150 M.

General Motors, Spring Hill Stamping Feb 2014 to Apr 2014

• Project Coordinator - Installation of Compass Systems shredder and conveyor system for new AAA Press. $2 M. General Motors, Bowling Green Corvette Assembly Aug 2013 to Feb 2014

• Construction Manager – Engine Build Facility - 15,000 sf Building Addition plus Renovations to operating plant. $7 M. General Motors, Spring Hill Stamping Jan 2013 to Aug 2013

• Construction Manager - AAA-Press Pit – 80’ x 125’ x 30’ stamping pit excavation and construction inside operating plant, immediately adjacent to working press. Crushed stone onsite for use as mass fill, later. Poured 2500cy base mat in one day. Built structural concrete deck. $50 M. Sorenson Gross Construction Services Nov 2011 to Jan 2013 General Motors, Spring Hill Power Train

• Project Coordinator – LGE Engine Line Program – Supervision of process equipment installation, Project Tracking, and Claim Analysis. Produced Project Manual for all equipment. $100 M. URS / Washington Group Apr 2011 to Oct 2011

General Motors, Bowling Green Assembly

• Project Coordinator –500,000 sf roofing renovation at the operating GM Corvette plant. $950,000 Tennessee Department of Commerce and Insurance, Nashville, TN Apr 2004 to Apr 2011

• State Electrical Inspector, Columbia, TN - Performed electrical inspections for commercial, residential, and industrial installations. Duties also included obtaining regular CEU’s and educating electricians as needed. Morrison Knudsen / URS / Washington Group International - Boise, ID Feb 1988 to Jan 2004

• Senior Scheduler – Mercedes Benz, Plant Construction, Tuscaloosa, AL

• Scheduling Consultant – General Motors, Plant Expansion, Shreveport, LA

• Construction Manager – Saturn Assembly, SUV Expansion and Press Bldg Addition, Spring Hill, TN

• Project Engineer / Office Manager – General Motors, Plant Renovation / Retooling, Janesville, WI

• Project Scheduler – General Motors, Plant Renovation / Retooling, Janesville, WI

• Project Scheduler – General Motors, Plant Renovation / Retooling, Doraville, GA

• Project Scheduler – General Motors, Plant Renovation / Retooling, Linden, NJ

• Project Scheduler – Delco Electronics, Misc Projects, Oak Creek, WI

• Purchasing Agent – Saturn Auto Plant Construction, Spring Hill, TN Tennessee Department of Commerce & Insurance, Nashville, TN Mar 1986 to Jan 1988

• State Electrical Inspector for the construction of the Saturn Auto Plant Other Pertinent Experience

• Electrician

• Plumber

• Remodeling & Maintenance Contractor

• US Navy

REFERENCES

Bill Mortimer

Project Manager

GM Global Facilities

810-***-****

ac8g1m@r.postjobfree.com

Tim Rogers

Automotive Group Manager

AECOM / Hunt

248-***-****

ac8g1m@r.postjobfree.com

Tom Wilkinson

Sr. Project Manager

AECOM Hunt

615-***-****

ac8g1m@r.postjobfree.com

Steven Morgan

Sr. Pastor

Destiny Church, Columbia, TN

931-***-****

ac8g1m@r.postjobfree.com

Greg Spears

Facility Engineer

GM Spring Hill

931-***-****

ac8g1m@r.postjobfree.com

Randy Tosh

Building Inspector