CHAITRA ADARI, CMIT

**** * ******* ****** #*** https://www.linkedin.com/in/chaitra-adari/

+1-503-***-**** *******.*****@***.*********.***

SUMMARY

• Masters graduate in Construction management, possess 6-years of professional experience with strong practical and technical skills within construction engineering & project management.

• Results orientated and hands on experience in all phases of the industry, proficient in estimation of commercial buildings

& heavy engineering, subcontract management, costing, pre-construction, project controls, risk management, documentation, and procurement.

EDUCATION

Master of Science in Civil Engineering May 2018

California State University, Fullerton, California Bachelor of Technology in Civil Engineering May 2011 Vellore Institute of Technology University, Vellore, India SOFTWARE SKILLS

●Procore ● BIM ● Bluebeam ● Primavera ● Microsoft office ● On-screen take off and RS means

● Revit ● Sage ● AutoCAD ● Naviswork ●Microsoft Project ● WinEst PROFESSIONAL EXPERIENCE

Project Engineer Intern – Hal Hays Construction, LA & Orange County, CA. Aug’ 2017-Dec’ 2017

• Prepared job books, Site specific safety plans, mobilization and demobilization plans.

• Transmitted Submittals, RFI’s, Daily Reports, PO’s, Subcontract’s & Change Order’s.

• Performed quantity takeoff using On-Screen Takeoff and assist the estimating team with accurate quantities.

• Assisted project manager in preparing all project controls sheets, budget sheets and WIP reports.

• Prepared three weeks look ahead schedule and addressing the critical issues in the co-ordination meetings. Project Engineer – CGR, Container terminal at JNPT, India July 2015- July 2016

• Identified critical activities, monitored and controlled project schedule and prepared project control report.

• Prepared all the contractual documents- RFI’s, Change orders & Extension of Time, Bonds & Insurance.

• Contributed in pre-construction meetings and technical bid of the 2nd phase for $1.2 billion project. Cost Manager – Gammon India Ltd, Sea Water intake & outfall, India Feb 2012- June 2015

• Developed cost reports, invoices, project valuation sheet and project payment sheet for monthly payments.

• Studied and prepared project budgets for financial estimates- budgeting, cost control, profitability, cash flow.

• Successfully claimed EOT for 600 days & $50 Million change orders guidelines due to deviations in contract.

• Implemented Lean, EV project management techniques, detailed Risk analysis and assessment. Field Engineer – ITD Cem, Angre Port, India Aug’ 2011 – Feb’2012

• Worked with superintendent in managing site operations and ongoing construction activities for executing marine piles.

• Prepared and implemented Accident Prevention Plans (APP), Quality Work Plans (QWP) and Safe Work Plans (SWP) ACADEMIC PROJECTS

• Cost control, scheduling, and planning for CSUF arboretum project. (Gantt charts, risk assessment & trade-off analysis)

• Selection of sub-contractor using artificial intelligence (analyzing different parameters in selecting a sub-contractor)

• Case study of real time projects – pre-construction phase, bid package, project management principles & quality control. ACCOMPLISHMENTS/CO-CIRCULAR ACTIVITIES

• Completed CPR/AED from American Health Care Academy, Certificate No: A1168026, Renewal Date: 08/07/2019.

• Was active member of Toastmasters club, Mumbai, India.