IVAN CANJAR
**** ****** **** ********, *********, ON L1X 1A4
416-***-**** **********@*****.***
Profile
Plant Manager: talented, highly articulate leader with over 20 years operations experience focused on safety and process improvement
Strong strategic planner, problem solver and persuasive leader: recognized for consistent success in developing systems, processes and procedures to streamline operations, increase revenues and enhance profit performance
Cross-functionally driven individual: proven track record in production, distribution, warehousing, engineering and customer service management
Proven record of delivering sustainable business results (cost, service, quality, safety): through people development and strategic thinking across multiple business units
A servant leader: values diverse opinions, cultivates a culture of trust and develops other leaders in both union and non-union environments
Success: leading turnaround, both cultural and performance, with large operational teams
Professional Work Experience
Plant Manager, Linde Canada, Brampton ON
Sept.2012- Present
Re-packager and distributor of packaged gas – industrial, food and medical gases
Areas of Responsibility
Plant Operations: Budget $3.5 Million, 4 direct reports, 33 unionized indirect reports, packaging of 24000 cylinders per month/240 SKU’s (2nd largest Canadian plant). Quality Control, Plant Maintenance, Engineering Liaison
Distribution: Budget $1 Million, 2 direct reports, 14 unionized drivers, 35000 cylinders per month. Directly serving customers in the GTA and branches across Ontario, bulk deliveries
Key Accomplishments
Maintained a zero loss time safety KPI while improving plant’s safety KPI from 16 years without a lost time accident to 20 years – longest running in Linde North America. Certified Member of the Joint Health and Safety Committee
Improved inventory accuracy from 58% in 2012 to 87% in 2015. Continued improvement in 2016 – 89%
Reduced unit cost by 8% through operational efficiencies and overtime reduction
Successfully completed Health Canada Audit in 2015
Implemented driver safety initiative, “Drive Cam” in the route trucks
Plant Supervisor, Linde Canada, Whitby ON
Jun. 2011 – Sept. 2012
Promoted to Plant Manager after only one year as a supervisor
Key Accomplishments
Established a team focus for progressive improvement of plant’s on time order fill rate KPI, resulting in continuous improvement from 82% to 97% within 6 months
Transitioned a similar process to shipping on time KPI – reduced shipping cost by $85,000
Collaborated with team at Whitby plant to achieve or exceed all KPI’s for 2011
Owner/Operator, Inscription Printing & Graphics
May 2005 – Jun. 2011
Textile and Large Format Printing, Graphic Design- Products included custom printed fabrics, banners, signs and posters on digital printers utilizing RIP software on PC system (some experience on MAC)
Key Accomplishments
Developed marketing strategy, built client relations, sales and customer service
Managed all aspects of print production, equipment purchasing, sourcing raw materials, production – printing, laminating, cutting, assembly, and shipping and receiving
Ensured accuracy for all colour matching and printer profiling using X-Rite/Gretag Macbeth spectrometers and software
Generated and modified layouts using Adobe, Corel and various graphic software
Self-taught
Manager, Rockwell Automation
Sept. 2007 – Dec. 2008
Managed employees in the production of electrical distribution equipment
Key Accomplishments
Liaised with engineers, planners, human recourses, payroll, upper management and other manufacturing departments
Directed a 6S initiative workstation standardization
Utilized the Lean principles, 5S and continuous improvement to reduce waste and improve efficiencies
Trained, supervised and coached employees in plant policies and procedures in weekly meetings
Production Manager, Kraft Canada (Peek Freans Plant)
Nov. 2002 – May 2005
Manage the Mixing and Baking departments in a 24/7 non-unionized production
environment with 9 leadhands, 75 direct employees, 6 ovens, 9 mixers
in the production of cream filled cookies, biscuits and crackers
Key Accomplishments
Created a system to collect the data of temperature measurements over time to verify the completion of weekly fumigation of the flour silos were within specifications.
Worked closely with Engineering as the stakeholder of the mixing department, reduced the department headcount by two with the realization of an automatic flour delivery system and automated oil delivery system
Successfully converted the mixing department from a trans- fat oil to a non- trans- fat oil system working with product development, engineering and plant maintenance
Introduced an automated process for the daily labour hourly report and weekly labour schedules so they could be delegated to the lead hands
Maintained a zero lost time accident rate in both departments and developed the confined space training manual for the plant
Managed an operating budget of $5.7 Million. Managed raw materials, production flow and employee schedules
Production Manager, Alderbrook Industries
Aug. 2000- May 2002
Manufacturer of seasonal decorations
Key Accomplishments
Spearheaded workflow process redesign by leading the increase of the production capacity for an artificial tree making machine by 30%
Completed time studies and material flow analysis to determine the most economical cycle time target. Contracted a PLC programmer. Machine reliability improved by 10% as a result of the changes
Modified the SOPs for the new process and re-trained the operators
Production Supervisor, Coca-Cola Enterprises
Feb. 1997 – Aug. 2000
Bottler of liquid refreshments
Key Accomplishments
Supervised 30 employees in a union environment and managed employee discipline as per collective agreement and grievance procedure
Oversaw water treatment, syrup batching, production and packaging quality
Lead talent development through hiring, orientation, training and dismissal of seasonal employees
Production Supervisor / Manufacturing Engineer / Designer Schneider Electric, Toronto ON
Feb. 1990 – Mar. 1997
After only 2 years of design experience, promoted from detail draftsman
to mechanical designer and later to team leader
Key Accomplishments
Provided leadership to a multi departmental team for a project that rationalized parts for circuit breakers through re-design. Resulting in cost savings
Orchestrated process improvements through trouble-shooting for a new semi-automatic production line. Created ISO9002 documentation and developed a KANBAN inventory system for an existing family of products
Supervised 150 employees in a unionized environment. Participated in resolution of grievances.
In a classroom setting, facilitated and instructed employees in the importance their role played in the company’s success (TQM)
Technical Proficiency
SAP, ADP Payroll, MS Office Suite (Word, Excel, PowerPoint & Visio), MS Projects,
Personal Designer CAD software, Corel Draw, Adobe Photoshop and Illustrator & Kronos (time management)
Education
Mechanical Engineering Technologist (3 year diploma)
Sault College Sault Ste. Marie, ON
Professional Development
Linde: Certified member of the Joint Health and Safety committee, “MAKE” training, Front-Line Leadership Training – Level 1 and 2
Self-Taught: Large Format Textile Printing
Biscuit Technical University (BTU): Mixing and Baking Modules for Cookies and Crackers
Kraft Employee Development: Leading People at Kraft, Safety Training (confined space, forklift and working at heights training).
American Institute of Baking Seminar (AIB): Mixing and Baking Cookies and Crackers,
Coca-Cola Bottling: Production Management Development Program
Schneider Electric: Team Leadership, Classroom Instruction Training, Presentation and Facilitation Skills, Occupational Health and Safety and the Law