Post Job Free

Resume

Sign in

Engineering Project

Location:
Tehran, Tehran Province, Iran
Posted:
November 20, 2017

Contact this candidate

Resume:

*

Nader Rashidi’s CV

Address: No *, Second Floors, Farmehr Building, Farzad Alley, Zabeti St., Heravi Sq, Tehran, Iran

Mobile: +98-912*******

Email:ac3eo7@r.postjobfree.com

Brief Personal Details: Education: B.Sc in Chemical Engineering Date & Place of Birth: September 15 1985-Tehran

Marital Status: Married

Military Service Status: Exempt

Spoken Language: Farsi (Persian), English

Qualification: B.Sc. in Chemical Engineering-Azad

University Tehran South Branch (2003-2007)

Technical Certificates: - IELTS from BRITISH Consulate (Fluent)

- Process Simulation Software (HYSYS)

-ASPEN PLUS Software

-Welding Course from TWI

- Internal Audit of Integrated Management System

(IMS) From TUV NORD (Iran-Germany)

- Basics, Structure & Documentation of

Integrated Management Systems (IMS) From

TUV NORD

-Exchanger Design

- Opercom Methodology Course

- PMBOK Course

- Valve Inspection

- BOSIET

- HUET

Professional Experience:

Experiences in Oil & Gas industry covering full cycles of Project (FEED, Basic Engineering, Detailed Engineering, Construction, Pre-commissioning & Commissioning, Start-up and Operation). High experience in preparation, implementation and execution, with multi-discipline, of Pre- commissioning & Commissioning and Start-up activities, in accordance with COMPANY and International Specifications, with key experience in ICAPS, Operational Test Procedures (OTP) writing, Vendor Interface, and equipment and manpower planning.

Providing “Best Practice” in Pre-commissioning & Commissioning with HSE compliance. Good and effective team working with strong leadership ability. Regularly performed / stand-in as key liaison between Engineering, Construction, Commissioning, Start-Up Team and Field Operations to ensure smooth project completion and handover. Education:

2

Core Strengths:

- Knowledge of Natural Gas Processing (Phase Behavior

& Flash Calculation, Gas Hydrate, Natural Gas

Treatment, Condensate Stabilization, Gas compression, Acid Gas treating

-Knowledge of Utility Units (Compressed Air, Nitrogen Generation, Steam Generation, Cooling Water,

Desalination.

- Familiar with Project Documents i.e. Basic/Detailed Engineering Documents

-Familiar & Issuing All Commissioning Documents i.e. Leak Test, OTP, Chemical Loading & Cleaning, General Commissioning Docs, Sub-system Generation...

-Familiar with TOTAL Opercom Methodology & ICAPS

Software

-Familiar with EPC contracts in Oil & Gas Industry 2016 Up To Now POEC

- South Pars Gas field development Phase 17&18

(Offshore Platforms)

Project Involve:

-Pre-Commissioning & Commissioning & Start-up of

Offshore Platforms 17B &18B

Position:

Deputy of Hook up & Commissioning Manager

Main Responsibilities:

-Ensure that the pre-commissioning and

commissioning activities are planned well in advance and are fully integrated with the project construction schedule.

-Prepare plans for transition of the project from

project management team to the operations

organization at appropriate stage of the project.

-Prepare commissioning plan at sub-system level

-Manage and ensure that offshore commissioning is

performed in accordance with all specified

requirements

-Establishing, instruction and performance of the

commissioning group.

-Prepare schedules for the test and commissioning

activities of total scope of supply.

Job Experiences:

3

-Ensure that commissioning activities are planned, arranged and executed in such a way that the

integrity of safety and the environment is maintained throughout the process.

2014 Up To 2016 Tesco Oil & Gas Company (Part Time)

- South Pars Gas field development Phase 22&24

Project Involve:

-Pre-Commissioning & Commissioning & Start-up of

Phase 22, 24

Position:

Commissioning Coordinator

Main Responsibilities:

-Review and checking Pre-Commissioning

procedures

-To assist construction departments by defining of Priority Systems according with overall construction and pre- Commissioning & commissioning planning

And schedule, Participate in constructability

analyses in order to meet project schedule.

-Preparation of pre-commissioning, commissioning

Execution plan

-Witness Pre commissioning activities

- Follow-up of technical modifications,

Documents Update and punch closure as

required

2012 Up To 2014 Tesco Oil & Gas Company

- South Pars Gas field development Phase 15&16

Project Involve:

-Pre-Commissioning & Commissioning & Start-up of

Phase 15, 16

Position:

-Engineering Manager

Main Responsibilities:

- Establish the Overall Execution Plan,

Organization And Schedule for the Engineering

Activities in Accordance with the Project

Policies

- Supervise the Preparation of the Project Procedures to Coordinate the Engineering Activities of the

Sub-contractor

- Supervise the Engineering Sub-contractor Activities 4

- Review the Engineering Progress Status and Report to The Project Control Manager

- Responsible for the Engineering Standards and

Specifications and for Resolution of Technical

Alternatives, deviations and concessions with

Contractor

- Coordinating Activities of VENDORS and any

Subcontractor Participating in the Work

- Convene PSSER (Pre-start up Safety &

Environmental Review) Meeting with Subcontractor

- Coordinating Procurement Section for Purchasing

Commissioning Chemical & Lubricant & Spare-part

2011 Up To 2012 Tesco Oil & Gas Company

-South Pars Gas field development Offshore 16 & Phase 13 & 22, 24

Project Involve:

-Pre-Commissioning & Commissioning & Start-up of

Phase13& 22, 24 and Offshore Phase16

Position:

-Process Engineer Head

Main Responsibilities:

-Issue Pre-commissioning & Commissioning Procedures

- Defining & Issuing Pre-commissioning & Commissioning Priorities

-Preparing Systems Sub-system Identification &

Mark-up

-Preparing & Issuing Early Start-up Scenario for Gas in

-Blind List Preparation

-Supporting ICAPS Software for Data Base Creation

-Cooperation with Engineering Department to

Update Detail Design Documents

- Confirming Piping Loops for Blowing & Flushing Stages

- Coordination with Procurement Section

- Attendance in FAT (factory acceptance test)

-PFD & P&ID review

-Estimation & Calculation of Chemical Consumption

-Estimation the Amount of Required Spare Parts

2008 Up to 2011 SEPANIR Oil & Gas Company

-South Pars Gas field development Phases 15&16

Project Involve:

Engineering

Position:

-Process Engineer

5

Main Responsibilities:

- Reviewed and Developed Process Documents

-Attendance in Technical Meeting

-Preparation of Reports

-Scope of Work Preparation

July 2007 Up to Feb 2008 Nargan Engineering (Part Time)

-South Pars Gas field development Phases 15&16

Project Involve:

Engineering

Position:

-Process Engineer

Main Responsibilities:

-Engineering Design Service (Feed Package)

-Procurement services

Computer Literacy: Technical:

- Aspen Pluse, Hysys, & Familiar with ProII & HTFS General:

- Microsoft Office (Word, Excel, PowerPoint)

Interest: Studying, Research, Mountain climbing, travelling Institutional Experience: A Member of IACHE (Iranian Association Chemical Eng.)