Professional Experience

Construction Innovations Consulting

Project Manager /Superintendent, Los Angeles, CA 2016 – Current

2016 Stagg Village LLC/ Winnetka, CA

Completed 6 custom homes over 4200 sqft ea

2017 Firmament Village LLC / Van Nuys CA

Completed 9 custom homes over 3200 sqft ea

Conejo Constructors Corporation

Project Manager / Superintendent, Westlake Village, CA 11/2014-Current

2014 Darling Development Group/ Sherman Oaks, CA

Completed 2 custom homes over 7600 sqft

Consult services on 124 condo development in Murrieta, CA and multi home development in Simi Valley, CA

J&J WORLDWIDE SERVICES

Project Manager/Quality Control System Manager, Honolulu, HI 03/2012-05/2013

2012 Department of Defense/Tripler Army Medical Center/Honolulu, HI

Completed 3 out of 4 phases on 8BFlouroscopy (demoed patient rooms and TI into new office space)

Completed 3rd phase of 2GPathology (demoed old lab, TI, and modernize new laboratory space)

PRIMATECH CONSTRUCTION

Project Manager, Honolulu, HI 5/2010-08/2011

2011 Pahoa High School Gym/Pahoa, HI

30,000 sq. ft. gymnasium on a ten acre site, 10 million dollar project

TRITON MARINE CONSTRUCTION CORP.

Project Superintendent, Honolulu, HI 11/2008-5/2010

2008 ADA and Bus turn out along King St/Honolulu HI

Modernization, 2 million dollar project

2008 HI Viaduct repair adjacent to Home Depot/Pearl City, HI

Replaced concrete for approximately 24,000 linear feet on 4 lanes of highway, 3.8 million dollar project

2009-2010 Kaneohe Marine Base/Kaneohe, HI

Storage facility, retrofit and modernization, 1 million dollar project

2010 H1 Viaduct repair adjacent to Aloha Stadium/Honolulu, HI

Replaced concrete for approximately 30,000 linear feet on 4 lanes of highway, 5.8 million dollar project

HONOLULU BUILDERS

Project Superintendent, Honolulu, HI 7/2008-11/2008

2008 Simply Organized/Kapolei, HI

TI, $800,000 project

DARLING PACIFIC BUILDERS, CW DRIVER, MOOREFIELD CONSTRUCTION, WOODCLIFF CORPORATION, GERSTENBERGER CORPORATION, GONZALES CONSTRUCTION CORP.

Senior Project Superintendent/Project Superintendent 1987-2008

2006-2008 Will Roger State Beach/Pacific Palisades, CA

5 miles of parking lots along PCH, modernization and rebuild of 3 lifeguard headquarters, 17 million dollar project

2006-2008 Department of Transportation “CALTRANS”

City of Lebec – Off/On ramp modernization, 9 million dollar project

Lebec Cal Trans Maintenance Station, the demolition of existing buildings on 5 acre site

Reconstructed 2 buildings, 2 mechanic buildings w/12 bays combined, 110,000 sq. ft., 1 utility building, 8,000 sq. ft., 7.8 million dollar project

2004-2006 East LA Civic Center/Los Angeles, CA

Modernization and addition, 9 million dollar project

2002 (18 month project) East LA Mayor’s Office/Los Angeles, CA

Modernization and addition, 6.3 million dollar project

2000 (21 month project) CALTRANS Bridge Expansion Interstate 5/126

Retrofit and modernization, 7 million dollar project

1999 (7 month project) Telemundo TV Station/Burbank, CA

TI, 2.3 million dollar project

1998 (7 month project) Universal Studios City Walk/Burbank, CA

Earthquake retrofit and modernization, 2.5 million dollar project

1997 (8 month project)William S. Hart High School improvement, LAUSD/Santa Clarita, CA

35,000 sq. ft. gymnasium building, 29,000 sq. ft. social studies building, 7 million dollar project

1995-1997 (22 month project)CALTRANS Highway 126/CA

31 miles of road expansion and modernization, 2 lanes to 4 lanes, 11 million dollar project

1994 (16 month project) City of Commerce Library & City Hall addition/City of Commerce, CA Modernization and addition, 8 million dollar project

1992-1994 (24 month project)Wayne Ruble Middle School/Fontana, CA

Ground up construction, 28 acre site, 11 buildings, 1 gymnasium, 9 million dollar project

1990 – 1992 (20 month project) Marshall Elementary/ Hollywood, CA

Ground up construction, 4 buildings, 1 cafeteria, 5 million dollar project

1988-1990 Department of Transportation “CALTRANS”/Los Angeles, CA

1989- 1990 (24 month project) Oversaw the Santa Clarita Cal Trans Maintenance Station, ground up, 10 acre site, at the 5 & 126 junction, 1 equipment building w/ 7 mechanics bays, 30,000 sq. ft., 2 office buildings, 53,000 combined sq. ft., 13 million dollar project

1988 (12 month project)Chileo Cal Trans Maintenance Station, 1 equipment building w/ 7 bays, 25,000 sq. ft., 1 office building, 3,200 sq. ft., 7 million dollar project

1987-1988 (14 month fast pace project)Edwards Cinema 14 Plex Theater/ Ontario, CA

138,000 sq. ft., 3,000 stadium seating, including 2 story post tension parking structure 1,000 car capacity, 33 million dollar project, extensive site work

DARLING PACIFIC BUILDERS

Supervisor, Aguora Hills, CA 1984-1987

Managed entire project site activity and labor crew in daily operations

Served as general coordinator for construction site planning and development

Handled all site administrative affairs including: Supply contracts, inspections, change orders, repairs and materials

Negotiated all site contracts with contractors, i.e. contract prices, supplies, time frames

Responsible for all personnel and labor crew matters such as: crew functions, time sheets, expense accounts, safety compliance, and schedule compliance

Education

UNIVERSITY OF CALIFORNIA SANTA BARBARA 1981, 1982, 1983

B.S.; Economics, Santa Barbara, CA

SANTA BARBARA COMMUNITY COLLEGE 1979, 1980

Business; Political Science, Santa Barbara, CA

Skills and Certificates

ASHE, Health Care Construction Certificate, 2/26/13

Bilingual (English, Spanish, Portuguese)

PJ, Primavera P3/P6, MS Office 2007 (MS Word, PowerPoint, Excel, Outlook)

BLS/CPR/First Aide certified 10/2012-10/2014

Lifeguard Certified City and County of Honolulu

OSHA 30 hour construction safety 04/05/2012

ACI Concrete certified

Aerial Platform Operator Safety certified

Construction Quality Management for Contractors-#784, 09/18-20/2012

J&J Training

Stress Management 04/05/2012

Teambuilding for All Employees 04/05/2012

Working Safely with Solvents 04/06/2012

Safe Chemical Handling 04/25/2012

Spill Prevention, Control, and Countermeasure Plan (SPCC Plan) 04/25/2012

Lead Safety- General Industry 07/20/2012

Asbestos Awareness 07/20/2012

Preventing Workplace Violence – What Employees Need to Know 10/10/2012

Time Management Skills for Employees 10/10/2012



Contact this candidate