Post Job Free
Sign in

Project Manager Management

Location:
Doha, Qatar
Posted:
June 10, 2013

Contact this candidate

Resume:

SACHIN NADKARNI

PMP, LEED GA.

Villa **, Ezdan Village 4, Al Wakra

Doha-Qatar

Phone-009**-********.

Nationality - Indian

Born-17th August 1972, 40 years old.

*****-************@*****.***

Project Director - Electromechanical (MEP)

Qualifications:

a) LEED Green Associate Dec 2012

# 10812329 Green Building

Certification Institute. (GBCI)

b) PMP - Project Management Professional.

Certified by

# 1401713 Project Management Institute-(PMI) PMI - USA

April-2010.

c) Diploma in Marketing Management Dec-1998

University of Mumbai - First Class

d) Bachelor of Engineering - Electrical Engineering - July-

1995

University of Pune, India - First Class

e) Diploma in Electrical Engineering - May-1992

Board of Technical Education, Mumbai - First Class

f) Urban Planning certified "A" Grade Engineer. Doha, Qatar.

Personal Qualities & Strengths:

- Good Interpersonal & Communication skills

- Adaptability to new ideas and environment.

- Organized, Analytical with peoples skills

- Committed and result oriented.

Skills

. Project Management: Leading a team of Project Mangers and Engineers to

accomplish a given project from all stages of the project starting

from design, planning, execution

monitoring and control until project closeout

. Value Engineering: Carrying out Value engineering Workshops with the

design & execution Teams to achieve the specified results with better

cost effective solutions.

. Decision making: Involved in strategic decision making in co-

ordination with the Operation managers and General Manager.

. Personnel Management: To cultivate a competitive and healthy work

environment at the work place to achieve harmony amongst all

disciplines which would further act as a catalyst for achieving better

quality & quantity of work output.

. Public relations: To co-ordinate with Architects, Consultants & Client

to achieve smooth flow of work at site and to ensure timely Project

completion. To be a link between the site management and the back-

office management to ensure effective communication between all

stakeholders.

. Cost & Time Management: To maintain and monitor the budget and actual

costs being incurred in line with the project schedule during all

project phases and further assist management to track the overall

financial growth of the project.

. Quality Management: To ensure that all the works are being carried out

to the best quality standards.

. Self Motivated & continuous Knowledge upgradation: Self motivated and

keen to be in line with the latest trends and skills in the

construction industry.

Professional Experience

1) M/s Takyeef Electromechanical WLL. July 2008 to till date.

Qatar

Designation: Projects Director.

Job Profile:

- Planning, controlling & execution of the all Electro-mechanical

works by leading a team of Project Managers, Engineers,

Supervisors & work force.

- Strategic Planning & Decision Making.

- Resources planning & Allocation.

- Overall Project Monitoring.

- Value Engineering

- Cost Control, Budgeting & monitoring.

- Quality Control/ Quality Assurance check of all ongoing works

at

site.

- Co-ordination with the Procurement department to facilitate material

submittals, placement of orders, Delivery scheduling etc.

- Review co-ordination matters with logistics department with

reference to Manpower transport/ material transport etc.

- Co-ordination with Client, Architects & Consultants to facilitate

smooth flow of work at site.

- Motivating the team members to ensure to have harmony and unison

amongst the different disciplines at site.

Projects Handled-

a) New Research Building - Qatar University.

MEP works to the tune of 75 Million Qrs.

Client - M/s Qatar University.

Consultant - M/s Arab Architects

b) Library Building - Qatar University.

MEP works to the tune of 75 Million Qrs.

Client - M/s Qatar University.

Consultant - M/s Arab Architects

c) Warehouse Project at Qatar Logistics Village.

MEP works to the tune of 25 Million Qrs.

Client - Ms/ Gulf Warehousing company.

Consultant - M/s Gulf Engineering Consultants.

d) GMP lab at Rumaillah hospital.

Client - M/s Hamad Medical Corporation.

Consultants - M/s Qatari Engineers.

2) M/s Voltas Ltd. UAE May

2006 - June 2008

Designation: Project Manager - Electrical.

Job involved:

- Leading a team of engineers and Supervisors to expedite the fast track

project.

- Co-ordination with the Project Manager, Architects and consultants for

timely job completion.

- Cost Control & Monitoring

- Material and resource Management.

- Quality Management.

- Co-ordination at site with other services to clear all MEP related

issues and bottle necks that delay the projects.

- 1500KVA Substation Installation with new MCC's, SMDB's, DB's etc and

installation, testing and commissioning of the same.

- Installation, testing and commissioning of 2 nos X 3200A Bus duct

system.

- LT cabling related to the entire distribution network.

- Internal electrification of all the 400 deluxe room and suites.

- LV systems for MATV, Tel, Data, Room Management system, BMS, Fire

alarm, access control systems, CCTV etc.

- UPS systems

- Cable Tray and trunking network for the entire hotel.

- Relocation of the existing DG set.

- Lightning protection system.

- Earthing systems.

- Cable Tray and trunking installations.

- Preparation of as-built drawings through the draughtsman's.

a) Refurbishment project for Hotel Intercontinental situated at

Abu Dhabi. - A 400 room hotel project. - Dhs 85M.

Project Managers - M/s Turner.

Consultants - Ian Banham Associates.

b) Etihad Towers - Abu Dhabi, UAE - Dhs 120M

This is a 120 million AED project comprising 5 nos. of towers - 70

floors with 3 Podiums and 4 car park basements.

3) M/s Serum Institute of India Ltd Sept 2000 - April

2006

Largest manufacturers of Vaccines.

Designation - Manager - Electrical Projects.

Job Profile:

- Co-ordination with Architects and consultants and ensure effective and

timely project execution.

- Material and manpower planning

- Complete designing and electrification of the new manufacturing blocks

in the factory involving all the electrical related works.

- Exposure to the CGMP & WHO requirements related to electrification of

Clean rooms

- Electrification of the Clean rooms. (Where vaccines are manufactured)

as per CGMP and WHO standards.

- Use of CGMP power distribution accessories for clean rooms.

- Custom designing of Clean room Lighting fixtures.

- Audio- Video communication system required in clean rooms

- Access control systems.

- Co-ordination with consultants/ Process experts and other agencies for

timely completion of the project.

- Executed almost 15 expansion projects to the tune of Rs 4.5 crores.

4) M/s Sterling & Wilson Electricals Pvt. Ltd. Aug 1995 - Aug 2000

India

Leading Electrical Contractors - M/s Shapoorji Pallonji Group

Designation - Senior Project Engineer & Co-ordinator.

Job Profile:

- Optimizing use of resources and leading a team of junior Engineers &

supervisors.

- Co-ordination between Client/ Architects/ consultants and management

to ensure timely, cost effective measures for completion of projects.

- Estimation of Job costs, material procurement, Labour planning,

Tendering, Project Scheduling and follow-up.

The works included:

- HT 11/22 KV substation erection, testing & commissioning.

- Transformer installation, testing & commissioning.

- HT Panel OCB/VCB/SF6 panel installation, testing & commissioning.

- HT Cabling.

- LT panel installation, testing & commissioning.

- Cable tray works.

- Trunking.

- LT Cabling.

- Wiring for lighting & Power circuits.

- Earthing stations

- Lightning Protection.

- Telephone Network.

- Data Network.

- Fire detection and protection systems.

- Lift cabling works.

- HVAC cabling works.

- Landscape Lighting

- Audio system cabling.

- Light fixture installation.

- Liasioning with state electricity board and government authorities.

- Preparation of all as-built drawings of the entire power distribution

schemes for maintenance purposes

- To complete the testing, commissioning and handover procedures of the

entire system to the client upto their satisfaction.

Projects Executed:

a) Complete electrification of NCPA residential complex, Mumbai.

Installation worth Rs 20M.

b) Complete electrification of M/s Royal Palms Golf club and country

club at Goregoan, Mumbai Installation worth Rs 5M.

c) Complete electrification the corporate office of M/s Onward Novell (I)

Ltd, Andheri, Mumbai Installation worth Rs 10M.

d) Complete electrification for the Majestic Bungalow of Dr. Cyrus

Poonawalla - Chairman - M/s Serum Institute of India Ltd. At Pune,

Installation worth Rs 5M.

e) Complete electrification of M/s Blue Hills residential project at Pune

Installation worth Rs 4.5M.

f) Complete electrification of M/s Geometric Software Solutions Ltd, at

Hingewadi Infotech Park, Pune. Installations worth Rs 10.2M.

g) Complete electrification of M/s Sai Hira Commercial Complex, Pune.

Installations worth Rs 2.5M.

h) Complete electrification of M/s Westside Shopping Mall, Pune

Installations worth Rs 5M.

i) Complete electrification of M/s Shoppers Stop, Pune

A leading shopping Mall chain. Installations worth Rs 5M.

j) Complete electrification of M/s Reverisia residential complex at Pune

Installation worth Rs 6.5M.

Personal Information:

Maritial Status : Married.

Children : One daughter - 11 yrs.

Address in India: A-611/612, Akashdeep Apartments.

Ganesh Nagar, Dhayari,

Pune, Maharashtra, India - 411041

Passport No : H1113704



Contact this candidate