Ahmad Mokhtari Laleh
Senior Electrical Engineer & Freelance Technical Trainer
Nationality: Iranian
Marital Status: Married
Language: English (IELTS#6), Azari, Persian
Birth Day: 9th Feb, 1977
Email:**************@*****.***
Tel: +98-912******* – 214-***-****
LinkedIn Profile: http://www.linkedin.com/pub/ahmad-mokhtari-laleh/59/b94/60
1- Education / Qualification:
1. Master of Power Engineering (M.Sc)
Tehran Polytechnic, Electrical Engineering Department, 2004
1. Bachelor of Power Engineering (B.S)
Tabriz University, Electrical Engineering Department, 2000
2- Relevant work experience:
1. Field engineering experience in design, construction and commissioning at a petrochemical plant (3 years).
2. Office experience in design and review of electrical documents in Oil, Gas & petrochemical, Steel Making,
Gas Turbine Power Plant and Foundry Industrial (5 years).
1. Research experience in Power Quality Indices in 63/20kV Substations in Tehran, Iran (2 years).
2. High Voltage Lab experience in Tabriz University (2 year).
3. Electrical Training experience in training centers and industrial sites (during 5 years. 1229 training hours).
3- Skills:
Project:
1. Experience of EPC projects and working as part of a multi-discipline team.
2. Experience of EPC proposal.
3. Relevant site-based and office design, construction and commissioning experience.
4. Respond to contractor queries and attend meetings.
5. Liaise with other disciplines and client.
Electrical:
1. Carry out calculations for system studies and to support equipment specifications:
fault levels, voltage profile, load balancing studies, motor starting, harmonic analysis, cable sizing and power factor correction for power plant and industrial projects using ETAP.
1. Protection grading studies for industrial networks and familiar with Sepam, GE, Thytronic, Siemens relays.
2. Testing the functions of protection relay and applying setting. (DIGSI, SFT, ThyLink)
3. Cable Sizing by e-DPP software.
4. Preparation of SLDs and Control & Schematic Diagrams for MV/LV Switchgears.
5. Preparation of Specification and Enquiry for MV/LV Switchgears, Power Transformer, Neutral Grounding Resistor, MV/LV Capacitor Bank, MV/LV Motors, MV/LV Cables…
6. Familiar with Electrical standards.
7. Familiar with Area classification and Heat tracing.
Software:
1. Microsoft Office (word, excel, power point), Outlook, AutoCAD.
2. ETAP, e-DPP (cable sizing), DIGSI (Siemens), SFT(Schneider), ThyLink.
4- Employment History:
1. Sazeh Consultants (Engineering & Construction) www.sazeh.com (Full time Dec 2007 up to now)
Position:
Electrical Engineer at “Calculation and Support” team (Full time June 2011 up to now)
Projects:
Iran LNG, Gas Refinery South Pars Phase 12, Shazand Refinery.
Duties:
1. Power system protection studies and relay coordination.
2. Power system studies (load flow, short circuit, motor starting, transient stability
3. Cable sizing.
4. AC&DC UPS sizing.
5. Supporting site activities and solving electrical problems in projects.
6. Preparation of EPC proposal (Refinery, Petrochemical, Offshore
7. Attending meetings with contractors.
8. Project site visits.
1. On-job training.
Position:
Electrical Field Engineer (Full time Dec 2007 up to June 2011)
Project:
Arvand Petrochemical Co. (PVC production) By Uhde (Germany) & Sazeh (Iran).
33kV GIS Substation (Siemens), 6 & 0.4kV Switchgears / Harmonic Filter System (Reinhausen) in 33kV / 33&0.4kV Bus Duct (Vilfer and Zucchini) / LV& MV Motors (Siemens and Flender Loher) / Variable Speed Drives (Flender Loher) / 24 Sets Rectifiers (AREVA)
Duties:
1. Review of supplier documentation and any document issued by other engineering groups.
2. Giving solution to any conflict in Technical documents (drawings, schedules, lists, detail installation, MTO, packing list, specifications…).
3. Liaise with other groups: civil, structure, mechanical, piping and instrument.
4. Modification and design of cable routs, ladders, lighting fixtures, earthing, protection settings, control circuit of switchgears…
5. Carry out calculations for power system studies.
6. Answer to any TQs (Technical Query) issued by contractors.
7. Attending construction, pre-commissioning and commissioning meetings with Uhde and contractors.
1. BIDEC (Bita Innovative Design Engineering Company) www.bidec.org
Position:
Electrical Designer (Full time Jan 2007 up to Dec2007)
Projects:
Steel Making Plant (Hormozgan), Direct Induction Plants (Khorasan, Ghayenat, Kashan)
Duties:
1. Design of 6.6kV Switchgears (steel making, oxygen, water intake, jetty plants, direct induction plant).
2. Design of 0.4kV Switchgears (Power Center, MCC, Lighting…).
3. Design of lighting systems using Calculux software.
4. Power system analytical studies including load flow, short circuit calculation by Etap 5.0.3.
5. Motor starting study by Etap 5.0.3.
6. Cable sizing.
7. Study and design of Power Factor Correction system in Steel Making Plant.
8. Prepare of Specification and Enquiry for 6.6kV Switchgear, Power Center, Distribution, Power Transformers, Neutral Grounding Resistor, MV/LV Capacitor Bank, LV/MV Motors.
1. Compulsory Military Service
Position:
Electrical Soldier Engineer (Full time Apr 2005 to Dec 2006)
Project:
Small Gas Turbine Power Plant,
Duties:
1. Study of connection of power plant to existing substation.
2. Design review of 20kV Switchgear and connecting it to 63/20kV substation.
3. Design of all LV Switchgears (Forwarding pump station, lighting, auxiliary…).
4. Power system analytical studies including load flow & short circuit.
5. Review and approval of power plant grounding system according to IEEE Std 80-2000.
6. Review of all basic design and specification documents for all electrical equipments.
7. Sizing of transformers(4 units,11/20kV and 2 units, 20/.4kV), diesel generator(one set,0.4kV).
8. Review and approval of lightning protection system according to NFC17-102.
9. Study of generator electrical characteristics.
1. Part-time Works:
Title:
Relay Coordination Studies
Project:
Tabriz Oil Refining Co.- TZORC GPP Project-2012
Duties:
1. Modeling of all parts of plant (MV motors, power plant by ETAP.
2. Relay coordination studies for a 6.3kV switchgear (Thytronic relays) by ETAP.
Title:
Engineering of Adding Transducers to MV Switchgears for Load Shedding
Project:
Arvand Petrochemical-Offsite Project-2011
Duties:
1. Review of 33kV & 6kV switchgears control circuits.
2. Modification of control circuits and preparation of AutoCAD files.
Title:
Relay Coordination Studies
Project:
Arvand Petrochemical-Offsite Project-2011 (Norahan Engineering & Contracting Co.)
Duties:
1. Relay coordination studies for 33kV & 0.4kV switchgears (Siemens relay) by ETAP.
2. Applying setting to Siemens protection relays.
3. Supervisor Relay Test.
5- Training History:
Total:
Training hours: 1229, Training Courses: 53 (from 2007 up to now)
1. Etap Software Training(I) (3 days)- Mazandaran Cement Co., Fall 2012
1. Protection Relays(1 day)- Ghaed Bassir Petrochemical Co. Fall 2012
1. Protection of Industrial Plants (3 days)- South Zagros Oil & Gas Production Co. Fall 2012
1. Protection of Industrial Plants (3 days)- Gas Transmission Operation District 8, Fall 2012
1. Energy Saving (3 hours)- On job training at Sazeh Consultants Co.,Summer 2012
1. Protection of Industrial Plants (3 days)- Mazandaran Cement Co., Summer 2012
1. Cable Sizing (3 hours)- On job training at Sazeh Consultants Co.,Summer 2012
1. Power Plants (6 hours)- On job training at Sazeh Consultants Co.,Winter 2012
1. Potection of LV Networks (2 days)- For Cement Companies Engineers, Winter 2012
1. LV&MV Switchgears (3 days)- Faragostaran Training Center, Winter 2012
1. Single Line Diagrams (9 hours)- On job training at Sazeh Consultants Co., Fall 2011
1. Protection of Industrial Plants (3 days)- Iranain Oil Terminals Co., Fall 2011
1. Etap Software Training(I) (3 days)- Faragostaran Training Center, Fall 2011
1. Protection of Industriasl Plants (3 days)- FooladTechnic Int. Engineering Co., Summer 2011
1. Protection of Industrial Plants (3 days)- Mapna MD2 Co., Summer 2011
1. LV&MV Cables (3 days)- Training Center of National Iran's Oil Co., Winter 2011
1. Electrical Standards (2 days)- Training Center of National Iran's Oil Co., Winter 2011
1. Protection of Industrial Plants (1 days)- Iedeh Training Center., Winter 2011
1. Protection of Industrial Plants (3 days)- Faragostaran Training Center, Winter 2011
1. LV&MV Cables (3 days)- Training Center of National Iran's Oil Co., Winter 2011
1. Etap Software Training (II) (3 days)- FooladTechnic Int. Engineering Co., Winter 2011
1. Etap Software Training II (3 days)- Faragostaran Training Center, Winter 2011
1. Protection of Industrial Plants (3 days)- Faragostaran Training Center, Fall 2010
1. Etap Software Training (II) (3 days)- Faragostaran Training Center, Summer 2010
1. LV&MV Cables (3 days)- Faragostaran Training Center, Summer 2010
1. Protection of Industrial Plants (3 days)- Faragostaran Training Center, Spring 2010
1. Etap Software Training (I) (3 days)- Faragostaran Training Center, Spring 2010
1. Etap Software Training (I) (3 days)- AryaSasol Polymer Co., Spring 2010
1. Protection of Industrial Plants (3 days)- Tondgooyan Petrochemical Co., Spring 2010
1. LV&MV Cables (3 days)- Faragostaran Training Center, Winter 2010
1. Etap Software Training I (4 days)- Faragostaran Training Center, Winter 2010
1. Protection of Industrial Plants (3 days)- Borzouyeh Petrochemical Co., Winter 2010
1. LV&MV Switchgears (3 days)- Faragostaran Training Center, Fall 2009
1. Reactive Power Control (2 days)- Rahavaran Fonoon Petrochemical Co., Fall 2009
1. Etap Software Training (I) (4 days)- Fanavaran Petrochemical Co., Fall 2009
1. Etap Software Training (I) (4 days)- Rahavaran Fonoon Petrochemical Co., Summer 2009
1. Industrial Network Design (3 days)- Faragostaran Training Center, Summer 2009
1. LV&MV Switchgears (4 days)- Faragostaran Training Center, Summer 2009
1. Course: Protection of Industrial Plants (7 days)- AryaSasol Polymer Co., Spring 2009
1. Industrial Network Design (3 days)- Faragostaran Training Center, Winter 2009
1. Earthing and Lightining (1 days)- Faragostaran Training Center, Winter 2009
1. Protection of Industrial Plants (3 days)- Faragostaran Training Center, Winter 2009
1. Etap Software Training (I) (3 days)- Chagalesh Consulting Engineers Co., Fall 2008
1. Etap Software Training I (4 days)- Tabiran Co., Fall 2008
1. Etap Software Training (I) (5 days)- Tondgooyan Petrochemical Co., Summer 2008
1. Industrial Network Design (3 days)- Faragostaran Training Center, Spring 2008
1. Etap Software Training (I) (4 days)- Zharfsazeh Consultant Co., Winter 2008
1. Industrial Network Design (3 days)- Faragostaran Training Center, Winter 2008
1. Industrial Network Design (3 days)- FooladTechnic Int. Engineering Co., Fall 2007
1. Cyme Software Training (I) (4 days)- National Iranian South Oil Co., Fall 2007
1. Etap Software Training (I) (3 days)- Forooghedanesh Training Center., Summer 2007
1. Etap Software Training (I) (3 days)- Forooghedanesh Training Center., Summer 2007
1. Etap Software Training (I) (3 days)- Forooghedanesh Training Center., Summer 2007
Book:
“ Design Analysis and of Industrial Power Systems by Etap Software” (under printing)
References:
Alireza Niakani- Founder of Faragostaran Training Center (**.*******@*****.***)
Mohamad Javaherpiur-Electrical Manager at Sazeh Co. (*.***********@*****.**.**, +98-912*******)