Sr.Planning Engineer PMP

e-mail:

**********@*****.***

Phone:

974********

Industry:

Oil & Gas,Infrastructure,Water &Waste Water

Desired

Location:

Any

Willing

to Relocate:

Yes

Desired

Salary:

$90,001/yr - $105,000/yr

Resume:

PMI Certified Project Management Professional (PMP) with several years of experience in Planning, Scheduling and Cost Controlling Activities of EPIC, EPC Projects.

Experience working in Multimillion dollar Oil & Gas, Infrastructure Projects through Galfar Almisnad Engg. Contg. WLL, Hindustan Construction Co. Ltd., etc.

Core Experience in Planning, Scheduling, Monitoring and Controlling of Tendering, Engineering, Procurement, Construction and Commissioning Phases.

Budgeting and cost control including preparation of Project/Divisional Business Plans, Project Budgets and cost control related reports like Monthly VOWD/Projection Statement including Cost Analysis, Project Performance Report, EV Curve, Cash call, detailed project ETC & EAC and major concerns.

Experience in Preparing and Establishing Progress Measurement and Reporting System, Procedures and Formats.

Excellent command in planning management tools like. Primavera (P3 & P6), SAP AIO, MS Project etc.

Excellent command in MS Office (Excel, Word, Access and Power Point) for establishing and presentation of reports.

Experience in project risk management which includes identifies risks, qualitative & quantitative risk analysis, prepare risk response plan, monitor & control known & unknown risks.

Excellent analytical and communication skill to undertake regular reviews of schedules and progress with project stakeholders in order to identify any trends, variations, concerns, conflicts and preventive actions throughout the project life cycle.

SUMMARY OF EXPERIENCE

EPIC/EPC project experience in Oil & Gas,Infrastructure Water & Waste Water.

Details of experience is summarized as below:

SN Period Duration

(Years) Company Position Held

1. June?10- Till Date 2 Years Galfar Almisnad- Qatar Sr. Planning Engineer

2. Aug ?06 ? June ?10 4 Years Galfar Almisnad- Qatar Planning Engineer

3. May ?05 ? Aug ?06 1.3 Years Hindustan Construction Co. Ltd, India Planning Engineer

4. June ?03- April? 05 1.9 Years CADD Centre Engineering Solutions, India Project Management Professional

5. Sep ?02 - May ?03 0.8 Years Hindustan Engineering Construction -India Planner

~ 10

Work Experience # 1 & 2

Organisation : Galfar AlMisnad Engg. Contg. WLL ? Doha, Qatar.

D signation : Sr. Planning Engineer

Being an Planning Engineer & Sr. Planning Engineer, My responsibility is Planning and Cost control activities for Engineering, Procurement, Construction, Pre-commissioning & Commissioning of various Projects as listed below for Qatar Petroleum, Ashghal, etc.,

Period : Aug ?06 ? Till Date

Major Projects Handled:

Qatar Petroleum

? EPIC of GTC 123/06/ED Package 3 (Construction of Roads Utility Crossings & Street Lighting in the Industrial Area Mesaieed )

? EPIC of GTC 04/183/ED - (VTC 04 & VTC 07) Expansion of Ras Laffan Avenue at Ras Laffan

? EPIC of Access Road to Beach House & Tie In Facilites within Dukhan Fields

Ashghal ? Doha South Sewage Treatment Plant Phase-II Extension works

Oryx GTL ? Installation of OBL facilities

Major Responsibilities as Sr. Planning Engineer

Planning, Scheduling, Monitoring and Controlling Engineering, Procurement, Construction and Commissioning activities with respect to Plan, Progress and Resources using latest planning tools like Primavera Project Planner (P6)

Producing & updating comprehensive project planning package.

Perform critical path analysis of the project and analyze various scenarios arising due to late arrival of equipment and delay in engineering and construction etc.

Establish and maintain activity level integration between Primavera P6 and project control database

Demonstration of project controls capability in the areas of cost control and scheduling to clients (business development)

Liaison with multi discipline engineers for work scope development.

Maintaining and updating network to revised or evolving scope.

Review, evaluation of progress on weekly basis identifying critical problem areas and indicating remedial measures for corrective actions.

Preparing, regular updating & distribution of Progress Reports (Monthly, Weekly, Daily and S- Curve, histograms) etc to Client / Internal.

Deliver project budget & monthly cost control reports by segment and by cost centers (Material, Engineering, operation, Sub-Contracts, etc.) by using SAP

Analyze and monitor project performance against baseline, identify variances and initiate early warnings for slippage

Identification and propose implementation of risk control measures including contingency plans to manage out or minimize network risks.

Perform Project & Divisional level Planning & Cost Controlling Activities like Business Plan Preparation, Project Budget Preparation, Cash Flow Curves, Work load position, Corporate level resource rolling plans, etc.,

Review & finalize monthly VOWD/Projection statements Vs Actual/Forecast Costs. Review & analyze the Estimated Cost for new and balance works

Perform Earned Value Analysis; detailed project forecast cost and major concerns.

Verify Project progress and cash invoices submitted by Contractor.

Work Experience # 3

Organization : Hindustan Constructions Co. Ltd.,

Designation : Planning Engineer

Period : May ?05 - Aug ?06

Major Projects Handled:

Allahabad Bypass Project ABP-2

? Construction of Road from Km 158+000 to Km 198+000 (Except Ganga Bridge) with Main carriageway 4 lanes of rigid pavement and Service road of flexible pavement. Contract Value of 4469.9 Millions.(for NHAI funded by World Bank)

Rajasthan Road Project

? Construction of Road from Km 253+000 to Km 316+000 with Main carriageway 4 lanes of rigid pavement and Service road of flexible pavement. Contract Value of Rs.375 Crore. (for NHAI funded by Asian Development Bank)

Major Responsibilities of Planning Engineer:

Planning, Scheduling, Monitoring and Controlling Engineering, Procurement, Construction activities with respect to Plan, Progress and Resources using latest planning tools like Primavera Project Planner (Ver. 3.1),MS Project and Enterprise Version 4.0

Producing & updating comprehensive project planning package.

Supervise supporting roles in the project schedule and cost control area.

Maintaining and updating network to revised or evolving scope.

Monitoring/follow up to ensure timely completion of the project.

Review, evaluation of progress on weekly basis identifying critical problem areas and indicating remedial measures for corrective actions.

Review & analyze the Estimated Cost for new and balance works

Preparing, regular updating & distribution of Progress Reports (Monthly, Weekly, Daily and S- Curve, histograms) etc to Client / Internal.

Deliver project budget & monthly cost control reports by segment and by cost centers (Material, Engineering, operation, Sub-Contracts, etc.) by using MS Office.

Analyze and monitor project performance against baseline, identify variances and initiate early warnings for slippage

Analysing the risks involved to prepare proper mitigation plans for achieving the Project Completion successfully

Prepare and Maintain the Hindrance Register for Contractual & Variation Claims.

Work Experience # 4

Organization : CADD Center Engineering Solutions.

Designation : Project Management Professional

Period : June ?03 - April ?05

Major Responsibilities of Project Management Professional

Project Co-Ordination for Clients Proposal and Design of Project.

Estimate & Prepare a Project Report with details of Time, Cost and Resource Requirements.

Evaluate the Project requirements and providing necessary solutions for the particular nature of the Project.

Design & Drafting the conceptual ideas to a Manageable Project .

Training & Guiding Professionals & Students in Project Management Software?s.

Schedule Preparation & Project Consultation in free lancing.

Work Experience # 5

Organization : Hindustan Engineering Constructions.

Designation : Planner

Period : Sep ?2002 ? May ?2003

Major Responsibilities as Planner

Conceptualizing the Idea to a Project Report.

Collecting & Analyzing the ground conditions for the Project.

Planning & Scheduling

Drafting & Design

Cost Estimation

Work front availability checking.

Monitoring/follow up to ensure timely completion of the project.

******@***********.***