Jangwook(Jay) Yoon, PSP
2501 Threewoods Ln Fullerton CA, 92831
Home 714-***-**** Cell714-***-**** *********@*****.***
PROFILE:
- 14 years of experience in construction and project management specialized in CPM scheduling and Project Controls.
- M.S. in Construction Management
- Advanced knowledge and skills in Primavera scheduling & document control program
- Strong field management experience and expertise in building systems
EXPERIENCE:
Irvine, CA 2011 ~ Present
- Project Controls Engineer
Attend status meetings, Engage with responsible people and Provide client consultation
Update & Analyze schedule information to generate reports showing planning and trends
Prepare and Publish monthly updates, various reports, and change request TIA
Measure Earned Value, CPI, & SPI through cost loaded schedule and Forecast the project cost
Project involved
Major Transmission Line & Substation project -DPV2/DCR (Southern California Edison Company)
Huntington Beach, CA 2002 ~ 2011
- Manager, Project Controls & Claims
Monitor the change management process with issues, cost codes, and cost worksheet
Analyze & Control budget and cost variance (Cost Worksheet, Contract Summary with Changes)
Develop, Manage, & Maintain schedules providing various formats and time impact analysis
Analyze construction performance with cost loaded schedule using earned value analysis
Prepare Weekly Reports (RFIs, Submittals, Changes, Budget Variance, Schedules, Issues, QC Notice, Safety, Impact Issue Notice & Delay Notice)
Develop Primavera Expedition manual/procedure in compliance with company policy and procedure
Manage Business Development activities and develop proposals
- Scheduler
Develop all preconstruction & project schedules based on the budget, plans and project specification
Update and maintain the project schedules on a weekly basis
Develop resource and cost loaded schedule to manage the budget
Review and implementing company policy and procedures in regards to scheduling
Identify schedule impact issue, develop delay fragnets, and analyze the time impact
Prepare all schedule delay analysis exhibits for arbitration & mediation proceedings
- Project Engineer
Manage the RFI, Submittal, and Change Management process proactively
Provide support communication & document control(Notice, Correspondence, & Closeout)
Review Timberline Report to manage the budget, Prepare monthly billing, & Review schedule of values
Projects involved
Legacy Partners APT, Canyon Country APT, Playa Vista Chatelaine, Harbor Lofts, Doria Lofts
Broadway Arms, The Family Commons, Camino del Sol APT, PV Carabela, Cahuenga, Serenade,
Promenade Lofts, City Place, Miracle Mile, The Shores, The Boradway Lofts
Seoul, Korea 1997 ? 1999
- Project Engineer
Manage daily activities & cost summary for the project, Generate the weekly construction schedule
Review detail drawings, RFIs, monthly billings and schedule of values & coordinate the schedules
Manage engineering documents according to ISO 9001(document and report all papers)
Project involved
Puchon Subway Station & Department Store Project, Seoul Korea, $60 Million
EDUCATION:
University of California, Berkeley MS in Construction Engineering and Management
Han-Yang University Seoul, Korea BS in Architectural Engineering
SUMMARY OF QUALIFICATION & CERTIFICATE:
COMPUTER: Primavera Project Management(P5/P6), Primavera Expedition 10.0/11.0 Primavera Contract Manager 12.0 (American Constructors, Inc. Expedition Trainer), Claim Digger, SureTrak, Microsoft Project, MS Office, Visio, InfoMaker, SAP System, Server System
CERTIFICATION : AACE certified Planning & Scheduling Professional (PSP)
******@***********.***
Copyright © 2003-2005 Cooper Pugeda Management, Inc. All rigths reser