ADEWALE (WALLY) AKINLOLU

*** ***** ******, ********, ** 60202

Cell: 773-***-****

Email: ************@*****.***

SKILLS Proficient in developing CPM Proficient in Microsoft Office - Excel

project schedule, updating and spreadsheet, Access Database, Word,

tracking project schedules. and PowerPoint

Expert in all versions of Primavera Proficient in Oracle's Primavera

including SureTrak, P3, P5 and p6 contract management

Proficient in Earned Value Experience in project accounting

Management System (EVMS), which management

includes cost performance index Experience in engineering, procurement,

(CPI), schedule performance index and heavy construction

(SPI) cost variance (CV), and planning/scheduling

schedule variance (SV) Proficient in developing Work Breakdown

calculations. Structure(WBS) and Organization

Proficient in Microsoft Project breakdown structure (OBS) for effective

Proficient in Working Planning project control and resources

software INDUS Passport management

Proficient in coordinating work order

planning in INDUS Passport software

CAREER Nine years of domestic and international broad-based experience in

SUMMARY engineering, and construction management, and project controls. Expertises

include; Developing Engineering design and construction schedule and cost

control, construction management, and Outage nuclear power plant project

schedule, and project performance reports. Proficient in all Primavera

versions, and Oracle databases to generate management reports. Advance user

of spreadsheet to create project estimating forms and project performance

reports.

PROFESSIONA Day & Zimmermann NPS - Xcel Energy, Monticello

L November 2009 to Present

EXPERIENCE Position: Project Control / Project Scheduler

Responsibility: Interface with site manager to develop and maintain both

engineering and construction schedule for Nuclear Power Plant Extended

Power Uprate (EPU) On-Line and Outage Work order Planning and scheduling.

Develop project-estimating spreadsheet, and generate resource forecast.

Create project key performance report (and integrate cost and schedule.

Project Type:

Nuclear Power Plant Outage and Extended Power Uprate (EPU)

Collaborate with project managers, and Plant outage manager to develop CPM

Project and Outage schedule and EPU resources optimization

Develop Project budget form through spreadsheet thus increase estimate and

budget accuracy

Administer and coordinate engineering project schedule to meet project

targeted milestones dates

Participates in weekly project progress reviews

Generate Planners productivity reports for management use

Aerotek Energy Service Schaumburg, IL (8 weeks Contract)

September to October 2009

Position: Project Control / Project Scheduling Consultant

Responsibility: Developed and maintained Coal Power Plant Outage Schedule

using P6.2.1 version. Kept track of project schedule and resource daily to

meet baseline, determined causes of unexpected or undesired float in P6

schedule, and advise Project Managers on remedies or take appropriate

corrective actions to amend the situation.

Project Type:

Indianapolis Power and Light - Coal Power Plant outage Project

Collaborated with project managers and Plant manger to develop CPM outage

schedule

Coordinated daily schedule update meeting, and maintained schedule updated

daily

Reviewed Contractors schedule and incorporated their update into the master

schedule

Administered and coordinated critical path analysis of schedule to keep on

track of the project cost to meet baseline

Prepared and issue daily status report to Plant Manager, project team and

contractors

Through cost loaded CPM schedule and resources tracking the plant manager

was help to save 10% of the total budgeted Man-hours.

MWH Global, Inc. Chicago, IL

2008 - 2009

Senior Project Scheduler

Responsibility: Project information management, project controls, project

Planning/scheduling, and Update for multiple large projects.

Project Types:

AMP-Ohio Hydro Power Plant Project

2009

Assisted in analyzing existing schedule, and developed new construction

schedule for AMP-Ohio Hydro-Power Plant using P3, and P6

Cumberland Project USCORP

2009

Converted more than ninety-four different projects schedules from Microsoft

Project into Primavera P6, and restructured their work breakdown structures

(WBS) and activities ID for easy project cost control, and reports. Created

five years cash flow projection reports with yearly Financial Escalation

factors for program and project managers use.

Panama Canal Proposal Schedule (International Project)

2008 - 2009

Assisted in developing CPM engineering design schedules for the $300m

Panama Canal new sets of locks expansion projects

Sargent & Lundy, Chicago, IL

2005 - 2008

Position: Associate Project scheduler/Planner

Responsibility: Project information management, project controls, project

Planning/scheduling, and update for multiple large projects and provided

earned value management support to the project team.

Project Types:

Bruce Nuclear Power, Bruce, Canada

2006 - 2008

Prepared and coordinated Engineering Design schedule for Bruce Nuclear

Power Plant using Primavera P3e. P5.0 and P6

Prepared and coordinated project EVM for measuring and managing project

managers performance, and project evaluation

Maintained project schedules with more than 5,000 activities on a weekly

basis.

Developed automated project actual cost and percent complete between P6 and

Oracle database to generate cost performance index (CPI) and cost variance

(CV), schedule performance index (SPI) and schedule variance (SV)

Produced Periodic look ahead schedule, critical activities path schedule

and recommendation for corrective action if necessary

Exelon Nuclear Power projects

2005 - 2006

Prepared and updated projects work breakdown structures (WBS), and

developed project schedules

Cost loaded Project schedule in P6, monitored and updated resources on

weekly basis

Prepared and updated projects monthly status reports and transmitted to

Project Team and Program Manager

Prepared projects quarterly performance trends for upper management use.

Collaborated with accounting department to prepare projects monthly

invoices

NEXUS ALLIANCE LIMITED, Lagos, Nigeria (Contract as expatriate) December

2007

Position: Project Scheduling Software Consultant (Three weeks duration)

Responsibility: Lectured new NNPC staffs fundamentals of project

scheduling, and match up competence of Primavera software, and Microsoft

Project software

CATH ASSOCIATES, Evanston, IL

2004 - 2005

Position: Assistant Project Manager

Responsibility: Assisted project managers in project scheduling, cost

estimate and project status reports. Attended Client and contractors

meetings and evaluate project progress.

Developed project estimate, and schedule

Performed site Inspection during construction and created progress report

to Field Museum management

Prepared change order requests using AIA document.

Assisted in constructability review

SPACE AND PLACE, Lagos, Nigeria

2000 - 2003

Assistant Project Manager

Responsibility: Prepared project quantity take-off, estimate, and budget.

Supervised site works, and coordinated all construction trade on site.

Reported project progress and facilitated contract payment.

EDUCATION Keller Graduate School, Chicago, IL

2008 - CONTINUING

MBA with concentration in Project Management

DeVry University, Chicago, IL

2007

Bachelor of science in Technical Management with Concentration in Project

Management

Oakton Community College, Skokie, IL

2006

Associate Degree in Construction Management

PROFESSIONA Obafemi Awolowo University Ile Ife, Nigeria

L EDUCATION 1999 - 2003

Building Technology

AACE- Chicago Chapter Annual May Seminar - Continuing Education Credit

2010

- Des Plaines, IL

New & Evolving Project Control Tools

Catalyst Project Management - Itasca, IL

2008

Primavera P3 to P6-course 108 & Advanced Project Manager course 106

AACE-Continuing Education Credit - Des Plaines, IL

2008

How Project Controls Impact the Bottom Line

Dekker Ltd - Chicago, IL

2007

Optimizing Microsoft Project for EVM

Sargent and Lundy LLC - Chicago, IL

2006

Training: Complete 23 training modules of Power Plant Fundamentals

CMAA University - Chicago, IL

2005

Title: Advance Study of Construction Scheduling

Certificate of Achievement

AACE-Continuing Education Credit - Des Plaines, IL

2005

Project Controls and Scheduling

PROFESSIONA Member Project Management Institute (PMI)

L

ASSOCIATION Member The Association for the Advancement of Cost Engineering

S International (AACEI)



Contact this candidate