ANOUAR MANSOURI

**** ****** ** *** ***

LAS VEGAS NV, 89118

TEL: 702-***-****

Email: ********@*******.***

CAREER OBJECTIVE

To secure a position with a well established organization with a stable environment that will allow me to advance in the fields of civil

engineering and construction management.

CERTIFICATIONS

• NICET II/GTE, National Institute for Certification in Engineering Technologies-Generalist (expires 11/01/2010).

• NICET II/CMT, NICET-Construction Materials (expires 11/01/2010).

• ICC/RC, Reinforced Concrete Special Inspector (Expires 03/10/2013).

• ICC/FP, Fire Proofing Special Inspector (Expires 01/29/2011).

• NAQTC (Asphalt, Embankment, Lab), Nevada Alliance For Quality Transportation Construction (Expires 10/31/2011).

• ACI Field, Concrete Field Testing (Expires 09/23/2011).

• Currently preparing for ICC/CWI.

PROFESSIONAL EXPERIENCE

3/08 to Present G.E.S. INC. Las Vegas, Nevada.

Quality assurance supervisor

WINDMILL LIBRARY, Clark county, Nevada:

Project consisted of grading of the building a library on Windmill Rd and rainbow Blvd ($50 Million project). Project included

excavation, grading, backfill and installation of water lines, sewer lines, and utility lines. Performed grading observation and testing

using a nuclear gauge to determine density and moisture conditions. Inspected and certified footings. Obtained soil samples and

coordinated lab testing. Monitored and inspected the reinforcement placement in the building pad, footings and columns. Supervised

the testing technicians and reviewed their daily reports and timesheets for accuracy. Attended weekly progress meetings with

contractors to provide progress schedules, and address technical issues.

SURREY/PAMA, Clark County, Nevada:

Project consisted of building a commercial center ($35 Million project). Project included excavation, grading, backfill and

installation of water lines, sewer lines, and utility lines. Observed the location and removal operations of septic tanks. Performed

grading observation and testing using a nuclear gauge to determine density and moisture conditions. Inspected and certified footings.

Obtained soil samples and coordinated lab testing. Inspected the reinforcement placements. Monitored the drilling of 30ft caissons,

the installation of the reinforcing steel cages, and the concrete placements. Supervised the testing technicians and reviewed their

daily reports and timesheets for accuracy. Attended the weekly progress meetings with the various contractors to discuss progress

schedules, and address technical issues.

CARREY/INDUSTRIAL, Clark County, Nevada:

Project consisted of building a commercial center ($40 Million project). Project included excavation, grading, backfill and

installation of water lines, sewer lines, and utility lines. Performed grading observation and testing using a nuclear gauge to

determine density and moisture conditions. Inspected and certified footings. Obtained soil samples and coordinated lab testing.

Inspected the reinforcement placements, monitored the concrete placement operations, and supervised the testing technicians and

reviewed their daily reports and timesheets for accuracy. Attended the weekly progress meetings with the various contractors to

discuss progress schedules, and address technical issues.

9/05 to 2/08 KLEINFELDER INC. Las Vegas, Nevada.

Quality assurance supervisor

CITY CENTER LAS VEGAS, Clark County, Nevada:

Project consisted of building a mega resort and casino ($7.4 Billion project). Supervised the observation and inspection operations of

reinforcement and the east and west tilted towers, the east garage foundation, and signed the concrete placement authorization slip. Inspected th

reinforcement placements, monitored the drilling of 50ft caissons, the installation of the reinforcing steel cage and the concrete placement.

Coordinated with contractors the concrete placement operations and scheduled technicians. Supervised the testing technicians and reviewed the

daily reports and timesheets for accuracy. Attended the weekly progress meetings with Perini representatives and various subcontractors to

discuss progress schedules, and address technical issues

SOLIDS DEWATERING STATION, Clark County, Nevada:

Project consisted of expending and modernizing the sewer treatment plant ($2 Billion project). As a quality control supervisor, I performed

quality control observation and testing on the grading operations of the building pad, and backfill operations on sewer, water and utility lines

Anouar Mansouri

throughout the project. Performed soils testing using a nuclear gauge. Inspected the reinforcement placements in the building mat foundation,

and around the utility lines. Inspected the waterproofing around the basement walls. Supervised the testing technicians and reviewed their

daily reports and timesheets for accuracy. Assisted the Project Engineer with the cost and technical review of proposals and change orders.

Attended the weekly progress meetings with the City Representatives and various contractors to discuss progress schedules, and address

technical issues.

NOVELS, Clark County, Nevada:

Project consisted of grading of a 2 subdivision housing development ($30 Million project). Project included excavation, grading, backfill and

installation of water lines, sewer lines, and utility lines. Performed grading observation and testing on the Terminal pad and taxiways

embankment using a nuclear gauge and sand-cone equipment. Implemented the quality assurance program for the Department of Aviation.

Inspected the reinforcement placement in the building pad, the footings, and the sidewalks. Coordinated with contractors the concrete placemen

operations and scheduled technicians. Supervised the testing technicians and reviewed their daily reports and timesheets for accuracy. Attende

weekly progress meetings with Clark County Representatives and various contractors to provide progress schedules, and address technical

issues. Used Primavera 3.1 to track and control the project weekly schedule updates.

MCCARRAN AIRPORT TERMINAL3, Clark County, Nevada:

Project consisted of building Terminal3 and its taxiways at McCarran Airport ($250 Million project). Obtained a Federal Security Clearance

from the Department of Aviation. Performed grading observation and testing on the Terminal pad and taxiways embankment using a nuclear

gauge and sand-cone equipment. Implemented the quality assurance program for the Department of Aviation. Inspected the reinforcement

placement in the building pad, the footings, and the sidewalks. Coordinated with contractors the concrete placement operations and scheduled

technicians. Supervised the testing technicians and reviewed their daily reports and timesheets for accuracy. Attended weekly progress

meetings with Clark County Representatives and various contractors to provide progress schedules, and address technical issues. Used

Primavera 3.1 to track and control the project weekly schedule updates.

.

7/03 to 9/05 TERRACON CONSULANTS, Las Vegas, Nevada.

Quality assurance supervisor

REDROCK HOTEL AND CASINO, Clark County, Nevada:

Project consisted of building the east garage with the tunnel leading to the casino ($800 Million project). Inspected and certified the

column and continuous footings around the building, inspected the backfill and waterproofing operations around the tunnel, as well

as the fill placement in the garage basement. Obtained soil samples and coordinated lab testing. Inspected the reinforcement

placements, monitored the concrete placement operations, and supervised the testing technicians and reviewed their daily reports and

timesheets for accuracy. Attended the weekly progress meetings with Perini representatives and various contractors to discuss

progress schedules, and address technical issues.

PALMS HOTEL AND CASINO, Clark County, Nevada:

Project consisted of grading the Park Place Tower and the Concert Venue buildings as well as the pool area in tower II ($300 Million

project). Inspection and certification of column and continuous footings in and around the buildings. Monitored ground water

control operations and saturated soils removal and replacement and ground stabilization. Performed observation and testing using a

nuclear gauge to determine density and moisture conditions. Obtained soil samples and coordinated lab testing. Inspected the

reinforcement placements, monitored the concrete placement operations, and supervised the testing technicians and reviewed their

daily reports and timesheets for accuracy. Attended the weekly progress meetings with the City representatives and various

contractors to discuss progress schedules, and address technical issues. Used Primavera 3.1 to track and control the project weekly

schedule updates.

PANORAMA TOWERS I AND II, Clark County, Nevada:

Project consisted of building the garages of towers I and II ($70 Million project). Inspection and certification of column and

continuous footings around the buildings. Inspection of backfill and waterproofing around the garages and retaining walls, and fill

placement in the basements and inside the garages. Performed observation and testing using a nuclear gauge to determine density

and moisture conditions. Obtained soil samples both native and import materials and coordinated lab testing. Monitored the drilling

of 50ft caissons, the installation of the reinforcing steel cages and the concrete placement. Supervised the testing technicians and

reviewed their daily reports and timesheets for accuracy. Attended the weekly progress meetings with the various contractors to

discuss progress schedules, and address technical issues. Used Microsoft Project to track and control the project weekly schedule

updates.

HENDERSON EXECUTIVE AIRPORT, HENDERSON, NV:

Project consisted of building new runways and taxiways and expansion of the existing terminal ($40 Million project). Performed

grading observation and testing using a nuclear gauge to determine moisture density conditions, also performed thickness and

straight edge testing of sub-grade on the taxiways and runways. Observed asphalt placement on runways and taxiways. Inspected the

reinforcement placements, supervised the testing technicians and reviewed their daily reports and timesheets for accuracy. Attended

the weekly progress meetings with the City representatives and various contractors to discuss progress schedules, and address

technical issues. Provided quality assurance testing for the Department of Aviation. Used Primavera 3.1 to track and control the

project weekly schedule updates.

Anouar Mansouri

4/00 to 7/03 CONVERSE CONSULTANTS, Las Vegas, Nevada.

Quality Assurance Supervisor

US 93 Hoover Dam Bypass, Boulder City, Nevada:

Project consisted of US93 freeway and Nevada-Arizona bridge construction on the Nevada Approach ($180 Million project). As

Quality Control and Quality Assurance Supervisor, monitored the drilling operations of rocks to be blasted and used as rock fill for

embankment construction. Observed fill placement and compaction efforts. Certified footings. Collected soil samples for lab testing.

Observed the benching of the 2:1, 3:1, 5:1 and 6:1 overbuilt slopes. Monitored the breaking and scattering of oversize material to

prevent nesting. Counted the number of truck loads placed and compacted. Checked and approved the contactor’s payment

authorization slips. Verified steel deliveries and mill certifications. Inspected the reinforcing steel placements. Coordinated with

contractor on concrete placement operations and scheduled testing technicians. Monitored testing technicians and reviewed their

daily reports and timesheets for accuracy. Conducted weekly progress meetings and phase startup meetings with FHWA

representatives and various contractors to provide progress schedules, address technical issues, safety concerns and clarify FHWA

building codes and specs. Assisted the Project Engineer with the cost and technical review of proposals and change orders. Used

Primavera 3.1 to track and control the project weekly schedule updates.

Sunrise Highlands “THE QUARRY”, Clark County, Nevada:

Project consisted of mass grading of housing development, over-excavation of all silting basins ($70 Million project). Scanning of

the project with GPR System and investigation of anomalies and voids in the ground under the supervision of the project Geologist.

Observed the backfill operations of holes and caves using soils or bridging material and approved soil. Observed the removal of

diesel tank, municipal trash and all contaminated soils. Recorded the depth and location of any collapsible material encountered.

Obtained soil samples for lab testing. Performed observation and testing of grading operation using a nuclear gauge. Monitored the

benching process of 2:1 and 3:1 overbuilt slopes. Inspected the reinforcement placements. Attended the weekly progress meetings

with the various contractors to discuss progress schedules, and address technical issues.

Terminal D, McCarran Airport, Las Vegas, NV:

Project consisted of excavation, fill and grading of embankment for airport expansion (Runways 7R-25L and New north and south),

as well as installation of future tramway linking Terminal D to future Terminal ($150 Million project). Performed grading

observation and testing using a nuclear gauge and sandcone equipment to determine moisture-density conditions. Performed

thickness and straight edge testing of fill and asphalt placement operations on the taxiways and runways. Supervised testing

technicians and reviewed their daily reports and timesheets for accuracy. Provided quality acceptance testing for the Department of

Aviation. Performed inspection of the concrete mat foundation and walls for the tramway connecting terminal D with future

terminal. Reviewed submittal and change orders. Attended weekly progress meetings with Clark County representatives and various

contractors to provide progress schedules, and address technical issues.

I-15 Channel, Las Vegas, NV:

Project consisted of the construction of a reinforced concrete flood control channel ($90 Million project). Project included

excavation, groundwater control, installation of storm drain boxes, and backfill operations. Performed observation and testing using

a nuclear gauge. Inspected the reinforcement placements, and inspected the concrete placement operations. Attended the weekly

progress meetings with the various contractors to discuss progress schedules, and address technical issues. Used Microsoft Project to

track and control the project weekly schedule updates.

Iron Mountain Ranch, Las Vegas, NV:

Project consisted of mass grading of an 8-subdivision housing development ($80 Million project). Performed observation and testing

on ever-excavation, fill placement and grading of highly collapsible native material. Gravely import material was used for foundation

stabilization. Inspected the backfill operations of water lines, sewer lines, storm drains and utility lines. Performed grading

observation and testing using a nuclear gauge to determine density and moisture conditions. Inspected reinforcement placements in

the building pads, footings and columns, and performed observation and field testing of concrete and grout placements. Attended

weekly progress meetings with the Clark County representative, the owner and various contractors to provide progress schedules,

and address technical issues. Provided quality acceptance testing for KB home Nevada Inc.

EDUCATION

University of Nevada Las Vegas

Major: Civil Engineering

Level: Senior

COMPUTER SKILLS

Scheduling and planning software: Primavera Project Planner (P3.1), Microsoft Project.

LANGUAGES

French, Arabic, and some Spanish

Anouar Mansouri