MINUTES OF MEETING
Date/Time: Project Name:
Location: Project No.:
Subject: Weekly Coordination Meeting Prepared By:
File No.: Date Issued:
Attendees:
Distribution:
ITEM ITEM ACTION DUE
NO BY DATE
1. Administrative Issues
2. Schedule
3. Technical Issues
4. Safety Issues
5. Budget
6. General
7. Manpower Issues
8. Outstanding Issues
MINUTES OF MEETING
Date/Time: March 10, 2003 Project Name: Campbell Mine
DC Project
Location: Heat Office Project No.:
Subject: Highlights Report for Week Prepared By:
Ending 07 March 2003
File No.: Date Issued: March 10, 2003
Attendees: . Bensley, B Osaduik, G Lawson, R. DePiero, C Schimper, M
Raffield
R Corbeil, D Ukrainetz, P Gula,
L Major, M Creaney, R Mah
Distribution:
Safety:
1. No incidents to report for this period
Manpower:
This Week Last Week
Development (per shift) 3 3
Work Accomplished This Week
Procurement / Contracts:
1. Completed preparing Tender Package for Mine Office Building addition
2. Issued Tender Packages (6 bidders) for Mine Office Building addition
2. Issued P.O. for engineering design for Maintenance Shop O/H Crane
3. Issued P.O. for Grizzlies / Rockbreakers installation
General
1. No PCN's issued this week
Project Management/Design (Area 100)
1. Completed Mine Office Building addition conceptual design
2. Complete Capital Cost Breakdown
3. Site visit with local contractor to review renovation / addition
requirements at Office #2 was delayed due to Office being occupied at
this time. Site visit to be rescheduled. Decision has been made to
hire architect to design addition
Equipment (Area 200)
1. Expedited equipment deliveries
Development (Area 300)
1. Completed work on 39 Level Raise access. 24 ft. advance achieved
2. Commenced work on Maintenance Bay heading. 12 ft. advance achieved
3. Commenced work on 39 stn Dump Ore heading. 28 ft. advance achieved
4. Delay incurred due to mucking problem. The problem was resolved
Ventilation (Area 400)
1. No activity
Shaft Services (Area 500)
1. No activity
Hoisting (Area 600)
1. Continued work on completing Fire Suppression system and deficiencies
for 40 level Loading Pocket
Backfill (Area 700)
1. Backfill System review ongoing. Golders to be brought to site for
system design
Electrical (Area 800)
1. No activity
Mechanical (Area 900)
1. No activity
Work Planned for Next Week
Procurement / Contracts:
1. Expedite delivery of Grizzlies
2. Expedite delivery of Rockbreakers
3. Issue P.R. / P.O. for Golders for Backfill System infrastructure
design
4. Issue P.R. / P.O. for Main Feed Cable requirements for year 1
General
1.
Project Management/Design (Area 100)
1. Commence conceptual design for Office Building #2 addition
2. Continue review of outstanding Development (yr 2 and yr 3)
requirements
Equipment (Area 200)
1. Expedite underground mobile equipment
Development (Area 300)
1. Continue work on Maintenance Bay
2. Continue work on 39 stn Dump Ore