BRET ZLATNIK, PE, LEED AP **** Fox Hollow Circle

Wildwood, Missouri 63069

Home: 636-***-****

Mobile: 314-***-****

Email:

*.*******@*******.***

EXPERIENCE OVERVIEW/RESPONSIBLITIES

My career has provided me the opportunity to gain over 25 years of experience in the commercial construction

industry as a Project Engineer, Estimator, Project Manager, Senior Project Manager, and Regional Manager. With

a B.S. degree in Civil Engineering, PE Registration, LEED AP, Army Corps of Engineers CQM Certification, Wal-

Mart SWPP Certification, and extensive field experience I have been able to perform an extensive range of

management duties on a wide variety of projects and proposals with a successful record of profitable projects and

satisfied clients. My experience has involved providing a full range of preconstruction and construction

management services including estimating, procurement, scheduling, field management and coordination, quality

control, cost and budget management, and contract administration. From working closely with owners, architects

and engineers from project conception through completion my experience has allowed me to evaluate and

determine the most cost effective use of manpower, materials, subcontractors, means and methods to ensure a

high quality, safe and successful project.

RELEVANT EXPERIENCE/PROJECT LISTING:

2003-Present Senior Project Manager, Walton Construction

Power Plant Structural Repairs, Clarence Cannon Dam/Mark Twain Lake - Power Plant Remediation

Work for the US Army Corps of Engineers, St. Louis District - $ 969,235 (Negotiated, Joint Venture

Disadvantage Business Partner JL Brown Contracting Services)

Chesterfield Medical Institute, Chesterfield, Missouri: 20,000 square foot/2-Story medical office

building - $6.8 Million (Negotiated, GMP at Risk Contract)

Wal-Mart Supercenter Expansion, Chesterfield, Missouri: Existing store retrofit into a Supercenter -

$11 Million (Hard Bid/Lump Sum Contract)

St. Peter’s Rec Plex Renovation & Expansion, St. Peters, Missouri: 140,000 square foot Design/Build

project; Recreational facility and renovation to the existing facility; Two NHL sized ice rinks with

spectator seating, 2 gyms, High Intensity training center, and commercial kitchen - $ 18.5 Million (Hard

Bid, Lump Sum Contract)

AMC Theatre Mega Plex, Chesterfield, Missouri: 14 Screens, existing Mall expansion/retrofit - $6.7

Million (Hard bid, Lump Sum Contract)

Metro Link (Contract 13.1) Station Finishes, St Louis, Missouri: Finish build-out to four (4) Stations

with Elevators; Site work, architectural, structural, site furnishings, specialty items, elevator, HVAC,

plumbing and electrical finish work - $7.2 Million (Hard Bid, Lump Sum Contract)

BRET ZLATNIK, PE, LEED AP,

Relevant Experience Continued:

St Louis Art Museum Renovations, St Louis, Missouri: Renovation of upper penthouse into print

storage, viewing, and classroom area - $875,000 (Hard Bid, Lump Sum Contract)

Harrah’s Casino Hotel Tower, Renovation, Warehouse Expansion, Maryland Heights, Missouri: 12-

Story hotel tower addition, parking deck improvements, warehouse expansion - $47.5 Million (GMP at

Risk Contract)

2009 Proposal Collaborative work with Walton’s Procurement Group: Worked with the Procurement

Group assisting in assemblage of Proposals; Provided Production Group input/over-site; Pre-bid

scheduling (including conceptual scheduled for Design/Build proposals); Generated proposal narratives;

General Conditions estimates - Representative Projects: Truman VA Hospital Renovation -

Columbia, Missouri ($10.8 Million); US Army Reserve Center - St. Louis Missouri ($10.4 Million); Von

Maur Department Store at the Meadows - O’Fallon Missouri ($14.4 Million); VA Medical Clinic -

Biloxi Mississippi ($18 Million); 5th & Walnut Parking Garage – Columbia, Missouri ($14.6 Million);

Medical/Dental Clinic – Ft. Lee, Virginia (Prequalification Proposal); Central Campus Building 2 – Ft.

Lee, Virginia ($14.6 Million); General Purpose Warehouse – Tinker Air Force Base, Oklahoma ($20

Million); Forest Park Hospital Parking Lot/Entrance Modifications – St Louis, Missouri ($3.1

Million); USCOE Joint Operations Building 68 Renovation ($15.2 Million); Evansville High School

GC Package – Evansville Indiana ($16.6 Million); Sunset Hill Aquatic & Community Center – Sunset

Hills, Missouri ($5 Million); Ft. Leonard Wood TRUP09 Buildings – Ft Leonard Wood Missouri ($27.5

Million); Williamson County Jail – Marion, Illinois ($ 20 Million); City of Chesterfield Central Park

Phase 2 - Chesterfield, Missouri ($7.6 Million); Parkway Central Science Renovation & Addition – St

Louis, Missouri ($ 6.8 Million); UMC Tate and Switzer Hall Prequalification Package - Columbia,

Missouri; Ft. Leonard Wood Digital Training Facility – Ft. Leonard Wood, Missouri ($ 12 Million),

Barren County Jail – Glasgow, Kentucky.

2001 – 2003 Project Manager, C. Rallo Contracting

Ameristar Casino Platinum Club, St. Charles, Missouri: $3 Million (Hard Bid, Lump Sum Contract)

Pattonville School District, Maryland Heights, Missouri: $1.1 Million multiple school glazing

replacement (Hard Bid, Lump Sum Contract)

Earth & Planetary Sciences Building, Washington University, St. Louis, Missouri: Concrete Package

(flatwork and foundations) - $4.1 Million (Hard Bid, Lump Sum Contract)

2000.2001 Regional Manager, Bick Group

Charter Communication Primary and Head End Facility Expansion Program: Multiple projects varying in

size from $1 Million to $3 Million throughout the South Atlantic and Mid South Regions (Tennessee, Kentucky,

Georgia, Florida). Reviewed and assisted in site selection; coordinated design adaptation process for selected site;

assembled bid packages, made awards, and administered contracts. (Concurrently managed 10 projects; 3 Project

Managers).

Page 2 of 3

BRET ZLATNIK, PE, LEED AP

Relevant Experience Continued

1999.2000 Project Manager, R.G. Brinkman Company

Lowes, South Charleston, West Virginia - $ 4 Million

Chesterfield Day School, St. Albans, Missouri - $ 4 Million

Forsyth Center, Clayton, Missouri: 15 Story, Design/Build high rise commercial office/tenant building -

$45 Million

1997.1999 Project Manager, Medix Construction (Houston, Texas)

HealthSouth Outpatient Surgery Center, Hazelwood, Missouri: Outpatient surgery center with

radiology/oncology, physical therapy and physician office space; 20,000 square foot expansion and

60,000 square foot retrofit of an existing building shell adjacent to the existing surgery facility - $ 6

Million (Negotiated, GMP at Risk)

1993.1997 Project Manager/Project Superintendent/Project Engineer, Sverdrup Facilities

TWA Ambassador Club/Concourse B to C connector, Automation Upgrade Lambert Airport, St.

Louis, Missouri - $ 7.5 Million (Design/Build, Hard Bid, Lump Sum Contract)

McDonnell Science Building Animal Lab Renovation, Washington School of Medicine, St. Louis,

Missouri: Clean Room interior finish refurbishment of existing/operational lab space. Project performed

within the operating, limited access/high security area of the research facility - $ 2.3 Million (Negotiated

Contract)

East McDonnell Specialized Research Facility (EMSR)/Clinical Science Research Building North

Tower (CSRB), Washington University School of Medicine, St. Louis, Missouri: State-of-the-art

research facilities concurrently built, located in the heart of the Barnes-Jewish-Children’s Hospital

complex;

East McDonnell Facility (EMSR): 8-Story, $40 Million (GMP at Risk Contract)

Clinical Science Building (CSRB): 10-story, $ 50 Million (GMP at Risk Contract)

Scott Street Tunnel, Washington University School of Medicine, St. Louis, Missouri: Connector

tunnel between the EMSR building and adjacent facility - $ 2 Million Design/Build (GMP at Risk

Contract)

1986.1993 Project Manager/Project Engineer, Fru-Con Construction Inc.

Castle Rock Factory Shops, Castle Rock, Colorado: 320,000 square foot, retail open air shopping mall

with food court - $ 20 Million (Negotiated Construction Management Contract with Joint Venture

Partner/Owner - The Prime Group)

Page 3 of 4

BRET ZLATNIK, PE, LEED AP

Relevant Experience Continued

Southwestern Bell Regional Data Center, St. Louis, Missouri: 640,000 square foot, 11-story, downtown

high-rise computer facility, reinforced concrete structure founded on piling, with a precast concrete, glass

and granite façade - $110 Million (Hard Bid/Lump Sum Contract)

Memorial Hospital of Laramie County, Cheyenne, Wyoming: 8-story, emergency, radiology, surgery,

outpatient and ICU facility expansion tied to existing facility, existing patient room renovation,

auditorium addition - $20 Million (GMP at Risk Contract)

1984.1986 Project Engineer, HBE Corporation

Eldorado of Sun City Retirement Center, Sun City, Arizona: Multi-building, 3-story condominium

complex with community center; $ 15 million Design/Build (HBE Owned Facility)

Bakersfield Credit Union, Bakersfield California: $3 Million (Design/Build)

Huachuca Federal Credit Union, Sierra Vista, Arizona: $1.3 Million (Design/Build)

First National Bank of Alpine, Alpine, Texas: $2 Million (Design/Build)

Kitsap Federal Credit Union, Bremerton, Washington: $2 Million (Design/Build)

EDUCATION/TRAINING & CERTIFICATIONS

Bachelor of Science Civil Engineering, Kansas State University (1984-Chi Epsilon)

Registered Professional Engineer (Wyoming 1990, Missouri 1998)

LEED Accredited Professional (2007)

U.S. Army Corps of Engineers Construction Quality Management for Contractors (2009)

Florida Certified Contractor’s License Holder (#CGC1516433)

Virginia Contractor’s License Holder (#2705 130839A)

Wal-Mart Storm Water Professional

SYSTEMS EXPERIENCE

Primavera P3, Suretrak, MS Schedule

Microsoft Office, Excel, Word

Constructware, CMiC

REFERENCES - Available Upon Request

Page 4 of 4



Contact this candidate