Resume:

Theodor A. Lichiardopol

*** *******

Lake Dr.,Canton GA 30115

Personal E-mail: **********@*****.***

Cell

310-***-****

Objective

Seeking a Mechanical Engineering, Maintenance Supervisor or Project

Engineer position in the pursuit of a successful career in manufacturing in

aluminum, titanium, steel, casting, and extrusion or forging industry.

Major strength in rebuilding and repair of large and small extrusion and

forging presses (from 1500T. to 14,500T.) used in aluminum industry.

Provided design and drafting assistance to manufacturing and installation

of components in support of plant maintenance.

Professional Experience

. Facilities project engineer (Contract engineer) for Weber

Metal from May 2007 to July 2008 Paramount, CA.

. Replacement of crack bottom crosshead on 12,000 T. forging

press. Taking the press a part and assembly back on record

time

. Support in all facilities major projects like additional

buildings, repairs of buildings, installation of new

clarifiers and preparation for new Ti grinder and new Ti

expansion building. Using Microsoft project to schedule all

above projects.

. Project engineer specialist for Firth Rixson Cucamonga, CA.

from November 2006 to May 2007 on repair and welding the cast

iron hammer frame in China. Align the ring roller in China.

Started the design and manufacturing schedule for the 1200T

ring roller for Schlosser Forge Co Schedule and direct the

exchange of the main ram on 4000T. Forging press.

. Project engineer for Universal Alloy Canton Georgia from June

2005 to November 2006 for redesign, dismantle removal and

installation of 16,000 Extrusion press from water design to

oil hydraulic. Design the run out table tooling and the

billet scalper for this press. Plan and design new raking

system to be able to move the material faster through the

heat treatment and finishing using the lean principle.

. Alcoa Inc. from January 1991 to May 2005 senior mechanical

engineer. Writing specification for welding main cylinder

cracked for 8000T forging press. Supervise and write work

orders for maintenance crew. Delegate the PM program with

maintenance. Prepare weekly project status and reports for

management and followed up open issues. Design and built with

maintenance crew a caustic recovery system next to auto etch

system. Dismantle and refurbish three forging presses from

I.L.M and install them on Alcoa/Kofem plant in Hungary.

Repair and redesign the two 14,000T extrusion presses in

Halethorpe MD. Plan, coordinate and direct the maintenance

crew on this plant. Minimize the production downtime using

the weekends to do all repairs required. Design and managed

the implementation of engineering projects, including

modification of pump room, extrusion presses, stretcher, heat

treat furnaces. Helping to close the plant on Halethorpe

after 2001 and restart the plant on October 2004. Install the

big block on melting furnace on Lafayette Indiana casting

house in record time and saving Alcoa $ 500,000. Involved and

schedule for maintenance crew all refractory repairs on

furnaces, casting pits, metal throughing and environmental

issue in Ingot plant. Prepare project status to upgrade and

modernize the two biggest extrusion presses in the word

located at Alcoa plant in Samara Russia. I spent three months

in Russia to start this project.

. Shultz Steel on South Gate CA. from May 1998 to June 1999 as

senior project engineer to design and fabricate all the parts

for 5,000T ring expander. Purchase all the bag houses for the

new grinding room. Obtain competitive bids for new air

compressors for the grinding room. Design the new air system

and hire the piping contractor to execute and install the new

system. Remove the old manipulator from 6000T forging press

Glama manufacture and replace with a Dango manipulator

manufacture in a record time of three weeks including new

foundation.

. Universal Alloy Anaheim CA from February 1997 to May 1998

involved with maintenance crew day to day activity and

overhauling two old extrusion presses.

Responsible with increasing the tonnage on the two extrusions

presses above through modification of the pull backs to

double acting pull backs.

Martin Marietta Aluminum (International Light Metals)

Torrance CA. from May1979 to January 1991 as senior project

engineer to design and followed through execution and

installation of big components for 14,500T. extrusion press,

8,000T. forging press. Involved on installation of two vacuum

furnaces for Ti plant. Taking on all

Other experience from July 1967 to 1977 was in Romania where

I worked in casting house with nonferrous alloys, being in

charge of 200 workers and on rolling mills major overhauls

and repairs in the plant and creating my own crews from

maintenance group and scheduling the time to do these

repairs. design institute for the design, installation of a

plant to cast and manufacture aluminum plates and aluminum

foil mill.

Professional references'. John C. McCollum senior facilities

engineer. I worked for him as facility engineer and project

engineer specialist for two years. Cell telephone number

714-***-****.

Paul Scaglione engineering manager at Universal Alloy. I

worked with Paul over 25 years in Alcoa and Martin Marietta

Aluminum (International Light Metals) cell telephone (714)-

238-2240.