I HAVE TWELVE YEARS OF SUCCESSFUL EXPERIENCE AS A SITE ACQUISITIONS/ZONING
SPECIALISTS, THIS INCLUDES NEW BUILDS UP TO UMTS PROJECTS. I'VE WORKED IN
OREGON, WASHINGTON, CALIFORNIA, MICHIGAN, OHIO, TEXAS AND ATLANTA, GA.
WORKING WITH MAJOR TELECOMMUNICATIONS CORPORATIONS.
employment History
CONSULTING
APR 08 - CURRENTLY
Oregon/Washington/N. California
Site Acquisition Specialist
Responsibilities:
. Various Jobs, Scip packages, Audits, Real Estate Values on Towers, Etc.
MACTEC DEV. CORP. /Nokia Feb. 07 - Oct. 07
Dallas, Houston, TX/Atlanta, GA
Senior Project Coordinator, Grade 23
Supervisor-Steve Hubacher
Responsibilities:
. Purpose of Project to update cellular towers with UMTS antennas &
cabinets
. Worked closely with RF, Op's., and construction to ensure a timely
build
. Procured signatures on letter of consent
. Review lease agreement between the landlord and client
. Expedited building permit applications
. Applications for co-locations for tower companies (American Towers,
Crown Castle, etc.)
. Perform review of the Structural Report and Construction drawings
. Pulled Building and Electrical Permits on approximately 125 sites,
total sites of 470 plus
Consulting June 06 - Feb 07
Oregon/Washington/N. California
Site Acquisition Specialist
Responsibilities:
. Various Jobs, Scip packages, Audits, Real Estate Values on Towers, Etc.
Consulting/Pacific Telecom Services Jan 06 - Apr 06
San Antonio, TX
Site Acquisition/Zoning Specialist
Responsibilities:
. Procured signatures with Counties and Cities which state no Building
Permits required
. Worked closely with RF, Op's., and construction to ensure a timely
build
. Find rooftop candidates & co-location sites that are suitable for Project
needs
. Negotiate lease agreement between landowners and major carriers
. Worked on approximately 120 sites, total sites of 480 plus
Consulting/The Lyle Co. Mar 05 - Dec 05
Portland, OR
Site Acquisition/Zoning Specialist
Supervisor-Steve Hubacher with Lucent
Responsibilities:
. Purpose of Project to update cellular towers with UMTS antennas &
cabinets
. Initially responsible for 110 sites out of 465
. Procured signatures on letter of consent, review lease agreement
between the landlord and client
. Worked closely with RF, Op's., and construction to ensure a timely
build
. Expedited building permit applications, 15 sites or 7 Jurisdictions
were convinced that work to be performed was maintenance (No Building
Permit Required)
. Perform review of the Structural Report and Construction drawings
. Worked closely with the 23 Metro Jurisdictions, zoning reviews and
building permits
. Very flexible in finding win/win solutions for unique situations
Consulting/Wireless Capital Partners Feb 02 - June 04
Seattle, WA. area
Lease Consultant
Responsibilities:
. Renegotiated leases with landlords for lower monthly payments or
complete buy out of contract
TrinTel Communications, Inc/SAS Sept 00 - Oct 01
All of Oregon & Northern WA.
Site Acquisition/Zoning Specialist
Responsibilities:
. Coordinated with RF Engineers, Zoning and Construction to ensure site
requirements
. Assembled and submitted 2 complete Site Candidate Packages (SCIP) for
client approval,
. Procured zoning maps, parcel maps, street maps and deeds for selected
sites
. Negotiated an acceptable lease agreement between the landlord and
client
. Complete building permit applications, attend public hearings, and
community meetings
. Performed review of the zoning and construction drawings and made
necessary changes
. Requested Title Reports for the approved candidate
. Covered Southern Washington and Oregon
Consulting-Da'Kine Construction Sept 98 - May 00
Northern MI and Toledo, Ohio
Site Acquisition/Zoning Specialist
Responsibilities:
. Coordinated with RF Engineers, Zoning and Construction to ensure site
requirements
. Assembled and submitted 2 completed Site Candidate Packages (SCIP) for
client approval,
. Procured zoning maps, parcel maps, street maps and deeds for selected
sites
. Negotiated an acceptable lease agreement between the landlord and
client
. Completed building permit applications, attend public hearings, and
community meetings
. Performed review of the Zoning and Construction drawings and made
necessary changes
. Requested Title Reports for the approved candidates
. Covered Southern Ohio and Michigan
. Completed 27 raw land sites in above time frame