Scott A. Neumann
***** ****** ****** ********, ** 90503
**********@*******.*** (310) 525 - 0683
[pic]
Qualifications
More than eight years of diverse project management experience with a
strong background and professional network in the construction industry.
Experience with running construction projects for Colich Construction,
management of projects for various city agencies with CBM Consulting, and
supervision of projects as part of the Community Redevelopment Agency of
the City of Los Angeles.
Professional
KOA Corporation / CBM Consulting, Inc. Gardena, CA (2004-Present)
Project Manager
Managed various Roadway, Building Renovation and Building
Construction projects including:
Construction Manager for the construction of the Admiral Kidd Park Phase 2
Improvement Project for the City of Long Beach, a $2.5 million dollar park
expansion.
Provided Staff Assistance for the Community Redevelopment Agency. Served as
Construction Specialist; assisted CRA staff in the planning & development
stages of new projects. Solely responsible for the management of all
projects under design & construction. Managed architects and engineers
during the design process. Prepared budgets for all projects under
development and, provided estimates on all projects during planning.
Construction Manager for the construction of the Long Beach Admiral Kidd
Teen Center, a $2 million dollar, 3,000-sq.-ft. Teen Center.
Construction Manager & Observer for the Hermosa Beach Sewer Improvements
project. Project consisted of the removal and replacement of existing PVC &
VCP sewer lines, sewer lining and construction of manholes in various
sections of Hermosa Beach.
Construction Manager for the City of Rancho Palos Verdes, Point Vicente
Interpretive Center Expansion, a $5 million dollar, 10,000-sq.-ft. building
expansion project
Construction Inspector for the Hawthorne Street Rehabilitation Project.
Project consisted of the reconstruction of a half mile of existing roadway
with ARHM- Asphalt-Rubber Hot Mix including new medians, the overlay of 5
city blocks, and the replacement of sidewalk, curb & gutter and curb ramps.
Construction Manager, Multi Service Center Remediation & Reconstruction
project, Long Beach. Mold remediation & reconstruction valued at $300k.
Construction Manager, Signal Hill Patterson Street Improvements project.
Value $350k.
Supervised the condo conversion of a 40 unit apartment complex including
the full remodel of 28 units, City of Long Beach. Created estimates for all
renovation work, supervised 3 contractors simultaneously
FORSA Construction (Subsidiary of CBM Consulting)
In charge of estimating for all FORSA projects.
Colich Construction L.P. Torrance, CA (2002-2004)
Project Manager
Management of Private and Public Works projects from $650K to $16MM.
Specific duties include construction field management and interaction
between home office, owner and engineer, contract
administration/documentation, scheduling of crews and subcontractors, pay
applications, subcontractor management, project cost controls, analyze and
report current project financial status and cost to complete, attendance at
weekly construction meetings, field reporting/logs, submittals, request for
information, change order requests, change orders and effective
communication between all parties involved on assigned projects. Estimated
projects valued over $3 million
Education
State University of New York at Binghamton, Binghamton, NY
BS in Accounting, May 2002
Center for Underground Infrastructure Research and Education
(CUIRE)
Completed the Inspector Training & Certification Program (ITCP) For the
Inspection of Cured-in-Place-Pipe (CIPP) Installations
Technical Skills:
Software - Expedition, MS Project, Word, Excel, PowerPoint, Publisher,
Adobe Acrobat & Photoshop