CURRICULUM VITAE

NAME: Mojtaba Darziani Azizi DATE OF BIRTH: 13 SEP1976

PROFESSION: Electrical Engineer

YEARS WITH FIRM: 11 NATIONALITY: Iranian

POSITION IN FIRM: Team Leader Electrical Engineer

PROPOSED POSITION ON TEAM: Senior Electrical Engineer

KEY QUALIFICATIONS:

Design, contract administration and site installation of electrical plant

for hydro, thermal power plant; petrochemical; refinery and natural gas

compressor station. Computer services including programming, data base

design and maintenance, data acquisition and control, systems design.

Calibration of instrument devices, preventive and corrective maintenance.

Loop checking of field devices to distributed control system (DCS), well

oriented in foundation field bus instrument, logic control/interlocking

(power & control) system. Familiar in all drawing and designing of

documents related to instrument functions such as: connection list, cause &

affect, safety matrix, P & ID, generator, excitation system and machine

performance tests. Familiar in protection relay: REG316 ABB, REL216 ABB,

MICOM, SEPAM, SIEMENS including test and setting calculation. Planning

scheduling and organization of electrical and instrument teams. Using the

MMS (maintenance management system) of works order development, design

engineering of power and instrument system.

Recent relevant assignments include:

Senior Electrical Engineer, Magwagwa hydro power plant,

February 2011 - Ongoing, Kenya

Team Leader Electrical Engineer, Tana hydro power plant,

October 2009 - January2011, Kenya

Team Leader Electrical Engineer, Jam gas compressor station,

March 2008 - September 2009, Iran

Team Leader Electrical Engineer, MES hydro power plant, (phase2) June

2007 - September 2008, Iran

Team Leader Electrical Engineer, Baniyas thermal power plant

June 2006 - May 2007, Syria

Team Leader Electrical Engineer, Karun 3 hydro power plant

September 2005 - May 2006, Iran

Senior Electrical Engineer, Aromatic 4, petrochemical plant

July 2002 - August 2005, Iran

Electrical Engineer, MES hydro power plant, (phase1)

February 2000 - June 2002, Iran

EDUCATION:

Bachelor of Engineering (Electrical), University of Water and Electricity,

Tehran 1999

Class 2

Professional Membership:

Graduate Member, Institution of Engineers, Iran

Other Training:

Aerial distribution workshop

Aerial transmission line workshop

Substation components workshop

Underground distribution workshop

EXPERIENCE RECORDS

FARAB, Hydro power plant main contractor; JKT, Petrochemical partnership

companies; Moshanir

September 2004 - Ongoing; July 2002 - August 2004; February 2000 - June

2002

Team Leader Electrical Engineer; Senior Electrical Engineer; Electrical

Engineer

Design, contract administration and site installation of electrical plant

for hydro, thermal power plant; petrochemical; refinery and natural gas

compressor station. Calibration of instrument devices, preventive and

corrective maintenance. Loop checking of field devices to distributed

control system (DCS). Familiar in all drawing and designing of documents

related to electrical and instrument function. generator, excitation system

and machine performance tests. Familiar in protection relay: REG316 ABB,

REL216 ABB, MICOM, SEPAM, SIEMENS including test and setting calculation.

Planning scheduling and organization of electrical and instrument teams.

Using the MMS (maintenance management system) of works order development,

design engineering of power and instrument system.

Magwagwa hydro power plant, Nairobi office, Kenya

Client: SMEC Intewrnational

Senior electrical and control engineer. Feasibility study and detail design

of the Magwagwa multipurpose dam and hydro power plant development project

on Sondu River. (February 2011- ongoing)

Tana hydro power plant, Sagana, Kenya

Client: Ken Gen

Team Leader Electrical and Control Engineer. Tana phase 2 is a new power

station design to produce up to 25 MW of power. And 2 substations: 66 KV

and 33 KV. Contract administration and site installation of electrical

plant: 2*32 MVA and 1*25 MVA step up transformer. Installation and

commissioning of 11 KV switchgear and 0.42 KV dry type transformer and LV

panels. Redesign drawings (Because of variances): circuit diagram, cable

connection, control I/O list, MV switchgear and diesel generator logic

diagram, DCS, generator auxiliary panels, interface between power station

and substation. Modification to auxiliaries and DCS panel. Conduct all

commissioning and machine performance tests. Loop checking of field devices

to control room and automatic start/stop test. (October 2009 - January

2011)

Jam gas compressor station, Iran

Client: Central locales oil

Team Leader Electrical and Control Engineer. Tender review and negotiation

of contract for phase 6,7 and 8 petrochemical plant. Installation of all

electrical and instrument devices for 4 units, SIEMENS turbine and

compressor: MV- LV switchgear and transformer, diesel generator adjustment

of PCV (pressure control valve), MOV (motorized valve), control valve or

actuator valve. Calibration of all instrument devices with analogue and

digital signals. Loop check and valve sequence check. Preparation of design

drawings (electrical and control systems) and test procedure. Including

calculation of protection parameters. (March 2008 - September 2009)

MES hydro power plant (Phase 2), Iran

Client: IWPC (Iran Water and Power Company)

Team Leader Electrical and Control Engineer. Review of tender documents and

drawings including redesigning of interface drawings and as-built design.

Installation, testing and commissioning of 4X 250 MW hydro power plant,

including 12 single phase step-up transformers (15.75KV/400KV) and SF6

400KV bus duct. Ppre-commissioning and commissioning of auxiliaries and LV-

MV systems. Loop check, signal check, logic and sequence check. Generator

and distribution line protection relay check. Generator and excitation

performance evaluation and machine efficiency tests. (June 2007 -

September 2008)

IWPC, Iran

Client: IWPC

Electrical Engineer. Preparation of tender documentation and contract

assessment and award of contract for the supply and installation of plant

and auxiliaries for 4X250 MW hydro power plant. (August 2007 - September

2008)

Banias steam power plant, Syria

Client: Ministry of Energy

Team Leader Electrical and Control Engineer. Planning, scheduling and

organization of electrical teams. Pre-commissioning and commissioning test

for all electrical, instrument and equipment including compliance with

technical specifications. Conduction of generator and excitation system

test, machine performance test and substation enerjization. (June 2006 -

May 2007)

Karun3 Dam and hydro power plant, Iran

Client: IWPC

Team Leader Electrical and Control Engineer. Review of tender documents and

drawings including redesigning of interface drawings and as-built design.

Installation, testing and commissioning of 8X 250 MW hydro power plant,

including 24 single phase step-up transformers (15.75KV/400KV) and SF6

400KV busduct. Ppre-commissioning and commissioning of auxiliaries and LV-

MV systems. Loop check, signal check, logic and sequence check. Generator

and distribution line protection relay check. Generator and excitation

performance evaluation and machine efficiency tests. (September 2005 - May

2006)

Aromatic 4 petrochemical plant. Iran

Client: Iran petrochemical company

Senior Electrical and Control Engineer. Installation and commissioning of 6

process zones for production of aromatic petrochemical material including

programming of control process. Loop checking of field devices to

distributed control system and function checks. Hart type instrument and

foundation fieldbus, conduction of functional tests of process

instrumentation and control devices. Sequence tests, logic

control/interlocking (power and control) system. Vendor assist for system

package test. Performed fault finding for various instrument devices.

Authorized to work in a hazardous area. (July 2002 - August 2005)

MES Hydro Power Plant (Phase 1), Iran.

Client: IWPC

Electrical Engineer. Consultancy services for installation and

commissioning of 4X250 MW hydro power plant. Site supervision for all

electrical and instrument equipment. Coordination of contractor to ensure

adherence to the contract document. Review of supplied equipment and

recommendation of areas of improvement. Supervision of commissioning of

electrical plant. (February 2000 - June 2002)

OVERSEAS ASSIGNMENTS

Syria, Kenya

LANGUAGES AND DEGREE OF PROFICIENCY

English: reading, writing and speaking - well

Persian: reading, writing and speaking - excellent

Date 3 June 2011

Signature of Staff Member

PAPERS

Effect of the fluctuation of the use of active and reactive power by

consumers on the network voltage. November 1999. Organized by the

university of Tehran, Iran.



Contact this candidate