William D’Angelo
*** ******* **. * Hendersonville, NC 28739 * 772-***-***** *********@*****.***
Construction Superintendent / Project Superintendent
Construction Superintendent with a 30+ year record of success overseeing all phases of multimillion dollar & Multi Family
commercial construction, County Capital Improvements, Military Installations, Schools, Hospitals, Hotel/ Apartment Renovations,
Condominiums, Student Dorms & large Structural Projects. Experience includes managing large crews of subcontractors in all
phases of ground up projects and a variety of other construction/demolition projects. Backed by strong credentials and a proven
history of on time, on budget (or below) with high quality project completions. I am willing to travel 100%.
Key Skills
Renovation / Demolition Projects Site Safety/ OSHA Compliance Budgeting & Cost Control
County Improvement Projects Heavy Equipment Operation Self Performed Supervision
Military Installation Projects Change Oder Management Subcontractor Supervision
Multi Family unit construction Heavy Concrete Background Heavy Civil Background
Employer Summary
Dot Construction Inc. (Beaufort,NC) Project Superintendent,6/11 to Present
Superintendent retained for several project’s located through out the southeast for United States Forest Service, Various Military Projects along with other
governmental entities.
Leland, NC)
D & G CONTRACTORS INC. ( Construction Superintendent,
5/10 TO 4/11
Retained to lead installation of new security gates, data communications systems & various other projects to fulfill multi government contracts at bases in
the Southeast. (Some information restricted.)
Asheville, NC)
WALKER CONTRACTING GROUP ( General Project Superintendent,
10/08 – 3/10
Managed all phases of pre construction site demolition & clearing of hazardous materials, including underground asbestos laden fuel tanks &
contaminated fill. Met & exceeded owner and client expectations through out.
Melbourne, FL)
M.H. WILLIAMS CONSTRUCTION GROUP, INC. ( Project Superintendent,
2/03 – 8/08
Provided site supervision on a diverse range of commercial construction, demolition, and multi family projects. Proven ability to run several projects
concurrently.
Project Highlights
Various unique Projects (6/11 to Present Budgets: $3M (Combined Projects)
Superintendent for military project located threw out the eastern United States
various smaller and unique projects located in the western North Carolina, Tennessee, Mississippi.
Military Entry Systems (5/2010 to 4/11) Budgets: $3.5M (Combined Projects)
Installed new entry systems, data communication systems as well as concrete barrier islands on multiple bases through out the Southeast.
Small Commercial, Tenant Build outs, & Retro fits (2008 to 2010) Budgets: $450K to $20M
Served as project/site manager for hazardous materials removal, demolition & clearing. Maintained site safety & managed multiple sub crews
during all phases up through installation of elevators & completion.
Commercial, Multi family, New Construction (2003 to 2008) Budgets: $750K to $25M
st nd rd
Led all phases of construction on custom multi family condominiums which included 1 & 2 floor parking as well as a 3 floor pool.
Managed phase 1 of new construction for Florida Institute of Technology with 3, five story student dorms, interior, exterior, utilities, landscaping
& parking.
Other Construction & Demolition Projects (1983 to 2003) Budgets: $500K to $30M
Completed diverse construction/demolition projects, including the ground up build of new firehouse, retro fit & new construction of hospitals,
schools, restaurants, and large superstores .Multi family units aprox. 450
Certifications
OSHA CERTIFIED 150 HOURS, 30 HOUR CERT #1738506
Hazmat
CPR/AED CERTIFIED (CONTROL # 153330)
Computer Proficient in Microsoft Office, Outlook, & Sure Trak,
State & Federal Background Checks
QC/QA Trained
Project History
6/11/2011 Present Dot Construction Inc. G.C. Superintendent
(Balsam Dam) Was in charge of replacing old spillway with a new mechanical system
(Mc Calls Cabin) With this project we completely reworked and reset all components of a 1858 Log Cabin from foundation to
new working fireplaces rebuilt period style doors and windows .
( ASOS) This project was for the Air National Guard which consisted of a New 5000sf Building and a 3500 sf demo and up grade
5/15/2010 4/7/2011 D& G Contractors Inc. Superintendent
Simmons AFB,NC Fort Belvoir, VA Fort Benning, GA Fort Polk, LA
Was in charge of construction on( 2) 3 story housing units with a total amount units for 125 for all jobs listed above and other security
project running concurrent
10/13/08 3/20/2010 Walker Contracting Group G. C. Superintendent
Walgreens... 2 story Walgreens is in Hendersonville, NC. Before the ground work began, 3 buildings on site needed to be cleared, 2 of
which were asbestos laden. They were disposed of per state requirements, as well as proper disposal of 2 1,000 gallon underground fuel
tanks and all contaminated fill, per EPA guidelines. After the site was cleared we removed 5 feet of fill and installed 239 timber piles,
reinstalled fill with 9" layers of ABC with 4 layers of geo grid. I then proceeded with the 15,000 sq. ft. 2 story building, with elevator. This
project had a budget of 3 million.
2/01/03 8/11/2008 M.H. Williams Construction Group, Inc. Project Superintendent
Pineapple House Condos... Located in Melbourne, FL, this 8 story condo complex has a 13.9 million dollar budget, 136 unit
condominiums with 1st & 2nd floor parking, as well as a 3rd floor pool. Each unit customized to buyers specifications.
Florida Institute of Technology (F.I.T Phase one includes three, five story student dorm rooms with all interior, exterior, utilities,
landscaping, and parking included. Project is budgeted at 21 M. 265 Units
Warehouse... with build out are new business offices, into which the owner will move his three companies to one location. Owner will also
be sub letting bays to other tenants. This project includes a second floor build, personal office build/design for owner, tenant build out,
underground utilities, landscaping, and parking lot. 55,000 sq. ft. tilt wall
10/04/99 01/13/03 Coast to Coast Forming Structural Superintendent
Riverside National Bank...Located in Port St. Lucie, Fl. This project was a 90,000 sq. ft. shell, budgeted at 1M, with elevator installation.
My part of this project was finished on time and on budget.
Office Building... The value of this project was $ 3M. This was a ground up 28,000 ft. office space in Boca Raton, Fl. After Certificate of
Occupancy, we proceeded in permitting of tenant build out. After this phase was completed we proceeded with build to suit office spaces
for incoming tenants.
Park Avenue BBQ Grill... located in Boynton Beach. Value of project was $950K. On this, as Superintendent, I had to gut and renovate
existing restaurant. This included new electric, plumbing, fire sprinkler systems, kitchen equipment install, coordinating and scheduling
subcontractors, along with owners' subcontractors.
4/25/93 9/15/99 Sikon (A division of Konover Properties) Superintendent
Shops of Salerno (Winn Dixie Located in Salerno, Fl. A budget of 6.7M. Completed on time.
Stuart Fine Foods…..Location Stuart, Fl., Job was budgeted for 5.9M.
Publix….3 Publix Superstores, entailing entire shell, structural steel and concrete. Wellesley
Inn one located in Plantation, and the other in North Miami. These were two five story ground up hotel buildings. I was the
Superintendent in charge of all aspects of project from lay out to end parking and landscape.
09/88 04/93 Janus & Hill Corporation Superintendent / Project Manager
Fire Station 18 This project in Jupiter, Fl., valued at $1.895M. On this project I performed dual roles as Superintendent & Project
Manager. The job was ground up and entailed my overseeing all aspects of construction from land clearing to Certificate of Occupancy.
Jerry Thomas Elem, Limestone Creek Elem, Lighthouse Cove Elem. The above listed schools are in Jupiter, Fl. Value of total HVAC
renovations was $1.35 M. As acting Superintendent, my duties included scheduling of all subcontractors, submittals, setting county and
engineering inspections, & seeing to Life Safety issues. Wellington H.S Crestwood Middle...Pahokee Jr.\Sr J.F.K. Middle
These schools are located in Palm Beach County, and were valued at $3.5M. These are classroom additions. I was acting Project
Manager working with the architect, as this was a "Design Build" project. Details of project include subs, submittals, pay requests, change
orders, & scheduling.
Composting complex Pembroke Pines, Fl. Composting & waste water treatment plant.
05/83 07/88 Centex Rogers Superintendent / Project Manager
Hollywood Memorial Hospital... Joe DiMaggio's Children's Cancer Center & Children's Rooftop Playground Cancer Center
was an existing office building we turned into living facilities for families with terminally ill children receiving treatment in Cancer Center. As
one of several Superintendents, I was in charge of overseeing all aspects of construction, which included scheduling, and subcontractors.
Value $4M. I was also Superintendent for the Rooftop Playground valued at $2.5 M.
Memorial Hospital West...NICU, Pediatric ER, Renovations to existing ER, New MRI Center, PICU, Women's Cancer Center,
New One Day Surgical Center, New Labs, New 100 Patient Bed Floor, Renovation to Existing Pharmacy, plus several others.
Total estimated value for I above listed projects $20M. Memorial Hospital, Pembroke Pines...As Superintendent / Project
Manager, I was one of the last to leave this project which included renovation to the entire 6th floor. Project included renovations to patient
rooms & updating interiors. Value was $5.1M.