VLADAN GAROVIC

Name Vladan Garovic

Date of Birth 18 February 1973

Marital Status

Address

Tel. number Married

S. Markovica 91/7, 34000 Kragujevac

+381*********- Serbia

+974********- Qatar

e-mail

Qualifications and Professional Institution Memberships umid3j@r.postjobfree.com

B. Sc.E.E

Technical Faculty

University of Kragujevac, Serbia

Present Lead Commissioning Engineer, Qatar

March 2009 ALSTOM GRID

Project Phase 8 KAHRAMAA, Qatar

Duties and responsibilities are summarised as follows:

• Lead Commissioning Engineer on the Phase VIII.

• Preparing documentations for testing, test reports, RAMS. Team leader of 10 Commissioning Engineers.

• Overall commissioning and testing on 66/11 kV, 132/66/11 kV and 220/66/11 kV GIS substations.

• Defect list clearance

February 2009

Commissioning Engineer, UK

January 2008 AREVA T&D

September 2008

January 2008

Project Grain 400/132 kV National Grid, UK:

Duties and responsibilities are summarised as follows:

• Electrical interlock, busbar protection and synchronisation on 2 bays extension to the existing AIS 400 kV substation (AREVA)

• Overall testing on 132 kV, GIS and 11 kV substation (SIEMENS)

• Primary testing REF on 132/11 kV transformer

• Relay testing for 132 kV, 11 kV feeders and transformer 132/11 kV.

Project NICAP Laleham 275 kV - Ealing 275 kV National Grid, UK

Duties and responsibilities are summarised as follows:

• Overall commissioning for implementing new numerical MESH corner and feeder protection on 4 MESH corners

• Primary injection test for MESH corner protection

• 415 V test shot on 275/132 kV transformer

• Secondary relay protection testing (MESH corner protection, transformer differential protection, REF, differential protection of 275 kV cable, shunt reactor protection, synchronization check). Relays P143, P142, P634, P842, P545 (AREVA); 7SD522 (SIEMENS), software’s MiCOM S1 and DIGSI 4. Primary injection test set CSU 600A and OMICRON CPC 100. OMICRON CMC 256-6. SVERKER 760.

Courses attended:

• CCNSG Safety Passport

• Competent Person Authorisation (National Grid)

• Basic Electrical Safety Competence – BESC (EUSR)

• Basic First Aid for Appointed Person (British Red Cross)

July 2007 Design engineer ,Belgium

May 2007 SIEMENS

Project :

Load shedding in Belgium power network, SIEMENS Belgium

Duties and responsibilities are summarised as follows:

• Preparation schematic for connection frequency relays in substation. Three 36 kV substations, five 70 kV, six 150 kV substations. Relay 7RW600 SIEMENS

March 2007 Commissioning engineer, Romania

November 2006 TOSHIBA

Project :

Brazi Vest 400/220/110 kV GIS, Romania. Supplied and installed by TOSHIBA

Duties and responsibilities are summarised as follows:

• Overall commissioning on 220kV side, wire checking, checking signals between LCP and station computers and SCADA

• Primary injection tests

• CT’s and VT’s tests

• Checking of complete wiring, commissioning and configuration of busbar protection GRB 100 TOSHIBA

• Checking of complete wiring and commissioning of the distance protection relays GRZ 100 TOSHIBA

• Checking of complete wiring and commissioning of the directional protection relays GRD 140 TOSHIBA

• Checking of complete wiring, commissioning transformer protection Siemens 7UT61

December 2007 Manager of department for maintenance HV substations and relay protection

May 2006 EPS, ELEKTROSUMADUJA Kragujevac, Company for Distribution Electrical Power, Serbia

Duties and responsibilities are summarised as follows:

• Coordinate works of two teams with 27 workers for maintenance HV and secondary equipment on seven 110/35 kV substations, thirteen 35/10 kV substations

• Preparing documentation and all necessary activities for annual maintenance substations

• Preparing documentation for tender

• Maintenance and testing station batteries and chargers

April 2006 Lead engineer for relay protection, secondary connection and measurements

October 1998 EPS, ELEKTROSUMADUJA Kragujevac, Company for Distribution Electrical Power, Serbia

Duties and responsibilities are summarised as follows:

• Reconstruction and commissioning relay protection in substation 110/35/10 kV and 110/10 kV

• Parameterisation and testing numerical relay protection 7SJ622 (SIEMENS)

• Primary and secondary testing protection relays in substations 110/35 kV, 110/10 kV and 35/10 kV

• Calculation, setting and testing of various type of protection relays

• Preparing documentation for tender

• Secondary circuits failures analysis and repairing

• Commissioning 35/10 kV metal-clad substation, with numerical relay protection supplied and install by SIEMENS