RESUME* POSITION SAUGHT – PROJECT MANAGER

NAME RAJIV CHAUDHARY

DATE OF BIRTH 12-11-1964

ADDRESS FOR

COMMUNICATION B-802, Sun Residency Complex Off Anand Mahal Rd, Adajan, Surat – 395 009, Gujarat M; 989-***-****.

PERMANENT RESIDENCE

ADDRESS 3, NARKESARY SOCIETY, JAYPRAKASHNAGAR, KHAMLA, NAGPUR-440025. (TEL:098********, 071*-*******)

E-MAIL ADDRESS s5b5mt@r.postjobfree.com

s5b5mt@r.postjobfree.com

PASSPORT NO F2821764

VALIDITY OF PASSPORT 17-10-2014

NATIONALITY INDIAN

MOTHER TOUNGE MARATHI

LANGUAGES KNOWN ENGLISH, HINDI, GUJARATI, MARATHI

PRACTICAL TRAINING • NAME OF CO: MAHINDRA & MAHINDRA LTD

• PERIOD: 15-06-1988 TO 15-07-1988

ELECTIVE SUBJECT MARKETING & SALES MANAGEMENT

SEMINARS DELIVERED • DR & KR PROCESSES

• MACHINE TOOL AUTOMATION

B.E. FINAL YR’S PROJECT DESIGN & FAB’N OF “PENTOGRAPH ENGRAVING M/C”

M.B.A. FINAL YR’S PROJECT “A STUDY OF INDUSTRIAL MARKETING STRATEGY”

EDUCATIONAL & PROFESSIONAL QUALIFICATIONS.

EXAM PASSED YEAR UNIVERSITY MARKS

B.E. (MECH) 1988-1989 AMARAVATI UNIVERSITY 60 %

M.B.A. (FINANCE) 1993-1994 NAGPUR UNIVERSITY 65 %

AUTOCAD-14 1997-1998 BRILLENT COMPUTERS, BHARUCH 78 %

ASNT LEVEL-II (RT) 2000-2001 MINT, SURAT 90 %

PRIMAVERA 2003-2003 - -

EXPERIENCE

ORGANISATION Period LOCATION DESIGNATION

JAHANPARS INTERNATIONAL 2009- 11- - PDO, Oman, QarnAlam Site Manager

ESSAR STEEL (DEC ENGG) 2008--09 Hazira SEZ , Surat, Gujarat, India Res. Const’n Mgr

SIEMENS (1165 MW SUGEN CCPP) 200*-**-**** MW Sugen CCPP Gujarat, India Mech. Consultant

NATIONAL CONTRACTING CO Lt 200*-**-**** MW Shoaiba Power Plant, KSA Project/Const’n Mgr

LAHOUD ENGG CO LTD 2002-03 Fujairah Water & Power Proj, UAE Site Mgr / Sr Site Eng’r

SIEMENS-POWER PLANT DIV 1997-01 655MW D/F CCPP,Paguthan, Guj,India Warranty/M Site Mgr

DALAL CONSULTANTS & ENGRS 1996-97 Mumbai, A’bad, Alibag Site Incharge/Sr SiteEng

SIEMENS-POWER PLANT DIV 1993-96 Comb. Cycle Power Plant, Uran Mech Site Manager

SIMPLEX GROUP OF INDUSTRIES 1989-92 BHILAI, ( M.P.) Project Engineer

STANFORD ENGG LTD 1988-89 DELHI Production Engineer

2009– 11 : QARNALAM POWER STATION PH-III (JAHANPARS INTERNATIONAL)

Worked as “ SITE MANAGER” with Jahanpars International LLC for their QAPS Ph-III Project installed Qarn Alam for PDO Oman

2008 – 2009 : 4.7 MTPA NEW STEEL MELTING PLANT - ESSAR STEEL LTD

Worked as “RESIDENT CONSTRUCTION MANAGER” with DEC Engg & Constructions Ltd & responsible for Execution of following projects at Essar Steel Ltd, hazira, surat, Gujarat. `

Installation of New Steel Melting Plant.

Piping Contract for new SMP

Interplant Piping Contract.

2007 – 08 : 1160 MW SUGEN COMBINED CYCLE POWER PLANT

(SIEMENS-AG, KWU, POWER GENERATION GROUP.)

Worked as Mechanical Consultant with Siemens & responsible for HRSG & BOP portion of Power Plant to ensure installation of Mechanical systems within scheduled timeframe.

2005 – 07 : 370*6 # 2220 MW SHOAIBA POWER PLANT SHOAIBA-KSA (ALSTOM )

(NATIONAL CONTRACTING CO LTD, KSA.)

Worked as “PROJECT MANAGER”/ CONSTRUCTION MANAGER” WITH A KSA BASED COMPANY FOR THEIR SUBCONTRACT AT 370 X 6 MW SHOAIBA POWER PLANT FOR “SAUDI ELECTRICITY CO. & INVOLVED IN FOLLOWING ACTIVITIES.

Planning & Execution of Erection activities w.r.t Master Schedule & schedule prepared based on available materials and fronts released & organize execution within budget.

Organizing Manpower & Supervising staff & other resources for different Erection Fronts.

Participating Weekly Meetings with Client/Consultant and organizing Erection activities accordingly depending upon priorities.

Organise & Co-orinate with QA/QC for inspection of completed systems & Test Packages

Co-ordinate, Organise & Perform various “Extra Works” requested by client and subsequent claim in monthly billing.

Releasing the systems for Pressure Testing and organizing necessary resources to perform.

Preparation of Method Statements and Erection Plans for installation of Heavy Equipments & organize necessary resources accordingly.

Preparation & Submission of “Weekly & Monthly Reports to Client & Proj. Management. Preparation of Weekly Schedule & Report to client and organize erection activities accordingly. .

Releasing the completed systems for Commissioning & Co-ordinate & Organise for Commissioning Assistance.

Co-ordinate with H.O. & Organize necessary resources for Mobilisation & demobilization.

Preparation of Erection Statement for Monthly Billing.

Handing over of Plant & Relevant Systems to Client.

2002 – 03 : 960 MW FUJIRAH DESALINATION & POWER PROJECT (GE)

(LAHOUD ENGINEERING CO LTD, DUBAI.)

Installation of 4 X 124 MW (GE Frame 9E) Duel Fuel Gas Turbines, Generators, Associated Equipments & Piping Systems like :

W/W Skid, Compressor Skid, FO Heater, Oil FW Skid, Jacking Oil Pump Skid.

CS, SS & Alloy Steel Piping Piping for Lub Oil System, Comp Air, CW, NG & Fuel Oil.

WORKED AS INCHARGE FOR ABOVE PROJECT (SUBCONTRACT) FROM JUNE-03 TO DEC-03.

1997 – 2K : 655 MW PAGUTHAN DUEL FUEL COMB CYCLE POWER PLANT

(SIEMENS-AG, KWU, POWER GENERATION GROUP.)

Initially involved in Installation of following Piping Systems

HP/LP STEAM PIPING – MAT: A-335-P22 / A106 GR-B

CONDENSATE PIPING - MAT: A106 GR-B / A106 GR-C

COOLING WATER PIPING – MAT: A53 GR-B (WITH INORTAL COATING)

HP/LP FEEDWATER PIPING - MAT: A106 GR-B / A106 GR-C.

ERECTION OF GAS TURBINES, STEAM TURBINE, CONDENSER, FEEDWATER TANK,

VARIOUS PUMP-MOTORS & VESSELS.PREPARATION OF SCHEDULES &

ARRANGEMENT OF RESOURCES LIKE NECESSARY TOOLS &

SKILLED/SEMISKILLED MANPOWER FOR EXECUTION OF JOBS.

WORKED AS INCHARGE OF MECHANICAL DEPT FROM DEC-98 TO MAR 2K & HAD BEEN RESPONSIBLE FOR ERECTION & MAINTENANCE OF VARIOUS MAIN & AUX SYSTEMS INCLUDING COMPLETION OF WARRANTY PERIOD & HANDING OVER THE PLANT TO CLIENT.

Other activities includes :

Qualifying welders as per ASME Section IX

Participating weekly meetings with client & consultant

Planning & Execution of jobs for major & minor shutdowns.

Preparation and Submission of weekly & monthly reports to Project Management, Preparation and submission of progress invoices to client and closing of site & handing over of plant to client.

( DALAL CONSULTANTS & ENGINEERS LTD, MUMBAI)

• CERAMIC TILES PLANT ( NITCO TILES LTD – ALIBAG )

Erection of prefabricated HSD & LDO Tanks, Propane Gas Bullet, Compressor, DG Set, & Chiller unit. Erection& Alignment of HSD/LDO & Service water Pumps.

Fabrication & Erection of Piping for Propane Gas, HSD, LDO, Raw water, Service Air & Compressed Air.

• DEFI PLANT ( HINDUSTAN LEVER LTD, MUMBAI )

Erection of Static Equipments like Tanks, Vessels, Blow Down Vessels and Rotating Equipments like Pumps, Mixers & Agitators.

Erection of Package systems like Thermic Fluid Heater, Condenser Reactor Stripper Separator, Air Drier and Climbing Film Evaporator.

Fabrication & Erection of Piping Systems involving materials :

ERW HEAVY / MEDIUM CLASS – IS 1239 / IS 3589

CARBON STEEL SEAMLESS – A106 GR-B

STAINLESS STEEL SEAMLESS – A312 TP304 / TP306

HASTELLOY – C-276 / ASTM B625

• LPG BOTTELING PLANT ( SHV ENERGY, SUPER GAS, A’BAD )

Fabrication & Erection of 2 Nos of Fire Water Tanks ( O 24 * 10.74 mtr, Erection of Prefabricated Bullet ( O 4 mtr * 24 mtr long), DG Set & Corrosel.

Fab’n & Erection of Piping for OF PIPING FOR LPG, Fire / Service Water and Compressor.

OTHER ACTIVITIES INCLUDE QUALIFYING WELDERS, PREPARATION OF DOCUMENTATION FOR ISO 9001, CERTIFICATION OF CONTRACTOR’S BILLS, HANDING OVER OF PLANT & SYSTEMS TO CLIENT.

1993 – 96 : 960 MW URAN COMB CYCLE POWER PLANT

(SIEMENS-AG, KWU, POWER GENERATION GROUP.)

Erection of Steam Turbine, Generator, Oil Resistant painting of Steam Turbine, Erection and Alignment of HP/LP Feed water Pumps

Fabrication & Erection of Feed water Piping ( A106 GR-B ), IBR Piping ( A335 – P22 ), Lub Oil Piping ( 15 MO3 ).

Fire Protection & Distribution Piping, CW, Condensate Piping, Installation of various Pumps.

Preparation of Tech Proposal for Modification of Cold Gas Flair (Dismantling & Reinstallation of O 409 * 25 mtr Stack) including 2.5 sq mtr RCC foundation, Strl supports and Stay wires.

Worked as In-charge of Mech Deptt and had been responsible for Maintenance of various Main & Aux Systems during Guarantee period.

SPECIFIC ( Shut-Down ) JOBS PERFORMED DURING WARRANTY PERIOD.

Overhauling / Maintenance of Gas Turbines, Pumps – Motors. ( Shut-Down Job )

Mech Seal replacement/Testing /Commissioning of Naptha Inj. Pump.(Shut-Down Job )

Rectification of defects found in GT, Diffuser & Diverter Damper. ( Shut-Down Job )

Installation of Nalco make Corrosion Monitoring System.

Modification / Replacement of leak Oil pumps in all GTs. ( Shut-Down Job )

Replacement of Pilot gas Rings in Combustion Chambers. ( Shut-Down Job )

Tech Modifications in Nox Red’n System in Combustion Chambers. ( Shut-Down Job )

Rectification of damaged Boiler Tubes in HRSG. ( Shut-Down Job )

Re-routing & Modification in Acid Dosing System.

Replacement of Mech Seals of Acid dosing Pumps.

On line sealing of LP Steam Piping to restrict leakage.

Maintenance work, Installation of Lyb Ring on Condensate Extraction Pump.

Replacement of CS piping by HDPE / FRP piping for DM water.

Replacement/Re-fixing damaged Seal Air Plates in Diverter Damper.(Shut-Down Job )

Cleaning of Condenser / Condenser Tubes. (Shutdown Job)

Rectification of defects found in Mixing Chambers like Welding of Cracks, Replacement of Ceramic Tiles etc. (Shut-Down Job)

Analysis, Execution & processing of Warranty Issues.

Handing over of Plant / Systems to Client.

WORKS PERFORMED ON GE (FRAME - 9E) GAS TURBINES.

Dismantling & Re-installation of Comb. Chamber Nozzles & Liners. (Shut-Down Job)

Replacement of hydraulic Actuator for IGV. (Shutdown Job)

Fixing of Identification Tags for GT components.

Removal & Re-installation of Fuel Oil Split Pump on GT. ( Shut-Down Job )

Implementation of various Tech Modifications on GTs. (Shut-Down Job)

Attending defects in Lube Oil System & Fuel Oil System. (Shut-Down Job)

1989-1992: SIMPLEX GROUP OF INDUSTRIES – BHILAI

COMPANY PROFILE:

Design & Manu. Of Mech Equipments for Steel/Power Plants & Turnkey Projects.

JOB PROFILE:

Worked as Project Engineer, Estimating/Marketing Engineer involving Projects :

LADLE REPAIR SHOP: ` BHILAI STEEL PLANT, BHILAI

CONTINEOUS CASTING PLANT: ` ROURKELA STEEL PLANT, ROURKELA

SINTERING PLANT: ` ROURKELA STEEL PLANT, ROURKELA

SLAG GRANULATION PLANT: `BOKARO STEEL PLANT, BOKARO

Co-ordination with Manufacturers / Suppliers to finalize Tech Specifications.

Preparation of Proposals for supply & Installation to suit site conditions.

Preparation of Techno-Commercial offers for various Mech. Equipments involving CI & CS Castings, Forgings, and Technological Fabrications & Turnkey Projects:

Various items of CI Castings like Pallets, Wheels etc, weighing 30 T single pieces.

Various items of CS Castings like Gear Wheels etc, weighing 16 T single pieces.

Various Forged & Machined items like Crane Wheels, Rail Wheels etc.

Precision Machined items, Technological Fabrications like Pressure Vessels etc.

Erection & Alignment of Equipments / Pump-Motors for Systems:

Fire Protection System : Erection of Pump-motors & Piping (IS 1239/IS 3589 )

Compressed Air System : Erection of Comp., Service Air & Inst Air Piping.

Cranes / Lifting Equipments : Erection of EOT Cranes & Lifting Hoists.

OTHER ACTIVITIES:

Participating Techno-Commercial Meetings with Client.

Preparation of Tender Documents.

Follow-up of Project Activities as per schedule.

Marketing Activities like Advertising, Registration with Client.

Marketing Research.

1988-89 : STANFORD ENGINEERING LIMITED – DELHI.

COMPANY PROFILE :

Manufacture & Supply of Tower Cranes in Collabration with ‘Minato’, France.

JOB PROFILE :

Detail Scheduling for Manufacturing & Assembly of Tower Crane.

To Check & Release Crane Components for Assembly of Tower Crane.

Preparation of ‘Bill of Materials’ & Inventory Control.

Assembly, Testing & Commissioning of Tower Cranes.



Contact this candidate