Post Job Free
Sign in

Engineer Project Manager

Location:
Kollam, Kerala, India
Posted:
August 18, 2020

Contact this candidate

Resume:

CURRICULUM VITAE

OBJECTIVE

In quest of an inspiring opportunity as an INSTRUMENTATION ENGINEER with 11+ years’ Experience in various jobs, Field Engineering, design, construction, calibration and commissioning of different type of electronic and pneumatic instruments.

Educational Qualification

Bachelor of Technology in Applied Electronics and Instrumentation from Calicut University, Kerala, India

EXPERIENCE PROFILE

Company : JGC (KNPC CF PROJECT, Kuwait)

Duration : October 2019 to March 2020

Position : Instrument Engineer

Duties & Responsibilities

Coordinating with client for various issues.

As built drawing review from vendor.

Punch closing related to engineering issues.

Participate in commissioning and start up activities.

Vendor coordination for various field instruments.

Company : JGC (GIZAN PROJECT, KSA)

Duration : February 2017 to April 2019

Position : Instrument Engineer

Duties & Responsibilities

Verification of instruments and material that arrived on site.

Coordinating with client, construction and sub-contractor for various issues.

Did Radio Frequency survey for Steam Trap Monitoring System.

Participate in Site Acceptance Test for DCS system.

Participate in Site Acceptance Test and Commissioning for Fire Alarm System.

Participate in Site Acceptance Test for Steam Trap Monitoring System.

Participate in Site Acceptance Test for Corrosion Monitoring System.

Coordinating with QC department for engineering clarifications.

Coordinating with vendors for material related issues.

Company : JGC (YAMAL PROJECT, CPOE YARD, CHINA)

Duration : September 2015 to July 2016

Position : Lead Instrument Engineer

Duties & Responsibilities

Field change sheet preparation and issuing to sub-contractor, due to design changes at the time of construction.

Give approval for the shop design drawing prepared by the sub-contractor.

Verification of instruments and material that arrived on site.

Issuing site instructions to sub-contractor.

Coordinating with client, construction and sub-contractor for various issues.

Replying site queries and technical queries reports to sub-contractor.

Ship loose items list preparation.

Job card preparation for carry over works from yard to site.

Check estimate preparation.

Company : JGC (ICHTHYS PROJECT, COOEC YARD, CHINA)

Duration : August 2013 to May 2015

Position : Instrument Engineer

Duties & Responsibilities

Field change sheet preparation and issuing to sub-contractor, due to the design changes at the time of construction.

3D model (Navisworks) reviewing

Give approval for the shop design drawing prepared by the sub-contractor.

Verification of instruments and material that arrived on site.

Issuing site instructions to sub-contractor.

Coordinating with client, construction and sub-contractor for various issues.

Preparing reply for site query and technical query reports to sub-contractor.

Ship loose items list preparation.

Conducting mock up tests and prepares reports for the management.

Company : TECNIMONT (Habshan-5 IGD project (GASCO)

Duration : December 2011 to February 2013

Position : Instrument Supervisor.

Duties & Responsibilities

Supervising the field activities.

Participating field inspections.

Coordinating with engineering team and sub-contractor for field related quarries.

Scheduling and supervising the subcontractor jobs.

Progress reporting to the Discipline Superintendent.

Attending the Weekly, Monthly progress meeting with Client, Vendor and Subcontractor.

Witnessed instrument bench calibration and field calibration.

Witnessed valve calibration and leak test in vendor work shop.

Reviewing the as built documents submitted by the contractor.

Done valve assembly activities with vendor.

Witnessed TSO and PSV valve testing.

Planning, Controlling, and monitoring the site work efficiently.

Approval of construction modifications, drawings and checking material quantities, types and suitability. Getting the work done by the contractor as per the scope of work & standard of project procedures.

Company : SAUDI KAYAN

Duration : April 2010 to August 2011

Position : Instrument engineer

Duties & Responsibilities

Participate in commissioning and start up activities.

Familiar with functional test for instrument and electrical loops.

Witness loop check for instrument and electrical loops.

Trouble shooting of different instrument loop.

Verify the installation of instrument as per P & ID and hook up drawings

Perform Punch killing activities.

Witnessing bench and field calibration of different instrument.

Verification of drawings submitted by the EPC contractor.

Company : YANSAB (AKER KVAERNER GULF LIMITED. PE, PP and HDPE)

Duration : March 2008 to January 2010

Position : Instrument QC / Loop check coordinator

Duties & Responsibilities

Inspection of Installation of Various Process Control Instruments according To P&IDS, Hook up Drawings and Location Drawings

Loop folder inspection and preparation of documents.

Witness Calibration of Various Electronic/Pneumatic Instruments & Verify Against Specification/Data Sheet

Witness on Leak Test of Instruments Air Headers Air Sub-Headers and Pneumatic signal Lines

Witness of Pressure safety Valve Testing & Preparation of Documents

Insulation Resistance Test of Instrument Cables and installation of Instrument Cables, Installation of Marshaling Cabinets, Consoles, Control Panels, Local Control panels, Analyzer and Junction Box.

Preparation of Documents/Drawings and material inspection

Preparation of Calibration certificate and instrument loop check record.

Calibration of instruments as per field parameters using HART communicator, Micro-calibrator, Temperature & Pressure calibrator and Simulator.

Calibration and repair of control valves, ON/ OFF valves including Pneumatic and

Familiar with Yokogawa control system (centum 3000)

Worked in fire and gas system (dragger)

Company : SHARQ (Eastern petrochemicals)

Position : Instrument Engineer

Duration : NOV 2007 TO FEB 2008

Duties & Responsibilities

Working on various control systems and instrumentation worked include monitoring of instruments control panel and necessary actions upon generation status report of recorders and controllers.

Assisted calibration of field of instruments.

Implementation of instrumentation standard prior on the operation manuals, design and schematic diagram/drawings.

Reviewing and finalized all daily reports, work schedules, requirements need such as manpower and equipment on the job site.

Troubleshooting and Maintenance of different Computers & Its Peripheral Devices.

Updating and Preparation for instrumentation drawings Such as ILD, interconnection Drawings,Equipment layouts, Cause and effect, wiring diagram etc.

Worked in PEMTO and RAMIS software for spare parts management.

Company : ARRAZI.

Position : Instrument Engineer

Duration : June 2007 to Nov 2007

Duties & Responsibilities

Responsible for the commissioning, maintenance & calibration of all instrumentation apparatus.

Experienced in Loop checking activities

Installation of instrument as per diagram /instrument control room work/cable termination etc.

Loop checking and documentation instrument calibration pressure transmitter, pressure gauge, temperature gauge, pressure transits

Modem electronics, control cables instrument tubing and instrument process tubing.

Good knowledge about various preventive and corrective maintenance procedures

Company : TASNEE

Position : Instrument Engineer

Duration : Feb 2007 to May 2007

Duties & Responsibilities

Installation of different field instruments as per location drawing and P&ID

Bench calibration

Installation of primary and secondary trays.

Termination of different field instruments.

Field calibration of different pneumatic and electronic instruments.

Coordinating with engineering team for Technical queries & clarifications.

Coordinating with Procurement department regarding delivery of purchased items.

Personal Details.

Date of Birth : 30 December 1983

Marital Status : Married

Nationality : Indian

Passport Number : N 1719097 (Valid up to 09 May 2025)

Linguistic Proficiency : English, Hindi, Tamil & Malayalam

Permanent Address : Tharangini; Kuzhimathicadu (PO)

Kollam; India (691509)

References:

1.AKIRA NAKASHIMA

Field Engineering Manager (JKC Ichythys Project, COOEC Yard, China)

Email: *********.*@***.***

2.COLIN FISHER

Contract Manager / EPC Yard Representative (JKC Ichythys Project, COOEC Yard, China)

Email: **********@*****.**.**

3.Dwayne William Barnard

Pre-commissioning Manager (JKC Ichythys Project, COOEC Yard, China)

Email: *************@*****.**

4.RAY BISLEY

Project Manager (YANSAB – AKSI, KSA)

Email: ***.******@*************.**

I hereby declare that the above information is correct to the best of my knowledge and belief.

KIRAN PILLAI

KIRAN PILLAI

INSTRUMENTATION ENGINEER

MOB: +919********* (India)

***************@*****.***



Contact this candidate