Christopher R. Good
*** ********* *****, ***** *****, CA 95051 **********@*****.*** 408-***-****
PROFESSIONAL EXPERIENCE
McAfee, Inc, Santa Clara, CA 2011-Present
Global Project Manager
Managed (16) projects, totaling 690,000 square feet of office expansions, relocations, remodels and upgrades in North American, LTAM , EMEA and AsiaPAC geographic areas for a total of 67 million dollars.
Core member of team that managed 420,000 square feet of Real Estate acquisition for expansions and relocations including site selection, lease negotiations and terminations.
Worked directly with building owners and property management staff to complete termination negotiations for (6) locations totaling 295,000 square feet, including restoration and property removal. Reduced restoration liability 84% for a savings of 12 million dollars.
Prepare FIT plans and design alternatives for global customer presentations using AutoCAD.
Manage architectural, engineering, telecom cabling, audio-visual, video-conferencing (PolyCom cart and integrator), furniture and security professionals, contractors, vendors and service providers during project design development, procurement, construction and installation cycles. Developed (3) tier infrastructure standards based on size of location and business unit activity.
Design IDF/Telco Room and Lab infrastructure including equipment racks, patch panels, Starline Buss, rack mounted/stand-alone UPS, PDU/CDU and hot-cold aisle A/C equipment systems.
Managed (5) projects that achieved Platinum, GOLD or Silver LEED certification through fundamental and enhanced commissioning process.
Managed migration of Facilities service module and Knowledge Management library from Infra service desk tool to Remedy BMC.
Stanford University, Palo Alto, CA 2010-2011
Project Engineer
Provided engineering design specifications to insure building code, health and safety, environmental, sustainability and Title 24 (energy conservation) compliance for 5 million square feet of undergraduate/graduate student housing and administrative office space expansion, relocation, remodel and upgrade projects.
Prepared conceptual project drawings for management review and approval using AutoCAD.
Provided new construction, alteration, remodel and repair project product, material and construction methodology requirements for project managers, architects, engineers and contractors in Student Housing and Sustainability, Capital Improvement Project and Maintenance organizations.
Managed fundamental commissioning process for (3) projects that achieved GOLD or Silver LEED certification.
Reviewed construction drawings, bid specifications and final submittal documents to develop construction, product and finish asset database.
Premier Construction and Remodeling, Cupertino, CA 2005-2010
Commercial and Residential Construction Director
Managed solar, MEP, commercial tenant improvement and data center projects.
Responsible for all underground utility, gas, water and sewer installations.
Primary contact for client, real estate agents, designers, architects, engineers and regulatory agency personnel.
Prepared RFP and RFQ packages and completed bid award process. Prepared conceptual estimates and budget packages for presentation to client, developed cost controls, forecasting updates and variance reporting for same. Developed and administered all government, subcontractor, service and vendor contracts.
Managed subcontractor activities, finalized process to pass all building inspections, completed punchlists and performed client walk-throughs at completion of projects.
Visa Inc., Foster City, CA 1989-2005
Senior Construction and Facilities Manager
Responsible for the day-to-day operational management of all aspects of the campus facilities to ensure service delivery meets performance and quality standards for 2.7 million square foot high-rise and mid-rise, class 1A-plus leased/owned commercial, data center and manufacturing space throughout the U.S.
Negotiated and managed new space acquisition, subleases, lease renewals, terminations and CAM/escalation schedules. Implemented and utilized lease administration and tracking software.
Completed commercial office space, Lab and Data Center expansion and relocation projects at Foster City (San Francisco) world headquarters and throughout the U.S. for a combined cost of 47 million dollars. Completed the first LEED certified project.
Managed space planning department that updated and published monthly floor plans, prepared project conceptual drawings and completed space allocation for annual Facilities charge back using AutoCAD.
Relocated 5000 employees over a 16 month period from leased space to newly built world headquarters.
Worked directly with building owners and property management staff to complete termination negotiations for (27) locations totaling 1.7 million square feet including restoration and property removal. Reduced restoration liability77% for a savings of 23 million dollars.
Provided primary contact with client to develop scope of work, cost estimates, design specifications, schedules and operation impact for all projects. Managed change order process throughout the projects.
Received Gold Star Award as Customer Service Manager of the Year in 2004.
Shell Oil Company, Exploration and Production, Long Beach, CA 1981-1989
Construction and Operations Manager (Offshore/Onshore)
Collaborated with client to identify project requirements and goals. Completed site assessments, developed project plans, cost estimates, completion schedules and risk management strategies.
Managed development of engineering design, construction drawings, bid specifications, and environmental impact reports. Confirmed approved subcontractor qualifications, completed RFP process and awarded contracts.
Responsible for tracking project schedule, controlling cost, maintaining project documentation and providing customer updates.
SUMMARY OF QUALIFICATIONS
Proficient in AutoCAD, AutoCAD LT, MS Project, Primavera, MS Power Point, Adobe Acrobat Pro, Adobe PhotoShop, Snag-it, Excel, MS Word, Outlook, Infra and Remedy BMC. Past or current member of IFMA, BOMA and ABE, AEE. Active CSL # 890051 - B1,C61-D41
EDUCATION
B.A., University of California at Santa Barbara
REFERENCES
Robert Horn, Technical Trades Manager, Stanford 650-***-****
Charles Dow, Engineering Manager, Envirospec, 925-***-****
John Breglio, Director of Architectural Services, Visa 650-***-****