SUMMARY
Twenty eight (**) years experience in Civil & Structural Engineering with focus in Project and Construction Management, Quality Management Systems, Operation & Field Engineering including HSE Safety System. Experienced in both onshore and offshore Facilities encompassing Structural Platforms, Oil & Gas Facilities, Petrochemical Plants, Infrastructure/ Industrial Projects, Aviation & Airport Facilities, Electrical Substation Buildings, Multi Storey High Rise Buildings, Transmission & Power Lines, Marine Works includes Breakwater, Jetties, Cofferdam & Spillway and all related Civil structures.
EXPERIENCE
Oct.2010 - Present WorleyParsons, P.O. Box 44169 - Abu Dhabi UAE
Sr. Civil/Structural Engineer, GASCO ASAB-3 PMC Project. Project included the Construction of New LP Booster Compressor Station and Debottlenecking of existing NGL Plants both on Green Field & Brown Field Areas. Encompassed installation of six Compressors, Gas Transfer Pipelines (9 Different lines on 15 Kms) and Associated Facilities including Substation Buildings and all above /underground external utilities.
Responsible for Project Management Consultant (PMC) for the Construction of all Civil & Structural Main Process LP Booster Station & NGL Facilities (Green & Brown Field Areas).
Carry out all on site operation, provide technical knowledge and recommendations in resolving any unforeseen conflicts in the plan and specifications.
Verifies, review and approved all Feed Documents, Transmittals, approved IFC Drawings, design analysis standard codes/specifications, vendors scope of works, project master plan schedule equipment and material approval request ( MAR).
Ensure that company standard specification & procedures are adhere during site execution up to handling over of the entire project.
Attend the weekly meeting with the Gasco Management & Contractor representatives to discuss the progress and updated the ongoing activities to be completed in a priority system.
Review all the Test Results for concrete test cubes, pile load test, rebars , soil investigation reports, survey data’s and other Civil Work reports prior to final approval.
Review and finalize Technical queries, change design scope, & additional variation order.
Work in line with company HSE safety policies and procedure, ensure that contractors have understood HSE procedures, incident injury free, rules & regulation and all work are incompliance during site execution.
Team Leader/member during shutdown activities (Tie-ins Piping ) @ ASAB-0 & 1.
Jan.08 – Aug. 2010 WorleyParsons, P.O. Box 44169 - Abu Dhabi UAE
Sr. Civil/Construction Engineer, ADGAS OAG-1 PMC Project. Project included the Construction of New Processing Facilities Booster Compressor Station for Associated Low Pressure Gases from ADMA/ADGAS Das Island to Habshan where NGL is recovered, including interconnecting piperacks and Offsite, Podium, Flare , Substation & Control Buildings and reclamation works along the shorelines area.
Responsible for Project Management Consultant (PMC) for the Construction of all Civil & Structural Main Process Booster Station & NGL Facilities (Offsite & Podium Areas).
Carry out all on site operation, provide technical knowledge and recommendations in resolving any unforeseen conflicts in the plan and specifications.
Verifies and reviewed all Feed Documents, approved IFC Drawings,change design scope, technical query, standard codes/specifications, vendors scope of works, project master plan schedule equipment and material approval request ( MAR).
Attend the weekly meeting with the Adgas Management & Contractor representatives to discuss the progress and updated the on going activities to be completed in a priority system.
Witnessing & Review all the Test Results for concrete test cubes, pile load test, rebars, soil investigation reports, survey data’s and other Civil Work reports prior to final approval.
Ensure implementation of incident injury free and approved safety procedures and guidelines were being followed at site.
During the absence of Construction Manager, I’ll take charge as Acting CM for the Construction Activities.
Nov.06 – Dec.07 Qatar Petroleum, P.O. Box 3212 - Doha Qatar
Sr. Construction Supervisor, RLIC CCWP System Phase II PMT Project. Project included the Construction of New Pumping Station, Receiving Basin & Outfall Structure, installation of 12 lines GRE Pipes sizes of 2650 up to 3450 mm dia.pipeline corridor including dredging & reclamation works for the construction of Break water(3 kms long), Substation, Switchgear and Control buildings.
Responsible for Project Management Team (PMT) for the Construction of all Civil & Structural Works for New Pumping Station & Outfall Structure.
Carry out all on site operation, provide technical knowledge and recommendations in resolving any unforeseen conflicts in the plan and specifications.
Verifies & review all approved drawings,standard codes,equipment & material specifications.
Attend the weekly meeting with the QP Management & Contractor representatives to discuss the progress and updated the on going activities to be completed in a priority system.
Witnessing & Review all the Test Results for concrete test cubes, pile load test, rebars, soil investigation reports, survey data’s and Inspection of Batching Plant.
Ensure implementation of the approved safety procedures and guidelines were being followed at site.
Sep.05 – Oct.06 Parsons/Fluor Daniel LCC, Atyrau Republic of Kazakhstan
A. Building Superintendent, Tengizchevroil Asset Development (SGP) PMT Project. Project included the Construction of Second Generation Project-Production Facilities (Upstream), including Pump Houses, Water Treatment Building, Substation Buildings (9 nos) Storage Tanks – for Crude, Sulphur & Oil & Gas, power and all external facilities.
Responsible for Project Management Team (PMT) for the Construction of all Civil & Structural Main Production Facilities (Upstream)
Carry out all on site operation, assess site activities and give recommendation to resolve any conflict on plans & specification.
Monitoring concreting works such as Storage tank foundation turbine & vessel fnd,& substation buildings.
Ensure that company standard specification & procedures are adhere during site execution.
Attend the weekly meeting with the Chevron Management(TCO) & Contractor representatives to discuss the progress and updated the on going activities to be completed in a priority system.
Monitoring & inspection of pre-assembled piperacks, installation of stickbuilt modules and platforms.
Ensure implementation of incident injury free and approved safety procedures and guidelines were being followed at site.
Feb.04 – Aug.05 Technip Coflexip, P.O.Box. 1322- Safat, State of Kuwait
Sr. Civil Engineer,Vacuum Re-run Revamp ,(Unit-13) KNOC Project, EPC Project. Project included the Construction of Mina Abdullah Refinery –Unit-13 for re- vamping including Substation Buildings (B-122) Structural Piperack Train 1 & 2, Elevated Platform and OBSL external Facilities (Tank Farm).
Responsible for the Construction, Installation & Re-vamping of Unit-13 for Train 1 & 2.
Coordinate with the Client KNOC and Subcontractor for the contractual requirement of reinforced concrete Elevated Exchanger Platform.
Monitoring concreting works activities such cast in situ substructure and erection of precast superstructure.
Supervise the rerouting of existing underground pipelines and widening of existing electrical lines inside the battery limit on the operational refinery.
Responsible for the installation of 5 kms pipeline corridor from OBSL to Tank Farm and the construction package for Substation Building.
Prepare progress report including work permits and other related civil works for safety requirements of the project itself.
Mar.02 –Jan.04 Qatar Petroleum, P.O. Box 3212 - Doha Qatar
Sr. Construction Supervisor, RLIC CCWP System Phase I, PMT Project. Project included the Construction of New Pumping Station ,Receiving Basin & Outfall Structure, installation of 7 lines GRE Pipes sizes of 2650 up to 2850 mm dia. pipeline corridor including the construction of Substation, Switchgear and Control buildings.
Responsible for Project Management Team (PMT) for the Construction of all Civil & Structural Works for New Pumping Station & Outfall Structure.
Carry out all on site operation, provide technical knowledge and recommendations in resolving any unforeseen conflicts in the plan and specifications.
Verifies & review all approved drawings,standard codes, equipment and material specifications..
Attend the weekly meeting with the QP Management & Contractor representatives to discuss the progress and updated the on going activities to be completed in a priority system.
Witnessing & Review all the Test Results for concrete test cubes, pile load test, rebars, soil investigation reports, survey data’s and Inspection of Batching Plant.
Ensure implementation of the approved safety procedures and guidelines were being followed at site.
Feb.01 –Mar.02 Saipem ENI, Aksai District Western Province, Republic of Kazakhstan
Sr. QA/QC Engineer, Karachaganak Production Facilities –Unit-2, EPC Project. Project included the Construction of New Production Facilities- Unit-2, including the construction of Pipeline corridor, Main Substation building and Main Manifold structure.
Monitoring & inspection of all Civil, Structural and Piping works being carried out on site.
Checked & review project drawing, P&IDs ,specs, progress of work on site including consumables items and delivery of materials prior to issue for usage.
Verifies and review all approved drawings, standard codes, vendors scope of works, equipment and material specs.
Review weekly/monthly non conformance reports & implementing revision procedures for preventing recurrence.
Witnessing & Review all the Test Results for concrete test cubes, pile load test, rebars, soil investigation reports, survey data’s and Inspection of Batching Plant.
Review & compilation of all Quality records, quality plan & procedures, material receiving reports ,ITPs, NCR/CARS and as built drawing.
Feb.00 –Feb.01 GAMA ARABIA LTD, P.O. Box 20814, Al Khobar, K.S. A.
Sr. QA/QC Engineer, Hawiyah Gas Plant –Saudi Aramco Project, EPC Project. Project included the Construction of Sulphur Recovery Unit/ underground utilities, including the construction of Main Substation building and Structural Piperacks.
Monitoring & inspection of all Civil, Structural and Piping works being carried out on site.
Checked & review project drawing, P&IDs ,specs, progress of work on site including consumables items and delivery of materials prior to issue for usage.
Verifies and review all approved drawings, standard codes, vendors scope of works, equipment and material specs.
Review weekly/monthly non conformance reports & implementing revision procedures for preventing recurrence.
Review & compilation of all Quality records, quality plan & procedures, material receiving reports ,ITPs, NCR/CARS and as built drawing.
Nov.98 –Dec.99 Zakhem International Const. Ltd., P.O. Box 5728, Doha Qatar
QA/QCTeam Leader/Site Rep, Replacement of Khuff Gas Pipeline-QP Project, EPC Project. Project included the Replacement of 30” & 16 “ khuff gas pipeline corridor from point K to point N, including the construction of Substation building and Control Station.
Team Leader/Site Representative for QC Dept. for the implementation of Quality Management System.
Checking & verification of all Quality Plan, Procedures, Method Statement, ITPs, & all related Quality Records that are being implemented on the project.
Verifies and review all approved drawings, standard codes, vendors scope of works, equipment and material specs.
Report directly to the QA/QC Manager to discuss & submit the weekly/monthly quality reports within site construction area.
Attend weekly meeting with top management, discuss and update the quality reports and resolve outstanding quality issues such as NCRs,CARs and develop new method to improved the quality system
Review & compilation of all Quality records, quality plan & procedures, material receiving reports ,ITPs, NCR/CARS and as built drawing.
Nov.96 –Apr.98 KTA Tenaga SDN BHD, P.O. Box 11677, Kuala Lumpur, Malaysia
QA/QCSite Manager, KL International Airport KLIAB Project , PMT Project. Project included the Construction of KLIA Electrical Reticulation Project ( 33/11 KV ) Substation Buildings, Switchgear & Control Station including Power Line Systems (Package – 9).
Site Civil QA/QC Manager for QC Department for implementation of Quality Management System for KLIA ( 33 & 11 KV) Substation Buildings.
Checked & review project drawing, P&IDs ,specs, progress of work on site including consumables items and delivery of materials prior to issue for usage.
Verifies and review all approved drawings, standard codes, vendors scope of works, equipment and material specs.
Conduct training, perform internal quality audit program in conformity with client requirement for the project
Ensure that company standard specification & quality procedures are adhere during site execution.
Review & compilation of all Quality records, quality plan & procedures, material receiving reports ,ITPs, NCR/CARS and as built drawing.
Sep.95 –Sep.96 Dumez/GTM International Co, P.O. Box 48, Jurong , Singapore
Civil Engineer , Tuas Checkpoint Causeway Project , EPC Project. Project included the Construction of Administration Building including heavy earthmoving, reclamation works, piling foundations, Structural Terminal, Taxiway & Taxilane & External Utilities.
Aug.93 –Aug.95 Guam Construction Co. P.O. Box 23085, Tamuning Guam, U.S.A GMF 96921
Civil Engineer, Guam International Airport Project, EPC Project. Project included the Construction of Terminal Building (Extension/Renovation- Steel Structure), including National Historical Park-ASAN Overlook,Asphalt Roads, Bridges and Photo Town Building.
Sep.91 –Mar.93 KETTANEH BROTHERS Co., PO Box 383, Al Khobar, KSA.
Planner/ Civil Engineer, Saudi Aramco Aviation Facilities (KFIA) , EPC Project. Project included the Construction of KFIA- Saudi Aramco Airport Terminal Building- Main Hangar Structural Building, Operation & External Utilities.
Feb.87 –Jan.91 Abdullah Mosleh Organization, PO Box 2509, Jeddah, KSA.
Civil/Project Engineer, Gulf Cooperation Council HQ., EPC Project. Project included the Construction of GCC Building, Alpha/Yamamah Palaces (King Fahd/Prince Abdullah Residence), Kuwait Embassy Staff Houses, King Fahd University (KAAU-PCFHospital Building ),SPIMACO-Pharmaceutical Plant
Jul.84 –Jul.86 Brown & Root Company Ltd. PO Box 780, Manama, Bahrain
Field/Structural Engineer, Aramco Onshore/Offshore ZADCO Project, EPC Project. Project included the Fabrication & Installation@ onshore/offshore Structural Jacket,Decking,Platform,Bridges&Hook-ups
Aug.82 –Jun.84 Asta Development Corporation, Greenhills, San Juan, MM. Philippines
Civil Engineer , UCI. Ajinomoto Administration Building Project, EPC Project. Project included the Construction of Administration Multi Storey High Rise Building, Liberty Townhouses Pointe
EDUCATION
Bachelor of Science in Civil Engineering – Central Colleges of the Phils. – 1981(graduate)
Bachelor of Science in Mechanical Eng’g.- National University – 1982 (undergraduate)
Basic Autocadd 2000 - Arkicadd Computer Center – 2004
STAAD –PRO - MicroCadd Philippines
REGISTRATIONS/AFFILIATIONS
Registered Civil Engineer – License no. 25648 – PRC – 12/07/1981
Philippine Institute of Civil Engineer (PICE) - Member
Astoria Hotel/Club – Member(Gold)
A/Club Loyalty Program – Member (Classic)
Etihad Guest (Etihad Airline) – Member(Silver)
Best Site Engineer - A. Mosleh Organization (1989)
Sterling/Appreciation Award - Parsons Fluor Daniel (2006)
SPECIFIC TECHNICAL EXPERTISE/SPECIALIST COURSES
TECHNICAL SKILLS:
Scheduler /Planner – Primavera
Quantity Surveyor/Estimator
SEMINARS & TRAINING ATTENDED:
Basic Scheduling Techniques (Aramco) - Dammam, KSA. (1991)
Workshop in Internal Quality Auditing (KLIAB) - K.L. Malaysia (1997)
Welding Inspection Seminar (TWI) - Al Khobar, KSA. (2001)
H2S Safety Orientation Seminar (QP) - Doha, Qatar (2002)
Incident/Injury Free Workshop (Fluor) - Kazakhstan (2006)
Safety Work Permit (QP) - Doha, Qatar (2007)
Advance Safety Audit (ADGAS) - Abu Dhabi,UAE (2008)
Safety Orientation Seminar(ADGAS) - Abu Dhabi UAE (2010)
Permit To Work-PTW (GASCO) - Abu Dhabi UAE (2011)
HSE Culture Change Seminar (GASCO) - Abu Dhabi UAE (2011)
Authorization To Work-ATW (GASCO) - Abu Dhabi UAE (2012)
PERSONAL DATA:
Date Birth : December 14, 1959
Place Birth : Kalayaan, Laguna
Status : Married
Address : No 8 Zoraida St, Urduja Village Novaliches Quezon City, Philippines
Tel. Nos. : +63-928******* ( Philippines )
: +971-********* ( Abu Dhabi )
Nationality : Filipino
Passport No. : XX 5611747
Place Issue : Abu Dhabi, UAE.
Expiry Date : February 24, 2015
Driver’s License : Abu Dhabi/ Qatar/ Saudi License
E mail Address : *******.*****@*************.***
: ***************@*****.***