SUMMARY: Over 20 + years of experience and advanced knowledge specializing in the Engineering and Construction of Power Plants. Twenty five (25) years has been devoted to supervision. Heavy experience in shut downs & start-up projects, plant maintenance, rebuild and installation of process equipment, installing gas compressor, gas pipeline

for power plant natural gas, #2 fuel oil systems, high pressure, medium pressure systems and relocation of plants, setting and alignment of all types of equipment

and heavy in construction and maintenance activity scheduling Primavera P3 & P6.

ACTIVITIES: Corporate Management, Project Management, International Project Management,

Millwright, Foreman, Rigging, Superintendent, Human Resource management, Sub-

Contractors, Scheduling, Procurement, Cost control, Client interface, and setting

up PM programs and CP programs for gas turbines.

PROJECTS: Electrical Power Generation facilities, Fossil Fuel, Co-Generation Plants, Gas Turbines, Steam Turbines, Nuclear, OSB Mills, Petro-Chemical Plants, Natural Gas

and #2 Fuel system to power plants.

EDUCATION: San Diego State University – Bachelor of Science, Mechanical Engineering

PROFESSIONAL: OSHA Supervisor Training, CAL-OSHA Training, Industrial Relations Training, Dynamics of Modern Training, Millwright Technical School Instructor, IRD Mechanistic Trading, Computerized Heavy Rigging, Safety Programs, Red Cross, OSA HAZ-WAP I, II, & III, CPR & MSHA.

EMPLOYMENT: Various positions in the Construction/Power industry with the following:

- Signal International

-Wood Group Power Solutions

-Pro Energy Services Power Group

-Austin Industrial Power Group

-Austin Industrial Power/ Tech Services

-P.C.E. Constructors

-Burns & McDonnell Power Group

-RUST/NIC, Inc.

-Kellogg, Brown & Root (KBR)

-Siemens/Westinghouse Field Services

-Fluor/Daniel Power Group

-G.E. Power Group

DETAILED WORK HISTORY:

ROMA MC/SULZER TURBINE SERVICE Sept. 2010 to Jan. 2011

Central Termo Electrical Power Plant – Poza Rica, MX

Project Manager

Total refurbishment of 3 each 50 Mega watt G.E. Steam Turbines. Replace all piping H.P., I.P., and

L.P., piping coming from boiler to the turbines. Upgraded all control systems on turbine and replaced all control room equipment with Mark VI – A type.

SIGNAL INTERNATIONAL May 2010 – Sept. 2010

Citgo Gas/Oil Project – Orange, TX

SR. Project Engineer/Lead TA

Grass root project building (2) 7001FA Power Plant on barges, 120’ wide x 400’ long, to be sent to

Venezuela. Duties included over seeing all sub-contractors on site, working with engineering group

on all changes, and working with client on the turnover packages, punch lists and working with 4 QA/QC

people.

PROENERGY SERVICES, LLC Jan 2010 – May 2010

Sidor Power Plant, Puerto Ordaz, Venezuela

General Project Superintendent

Grass root power plant installing 2- LM6000 and 1- 7EA unit , all new B.O.P. system,

New switch gear yard, new black start generator backup system, and overseeing contractor, site

engineering issues & changes and all start up activities.

PROENERGY SERVICES, LLC/TECH SERVICES August 2009 – Jan . 2010

S.C.E. Peaker Project – Mira Loma, CA.

Senior Project Manager

Building 4 new control rooms & maintenance shops, upgrade on Data Highway Systems (2) new

retention ponds, 1.5 miles of road to sites, overseeing 11 sub-contractors, all start up activities and

working on schedule issues and engineering on field change orders.

AUSTIN INDUSTRIAL POWER September 2008- June 2009

CPS Power Plant – Elmendorf, TX

Senior Project Manager

Installing of 4- GE LM-6000 Units with SCR Sections, overall responsibility of total site project, scheduling, engineering issues, engineering upgrade, craft personnel, superintendents’ day to day activities, office personnel and all sub contractors, including 3rd party contractors. Constructed 2

miles of 16” new natural gas pipeline to the main plant including new metering station, branched off to filter stations going to 4 new Toromont gas compressors .

WOOD POWER GROUP SOLUTIONS October 2007-August 2008

Arizona Public Services – Yuma, AZ

Site Project Manager

Oversaw installation of (2) LM6000 Gas Turbine Units with SCR Section at existing power plant. Demo old foundations as needed, overseeing all site activities and 4 sub contractors. Constructed 12” natural gas pipeline for 2 new Toromont, 1.7 miles going from main line to new gas compressors, new metering station.

PRO ENERGY SERVICES POWER GROUP May 2007-September 2007

Los Angeles, CA

Senior Project Manager

Over installation & commissioning GE/AEP Southern California Edison of (4) LM6000 Gas Turbine units and all sub contractors activities. Constructed7 miles of 12” natural gas pipeline for 4 separate plant locations and new metering station.

PRO ENERGY SERVICES POWER GROUP February 2007-May 2007

LM6000 Power Plant – Tanzania, SA

Senior Project Manager

New grass roots power plant consisting of (3) TM 2500 units & (1) LM6000 classic unit, overseeing all craft people and sub contractors. Constructed 12” natural gas pipeline for 5 new gas turbine, 25 miles, new metering station and 1 1/2miles of 8” pipeline to the unit.

AUSTIN INDUSTRIAL POWER November 2005-January 2007

FMPA Unit #4 Stock Island – Key West, FL (GE Energy Services)

Senior Project Manager

Install a new LM60000NG Unit at the existing power plant. Demo all old foundations as needed. Rebuild all storm water ponds, install new foundation for fuel oil system and fuel oil piping. Updated all switchgear yard equipment. Overseeing all site craft activities, site engineering activities, start-up and all sub-contractors. Constructed 4.3 miles of pipeline to the power plant, for #2 fuel oil, for two new compressors, with 1.4 million gallon storage facility.

P.C.E. CONSTRUCTORS, INC. May 2005-November 2005

Desert Power – Rowley, UT

Senior Project Manager

Rebuilt 2 LM5000 Units, upgraded two 2 on 1 units. Installed new HRSG Unit, new 80 mega watt steam turbine unit, new control room, new cooling tower, and overseeing all craft, site engineering group, and all sub-contractors. Constructed new 8” natural gas pipeline as required for the two new gas compressors.

P.C.E. CONSTRUCTORS, INC. September 2003-April 2005

Valero Refinery – Ardmore, OK

20 MW Simple Cycle – GE Steam Turbine Unit

General Superintendent

A new Grass Roots 40 MEGA Watt simple cycle power plant consisting of (2) GE Steam Turbines, cooling tower, electrical sub-station, (2) new package boilers, site craft activities, and overseeing all sub-contractors. Constructed new 10” natural gas pipeline as required for the new gas compressor.

BURNS & MCDONNELL POWER GROUP April 2003-September 2003

Sugar Creek Power Plant – Terre Haute, IN

950 MW Combined Cycle

Project Superintendent

Oversaw revamp of two (2) 7FA GE Simple cycle Units to combine cycle units. Installation of two (2) new HRSG units, 210 MW GE D-11 steam turbine generator, overall site engineering items, sub-contractors, site security, & start-up activities. Installed 4 new gas compressors with necessary gas piping and equipment.

BURNS & MCDONNELL POWER GROUP January 2002-April 2003

Zealand Power & Light, Mirant Corp – Zealand, MI

Project Mechanical Superintendent

Oversaw installation of (2) 7FA GE Generator & Turbine, installing (2) simple cycle 7FA peaking plant. (2) two on one combined cycle 7FA supply to a 210 MW GE D-11 Steam Turbine, over start-up activities, total output of plant 975 MGW Base Load. Oversaw all office buildings, site landscaping & security systems for total site. Installed 4 new gas compressors with necessary gas piping and equipment.

BURNS & MCDONNELL POWER GROUP November 2001-January 2002

Louisiana Power & Light – Carville, LA

548MW Combined Cycle Unit

Start-Up Superintendent

Oversaw all start-up activities of Grass Roots Power Plant & 8 Sub-Contractors activities, scheduling

of day to day activities for start-up. Oversaw all office buildings, site landscaping, & security system for total site.

BURNS & MCDONNELL POWER GROUP July 2001-November 2001

Great River Energy – Dexter, MN

Start Up Project Manager

Oversaw all start-up activities of 425 MW Simple Cycle Unit. Set up maintenance program, setup vibration program, working with 5 sub-contractors to complete their contracts. Oversaw all office

buildings, site landscaping and Security system for total site. Constructed 10 miles natural gas pipeline to plant, installed 2 new gas compressors and associated equipment.

KELLOGG BROWN & ROOT August 2000-July 2001

Garland Power Plant – Nevada, TX (Grass Root unit)

(2) 78 MW700, GE Turbine & Generator

Site Superintendent

Responsibilities included overseeing all site activities, civil, electrical, piping, millwrights, ironworkers, & rigging. Prepared lift plans, worked with Engineering Department on site issues, interfaced with client, oversaw 4 sub-contractors, worked with GE Representative on daily activities & issues, helped set up the total site target schedule of activities and rebuild two steam turbine units. Total revamp of all offices, buildings, air condition system & total revamp of site security system.

KELLOGG BROWN & ROOT July 1998-August 2000

Chevron Chemical – Rock Springs, WY

Grass Root Acid Units

Area Superintendent

Oversaw all millwrights, pipe fitters, riggers & ironworkers. Worked with engineering on unit issues, upgrade on new equipment that needs more changes to meet unit needs and setting up all P.M. Programs, set up the vibrating analysis, routing program, & lubrication activities.

ADDITIONAL EMPLOYMENT: 1968-1998

RUST/NIC, INC

Del Tin O.S.B. Grass Roots

Title: Project Superintendent

American National Can

Title: Project Superintendent

Arco Chemical

Title: Area Superintendent

Henkel Corporation

Title: Project Superintendent

Stone container

Title: Area Superintendent

FLUOR/DANIEL

Tenaska Co-Generation Plant

280 MW Power Plant

Title: Area Project Superintendent

Campbell Soup Plant

280 MW Power Facility

Title: Area Project Superintendent

Box Crow Cement

Title: Area Superintendent

KELLOGG, BROWN, & ROOT

Gulf Oil Chemical

Title: Maintenance Superintendent

**While working for KBR Engineering, I was involved in 9 overseas projects and 15 state side projects.

All power plants have gas pipelines and gas compressors, let down stations, filtering system, and metering stations.



Contact this candidate