CONSTRUCTION EXPERIENCE

BERGLUND CONSTRUCTION COMPANY, Chicago, IL 5/8/00-1/16/09

Senior Project Manager 10/06-1/09

North Aurora Police Station, Start 9/08 -1/16/09

Preconstruction Planning for a 30,000sf building with a budget of $11,000,000

Holy Cross Hospital, ER Addition. Start 2/08-Complete. 1/30/09

Preconstruction Planning, with a GMP Project

6,000sf 13 beds, one story addition to the adjacent ER. $4,120,089

Holy Cross Hospital, MRI Addition Start 2/08-Complete 9/1/08

1,500sf MRI suite addition $1,142,979

Holy Cross Hospital, CT room build out 600sf Start 5/08-Complete 7/1/08 $205,000

Montgomery Village Hall, Start 6/07-Complete 10/1/08

23,511sf office building with a Village board meeting room $7,182,138

Deerfield Presbyterian Church, Start 2/07-Complete 6/1/08

Preconstruction Planning, with a GMP Project

18,000sf Worship center facility with classrooms in the basement $4,985,125

Project Manager 5/8/00-10/06

Park Center, Office Building, Long Grove, IL Start 10/06-Complete 5/10/08

Preconstruction Planning, with a GMP Project

Exterior remodel of a three story office building with new windows

and entrances. Building was occupied during construction $5,676,766

800 Commerce Office Building, Oakbrook, IL Start 9/10/06-Complete 4/30/07

GMP Project

Façade and entry upgrade, changed precast Façade to EIFS $3,128,921

3470 Lake Shore Drive, Chicago, IL Start 8/5/05-Complete 5/10/06

28 story Condo High Rise window replacement, $1,327,320

Hedrich Blessing, Office Building, Chicago, IL Start 11/05-Complete 8/15/06

Preconstruction Planning, with a GMP Project

11,000sf precast office building with a photography studio $2,021,805

Edward Hospital Cancer Center, Naperville, IL Start 3/04-Complete 4/10/05

35,000sf two story cancer center, addition to main Hospital $5,875,684

Northwestern University, Athletic Office Building, Start 2/9/04-Complete 6/10/05

Demolition of existing two story building and construction of the

new 32,700sf two story office building with wrestling practice facilities

in the basement $7,317,534

NU Practice Football Field, artificial turf Start 6/05-Complete 9/05 $750,000

NU ADA entry upgrades to three office buildings Start 5/04-Complete 11/04 $450,000

Augustana Lutheran Church, Hyde Park, IL. Start 8/10/04-Complete. 7/19/05

14,000sf two story addition, meeting rooms, offices, and a kitchen $1,490,000

University of Chicago & Chicago Hospital, Hyde Park, IL 3/15/02-6/2/03

Campus chilled water and steam pipe utility upgrade $ 6,000,000

Renovation, Six story Administration office building 25,000sf $ 2,500,000

Hospital renovation of laboratories 4,400sf $ 2,000,000

Hospital patient room upgrades $ 200,000

Cafeteria build out $ 300,000

Dixon Office Building, Chicago, IL Start 11/11/02-Complete 9/15/03

25,000sf three story precast building, office and retail space $ 2,100,000

St, Joseph School, Summit, IL Start 6/10/02-Complete 10/10/02

29,000sf school remodel and 600sf mechanical room addition $ 1,100,000

Louis A. Weiss Memorial Hospital, Chicago, IL Start 5/15/00-Complete 3/29/02

21,204sf three story hospital addition and 25,658sf of remodel of

existing space. New 12 bed ER and 10 ICU rooms. $ 10,382,274

MORSE DIESEL, Chicago, IL Assistant Project Manager 6/10/1996-5/1/2000

520 N. Michigan Avenue, Chicago, IL Start 7/16/1999-Resigned 5/1/2000

Exterior façade rehabilitation of a historic building with a new

construction of a 17 story building for retail and hotel. $ 76,000,000

Federal Courthouse, St. Louis, MO. Start 6/10/1996-Complete 7/15/1999

30 story courthouse, assistant project manager in the construction of the

building structure and was the assistant superintendent of the build out

of the 28 courtrooms $ 200,000,000

BOVIS LEND LEASE, Chicago, IL Assistant Project Manager 6/5/1994–6/1/1996

McDonald’s Corporation, Oakbrook, IL

Complete office remodel of the 20 story corporate headquarters $ 25,000,000

AREAS OF PROFICIENCY

OSHA Training 10 hours, Project Manager Software: Autodesk Constructware ® and

Viewpoint® Construction Software

Microsoft Office 2007® (including Word, Excel, Outlook, Project, PowerPoint)