JOHN SANGIOVANNI
PH: 732-***-****
EMAIL: **********@*****.***
PROJECT SUPERINTENDENT / ESTIMATOR- Pipe, Utility and Heavy Construction
Jogi Construction Inc. Edison, NJ 01/11-Present
______________________________________________________________________
- Managed 4.2 Million Jersey City Newark Ave. Streetscape Project
- Assisted in the management of County Bridge Projects
- Documented, identified and processed change orders
- Calculated quantities, maintained records of material deliveries, performed take offs,
- Interpreted project plans and specifications.
- Coordinated crews, subcontractors and equipment for multiple projects
- Conducted meetings regarding progress, subcontractors, project conditions
- Assembled and processed submittals for Engineers.
- Maintained and documented project As-Builts, kept detailed records of all project issues
- Performed estimates, take offs and project schedules
MILLING AND PAVING SUPERINTENDENT / ESTIMATOR-Road Reconstruction
Paving Materials and Construction, Roselle, NJ 07/09-01/11
- Managed NJDOT projects for milling and paving, roadway reconstruction, drainage and traffic
control and staging changes.
- Coordinated all laboratory coring, testing and documentation.
- Reviewed project Plans and specifications and coordinated with Surveyors and Engineers.
- Documented discrepancies in plans and notified parties if field changes where needed.
- Coordinated and scheduled all crews, equipment, subcontractors, trucking, and material.
- Maintained project schedules by increasing and decreasing crews utilizing an all union crews.
- Calculated and documented project quantities, performed take-offs, interpreted plans and
specifications,
- Documented, Communicated and Negotiated through RFIs, letters, prepared and calculated
change orders for quantity increases, changed conditions, project delays project closeout.
- Attended weekly project meetings regarding progress, subcontractors, project conditions.
- Estimated and assembled bid packages for NJDOT, County and Municipal Projects.
- Processed bids through Excel Program, Heavy Bid, and Traditional Methods.
PROJECT SUPERINTENDENT- Pipe, Utility and Site Construction
Group Contracting LLC, Cedar Grove, NJ, 4/07-05/09
––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
- Supervised a staff of 2 pipe crews, rock crushing, blasting and earthwork operations
(30+employees) on a $6.2 million project.
- Managed projects independently with minimal oversight
- Directed equipment repairs and maintenance with repair staff and CAT service on 24 pieces of equipment
- Documented project changes through As-Builts and recorded all change orders and extras
- Successfully recovered $400,000 in change orders and extras
- Participated in weekly client meetings regarding progress and coordination with other contractors on work site
- Coordinated plan changes with engineers based on field conditions
- Performed take-offs and buy-outs
- Directed and supervised all utility construction water, sewer, storm, electric
- Oversaw Multiple utility projects throughout NJ
JOHN SANGIOVANNI
PH: 732-***-****
EMAIL: **********@*****.***
PIPE / PAVING FOREMAN
Marvec Construction, Verona, NJ, 7/03-1/06
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
- Supervised multiple crews in the installation of storm, sewer and water systems.
- Oversaw the installation of sewer lift stations
- Executed pipe installations utilizing trenchless tunneling systems
- Performed and supervised pipe fusing for bursting and slip lining operations
- Performed road reconstruction operations including milling, paving, sub-base curb construction
- Worked closely with sub contractor, engineers, township, county and MUA officials on projects
- Pressure tested systems mandated by specs, engineers, and MUA officials
- Video inspected lines for MUA officials, pre-construction and post-construction
LABORERS LOCAL 472
Aberdeen, NJ, 4/94 -7/03
Contractors - Vollers, Marcellis Warner, Barbella Environmental, Mt Hope, Solarmite, Aspen
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
Bridge Construction – Excavation, abutment ,pier deck and parapet concrete construction
Pipe Projects – Water, Storm, Sewer , Electrical conduit,, Gas line construction, Valve insertions and wet taps
Land Fill – Leachate, collection and Methane extraction systems, Pipe Fusion ,Cell Construction, Capping
Traffic Control Projects – Garden State Parkway, NJDOT, (TCC Certification Rutgers)
Site Work Projects – Earthwork, On-site recycling, Grading, Environmental Remediation, Pipe and utility construction
QUALIFICATIONS EQUIPMENT
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
– NJ CDL Class A – PADI open water diver - Backhoe, Front End Loaders ,Excavators, Dozers
– NJ DOT TCC (current) – Commercial Diver experience - Extec E-7 screener & Extec C-12+ jaw crusher
– 80 OSHA Hazardous Materials – First Aid/CPR -Metso HP200 Loco Track 110 cone crusher
– 10 OSHA Worker – Confined Space -Terex Direct Drive jaw crusher
- Quarry stackers– End dumps