CURRICULUM VITAE
NAME: NILESH R. KAJABAJE
Mobile +91-704*******
Email Id :- *********@*****.***
*********@**********.***
https://www.linkedin.com/in/nilesh-kajabaje-393b01134
Education
Bachelor Degree in Mechanical Engineering. Percentage: 70%, JAN - 2010 to JAN -2013. Diploma in Mechanical Engineering.
Percentage: 52%, June – 1997 to AUGUST- 2000. HSC in SCIENCE [TECHNICAL].
Percentage: 50%, June – 1995 to June – 1997
Completed a 30-hour Occupational Safety and Health Training Course in Construction Safety & Health (OSHA).
Completed MSCIT (Course of Maharashtra Govt.) with 54 marks.
Relevant Experience Summary:
Sr.
No.
Designation
Duration
Company Name
Project
1
MECHANICAL ENGINEER
11/2023 TO TILL DATE
FREE LANCER
METAL STEEL PLANT
2
COMMISSIONING MECHNICIAL FOREMAN
10/2022 TO 10/2023
BECHTEL SAUDI ARBIA
RIYADH METRO PROJECT
3
FREELANCE
MECHANICAL ENGINEER
3/2020 TO 9/2022
WORK FROM HOME
JSW STEEL
4
COMMISSIONING SPECIALIST
(MECHANICAL)
10/2019 TO 2/2020
WORLEY PARSONS
CAIRN ENERGY
5
COMMISSIONING
ENGINEER
10/2018 TO 2/2019
GREENVILLE OIL
& GAS
GREENVILLE LNG
6
COMMISSIONING ENGINEER
06/2018 TO 08/2018
ROUGE PIPELINE SERVICES
KNPC/MAB-1
7
COMMISSIONING ENGINEER
10/2017 TO 11/2017
CAPE PLC
JORDAN
PHOSPHATE MINES CO
8
Sr. COMMISSIONING SUPERVISOR
06/2016 TO 06/2017
PETROFAC EMIRATES LLC
ORPIC
9
COMMISSIONING
SUPERVISOR
11/2014 TO 03/2015
JGC
BARZAN
10
MECHANICAL
SUPERVISOR
04/2014 TO 05/2014
ETS
QP BENZENE
11
COMMISSIONING ENGINEER
08/2012 TO 11/2013
SAMSUNG SAUDI ARABIA
MA’ADEN SMELTER
12
MECHANICAL SUPERVISOR
01/2012 TO 4/2012
DESCON ENGG
TAKREER
13
COMMISSIONING
SUPERVISOR
11/2010 TO 02/2011
TOYO JAPAN
ENGG
PERAL SHELL GTL
14
MCHANICAL SUPERVISOR
05/2010 TO 06/2010
TOCO
OMAN LNG
15
COMMISSIONING MECH TECHNICIAN
04/2009 TO 04/2010
SAUDI ARAMCO
KAUST
16
MECHANICAL SUPERVISOR
05/2008 TO 01/2009
LAHOUD ENGG
BOROUGE 1
17
MECHANICAL FOREMAN
10/2007 TO 11/2007
QCON
QAFCO
18
MECHANICAL
FOREMAN
08/2005 TO 08/2007
AL -OSAIS
MERCO
History:
[ 1Nov 2023 To Till Date] FREELANCER Position: FREELANCE MECHANICAL ENGINEER
Project: Steel plant
Hires and trains materials handlers.
Oversees the daily workflow and scheduling of the Materials Handling department. Conducts performance evaluations that are timely and constructive.
Handles discipline and termination of employees as needed and in accordance with company policy. Maintains inventory, which includes keeping records in an inventory management system, acquiring additional stock as required, and distributing items from stock to fulfil requisitions.
Ensures safe operation of equipment used to move and transport materials to and from the storage areas of the facility.
Oversee installation of new equipment. Develop testing protocols and perform and analyse tests to track results. Create and maintain reports and documentation to track project development and design process, and report progress to clients and management.
[ 6 NOV 2022 TO 15 October 2023] BECHTEL SAUDI ARABIAPosition: COMMISSIONING MECHANICL FOREMAN Project: RIYADH METRO MPROJECT
Oversee the receiving, storing, and organizing of materials, equipment, and supplies to ensure efficient workflow and space utilization. Develop and implement standard operating procedures (SOPs) and best practices for material handling and inventory management.
Carrying out commissioning, troubleshooting & servicing on HVAC equipment. Working with Design Engineers, site teams and liaising with customers when needed. Interfacing with Sensors and BMS for installations, servicing and maintenance.
Providing overall administrative and technical management on large, complex, or multiple construction project from initiation to final acceptance by client. Responsible for leading and overseeing the project; and guide the project team, manage, monitor and control the entire project in line ith the agreed specifications and complete within the approved timelines.
Overseeing and direct construction, engineering, technical and field installation of all Mechanical, Electrical, Plumbing (MEP) systems.
Developing and maintaining relationships with engineers, design consultants, subcontractors, suppliers, inspectors, and owner’s representatives to ensure alignment with client goals and expectations from initiation to completion of the project.
Comprehensive knowledge and understanding of the contract documents Overseeing daily activities of Engineer-MEP, and subordinates.
Managing MEP procurement, project budgets, quality, safety, engineering, coordination, scheduling, installation, commissioning, and close-out processes.
[ 5 MARCH 2020 To 25 OCT 2022] FREELANCER Position: FREELANCE MECHANICAL ENGINEER Project: JSW STEEL, DOLVI, PHASE-2
Hires and trains materials handlers.
Oversees the daily workflow and scheduling of the Materials Handling department.
Conducts performance evaluations that are timely and constructive.
Handles discipline and termination of employees as needed and in accordance with company policy. Maintains inventory, which includes keeping records in an inventory management system, acquiring additional stock as required, and distributing items from stock to fulfil requisitions.
Ensures safe operation of equipment used to move and transport materials to and from the storage areas of the facility.
Oversee installation of new equipment. Develop testing protocols and perform and analyse tests to track results. Create and maintain reports and documentation to track project development and design process, and report progress to clients and management
[18 NOV 2019 To 29 FEB 2020] WORLEY PARSONS Position: COMMISSIONING SPECIALIST (MECHANICAL)Project: CAIRN ENERGY INDIA
Handling of commissioning team of 50 members including supervisor, foreman, charge hands, technicians From various streams electrical, instrumentation, mechanical (static & rotating), safety, process.
Commissioning activities including system walk down carry-out, punch point raising & follow up for clearing same.
For production start-up, landing of oil string casing on slip seal assembly.
Completion of the Well with necessary tubing & wellhead fittings like Hanger flange, X-mas tree etc. Readiness as well completion of perforation of the Well for initial testing to evaluate the nature/behaviour of the Well.
Then bringing the well regular production within earliest possible time.
Commissioning activities (new drilling well) W/F spool testing, hermetical testing, Well completion design, packer setting perforation, well activation, wellhead set-up.
Workover activities Well killing, spool repair / testing, Well Abandonment, casing repair &isolation, fish recovery, New Zone recompletion, artificial lift completion
[22 OCT 2018 To 27 JAN 2019] GREENVILLE LNG Position: COMMISSIONING ENGINEER
Project: GREENVILLE OIL & GAS
Organizes and coordinates activities and staff schedules, ensuring fulfilment goals are met and that shipments are timely, accurate, and undamaged.
Collaborates with managers and other departments to develop and modify materials handling processes and procedures.
Performs other related duties as assigned.
Responsible witnessing for all commissioning activities from beginning of the project. Preparation of commissioning start-up plans & schedule systems handover sequences. Interfaces all departments of project for commissioning activities.
Mentor of executing all scheduling, planning and progress reporting procedures.
Mentoring activities of CONTRACTOR, VENDOR/SUPPLIER participating in commissioning work. Participation in daily work planning meeting as required.
Participation in site safety audits walk down & meetings with EHSE department. Preparation & on site availability assurance of commissioning and start-ups spare part list. Mentoring preservation team activities.
Follow up for Fire & Gas detection and protection systems completion & activation.
Detection & repair/replace of faulty parts or equipment’s according project specification and same reporting to commission manager.
Chemicals and lube oil and utility gases first fill as per safety standards.
Participation in RFSU walk down& preparation of punch list if any
[23 JUNE 2018 to 29 AUGUST 2018]. ROUGE pipeline services
Position: COMMISSIONING ENGINEER Project : KNPC/MAB-1 PETROFAC LLC
Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives,
Develop punch item database by systems, checking for completion and close-out of punch items accordingly with client and company agreed standards,
Preparation & execution as well segregation of systems for early production with related procedure for system isolation and tagging procedures for live systems. Develop and prepare of work permit procedure
for pre-commissioning and commissioning activities in tight collaboration with HSE department of company and client; implement of logbooks for isolation (electrical, piping, mechanical and instrumentation equipment) with establishment of responsibilities.
Developing and preparation of pre-commissioning systems and detailed procedures for flushing, blowing, lube oil systems flushing, chemical cleaning/pickling of process lines of compressors, leak test, inerting, etc. accordingly with client standards and comments; submitted to review, comments and approval to Comm. Manager and client organization; Reinstatement procedure for systems
Planning and scheduling of specific activities (gas turbines, compressors, boilers) in collaboration with vendors and other departments.
Preparation of Mechanical Completion Certificate, Exceptions List and Ready for Commissioning forms of systems and submitted to company and client management for approval;
Review of Commissioning sequence and plan, development of detailed commissioning procedures for leak test, dry-out, steam turbine solo run, gas turbine solo run, test forms and Ready for Start-up for systems. In collaboration with others departments and vendor’s representatives, where necessary, convert vendors procedures, check list and forms for commissioning accordingly to company commissioning plan, submission to management for approval,
Support vendor’s representative to carry of commissioning test and during start-up. Preparation and update of commissioning progress reports, minutes of meetings.
[OCT 2017 TO NOV 2017] CAPE PLC. Position: COMMISSIONING ENGINEER
Project : Jordan Phosphate Mines Co
Key Accountabilities:
Process, package and ship orders accurately. Organize stocks and maintain inventory.
Inspect products for defects and damages. Examine ingoing and outgoing shipments. Organize warehouse space.
Receive, unload and place incoming inventory items appropriately. Check, verify and fill customer invoices.
Preparation for emptying NH3 tank with plant supply pump.
Preparation for full liquid NH3 removal though tank drain valve with temporary pump. Preparation & erection of temporary spools for temporary pumps.
Preparation & erection of N2 injection system for removal of residue NH3 vapour inside tank. Blinding for separation of cleaning NH3 tank from other NH3 tanks in operation.
Emergency flare stack readiness for operation
NH3 tank inside vapour mixture sample checking with HSE & operation dept. Red Blind list preparation & execution for vessel entry.
Manhole of NH3 tank opening preparation & execution Preparation & execution of temporary ventilation for vessel entry.
[06 June 2016 TO 11 June 2017] AAT OMAN.
Position : Sr. Commissioning supervisor (Process) Project : ORPIC PETROFAC EMIRATES LLC
Key Accountabilities:
Warehouse Associate Responsibilities:
Receiving, processing, labelling, and storing incoming stock. Maintaining clear records on all inventory and stock. Inspecting all stock for damages and keeping records of damages. Organizing the warehouse space. Preparing orders for shipment. Recording exact arrival and departure times for shipments. Operating stock management tools; for example, a forklift.
Counting stock and keeping inventory records. Pre–commissioning and commissioning of various sizes of pipeline as like flushing/blowing, Steam blowing, chemical cleaning, neutralization & dry out the system, leak test, purging, cold circulation & start-up with thorough understanding of process and P&ID for complex process plants and utilities/offsite facilities. Pre-commissioning activities like as Pipelines dry-out, N2-Hi leak test, purging and commissioning likewise cold hydrocarbon circulation, mark-up P&ID for Pre-Comm. and commissioning of pipelines, columns, HP vessels, Sieve Dryers, KO drums, flares, pumps trial and mechanical test runs & performance test. Reviewing the ITRs inspection, tests and records, OTPs – operating test procedures and interface with the mechanical commissioning checklists. Air blowing and reinstatement fully in compliance with specifications, tightness testing, start-up of process equipment’s, hydrocarbon separation and fractionation including steam and gas turbine drivers. Carry out detailed plant checkout against engineering, PFD, P&ID, rotating equipment installation and maintenance, ensure equipment preservation procedures, preparing equipment list, lube oil schedule, preparation of marked up system scope P&IDs, preparation of equipment lists, line diagrams, data sheets, utilities summaries, metallurgy diagrams, Operations readiness and assurance issues between operations personnel and construction personnel, Interface and provide clarification and guidance and technical support to construction engineers provide start-up assistance. Conduct internal joint disciplines walk downs of systems prior to Client official walk down, ensure equipment calibration and certification, cathodic protection, participate in risk assessment, review operations manual and standard operating procedures and on time project completion. Utility consumption, firewater system, water treatment plant, nitrogen generation and utilities, prepare equipment list, lube oil schedule, pre- commissioning and commissioning check sheets, review vendor documents, materials of construction, coatings, linings, CP, internal & external monitoring, chemical treatment associated with oil & gas facilities, punch list generation and clearing, log minor discrepancies in punch list for future reference, interface and regularly meet with client and vendor representatives. Rotating equipment installation and maintenance ensure equipment is being preserved as per the preservation procedure, mobilization of men and equipment, site organization, functional testing, reliability & performance test run, successful on-time project completion. Function test and Performance Test of Boiler, Desalination, De-Mineralized Water system, Fire Water system, Air compressors. Line checks, Punch listing. Cleaning & water flushing of pipelines. Air Blowing, Rupturing, Reinstatement, Inerting, System leak test. Equipment Mechanical Test runs, water runs, wet function tests .Internal function test & Final walk through with client. Implementation of site LOTO Program
Isolating systems and equipment. Developing LOTO Clearance boundaries using P&Ids. Isometrics, Electrical Diagrams, and vendor drawings to determine the proper procedure and sequence for isolation. Assuring proper application of locks and tags and controlling LOTO keys. Assuring proper compilation and completion of all LOTO paperwork, Logs, Logbooks and electronic databases. Coordinate and monitor LOTO activities with Construction, Commissioning, HSEC, the owner and subcontractors Compliance with all Safety PPE’s during operations.
Storage and uninterrupted supply of raw materials and intermediates to the processing units. Storage and supply of finished products to terminals.
Blending activities related to gasoline, diesel.
Co-ordination with DCS, terminals, Mechanical/Electrical/Instrumentation Department, Units and Laboratory.
Carrying out all operations with full work permit system.
My Scope of work includes checking the line-up, monitoring of Tank parameters through ATG readings,
tank preparation for dispatch to various units and to offsite, which includes tank settling, mixing, product sampling, water-draining. Monitoring pumps, handing over of pumps to electrical/mechanical dept for maintenance. Routine check-up of area for any abnormality.
Updating all operation parameters in daily Log sheet.
Abnormality if any reporting to DCS. Actively attending fire/safety training programs.
[01 OCT2014 TO 14 March 2015] APPLUS VELOSI QATAR.
Position: Commissioning Supervisor (Process) Project: BARZAN ONSHORE JGC
Key Accountabilities:
Transport products safely using a pallet jack and hand truck.
Dispose of damaged material and alert management of any noticeable errors in a product's quality. Attend weekly meetings that discuss the warehouse's safety processes.
Unload shipments from forklift and sort into the proper areas.
Create a chart of inventory information, including stock levels and upcoming supply orders. Air blowing preparation &execution according given test package marked P&ID.
Air blow points inspection (PIN) conducting with PMT & OED.
After blowing inspection Reinstatement activities by PMT support team follow up.
Mechanical isolation (MIDC) preparation & implementation for air freeing & air drying for given test package.
Marked up line up checking for air freeing & air drying.
Nitrogen hose connection according check valve (NRV) direction existing in given test package. Conducting inspection With PMT & OED for air freeing & air drying.
Performing step back 5x5 & LMRA before every activity. Conducting TSTI with workforce every day.
SIMOPS PTW preparation & Attending meeting with SIMOPS PTW coordinator. PMC PTW preparation & obtaining it from PMC PTW coordinator.
Scaffolding request preparation & follow up for PMC activities.
Temporary defeat for control valves for PMC activities preparation & follow up with JGC instrument dept. For utilities usages attending interface meeting every day.
Interface with area lead supervisor of Train 1 &2 for PMC activities. Columns, flash drum, KO drum preservation until client handover.
Pump suction strainer with temporary start up sieve installation & inspection carried out by PMT & OED. Pump MTR preparation & implementation according approved procedure.
Condition monitoring & recording during Pump MTR.
Pump mechanical seal barriedfuild filling in seal pots & nitrogen back up pressure filling & maintaining. Pump preservation according to approved procedure until handover.
Red blind deviation for fuel gas IN document preparation implementation. Vendor support for furnace refectory dry out activities.
Firefighting line network air blowing & water flushing & sprinklers testing carried out. Centrifugal compressor Lube oil skid PMC activities.
Blind list preparation & implementation for catalyst loading in C1, C2, and C3 treator. Catalyst loading post preservation until client handover carried out.
Capable of inspection, evaluating conditions of fuel storage tanks, pipelines, pumps, dispensers, filter, meter, gauge, and flow control mechanisms, manifold and valve systems, and other related petroleum system components.
Capable of detecting/recognizing system component malfunction, misalignment, leak, and adjustment issues and perform minor fuel system maintenance with guidance from the Team Leader.
capable of removing and replacing small system components, have a basic knowledge of automated tank gauging systems, meters and high/low level alarms. The Team Member shall also be capable of performing fuels systems operational duties on installed fuel systems.
Capable using, generating and extracting data from maintenance reports applicable to any maintenance actions performed.
[13 April 2014 TO 15 May2014] ETS QATAR.
Position: Start-up Supervisor Project : BENZENE S/D Seef QP
Key Accountabilities:
Blind list preparation &approval from client for confine space vessel entry in Benzene column. Client HSE walk down for vessel entry preparation.
Safely Manhole opening & creating fresh air draft inside column by using air operated fan & ventury installation.
Conducting internal inspection safely by client & third party inspector. Removal of damage tray segments, down comer, beam& distributor.
Column internal hydro jetting cleaning & scaffolding erection. Segregation of damaged tray segments & sending to denting dept.
New tray installation & conducting inspection by client QC & third party inspector. Conducting final box up inspection & final box up according HSE procedure.
Service utility station pipeline hot work.
Reboiler supporting plate replacement inside column hot work
I have experience in pipeline systems, storage tanks, pumps, valves, fuel monitors and filters, used oil storage and disposal facilities. Able to convert gauge and temperature readings to quantities of products and shall be able to perform quality assurance functions. Able to correlate pressures, temperatures, and quantities as read from various gauges and meters normally found at a fuel facility. Have a basic understanding of written description and instructions pertaining to facility operations, able to implement cyclic maintenance programs and safety programs relating to all aspects of facility operation and demonstrated expertise in spill clean-up procedures, prevention and control measures, related equipment operation and maintenance. Prepare and check receiving, transfer and close out documents. Connects lines, grounding wires, and loading and off loading arms or hoses to tank truck. Visually inspects samples of fuel. Gauge tanks for water, temperature, and fuel levels. Perform preventive maintenance and repairs on Bulk Storage facilities. Perform general housekeeping and grounds maintenance for terminal, pipeline and dock areas
[15 TO 22 Oct 2013AUG 2012]SAMSUNG SAUDI ARABIA KSA.
Position: Commissioning Engineer (Cast House) Project : Maa’den Aluminium Smelter
Key Accountabilities:
Natural Gas line network air blowing & air freeing by nitrogen. LPTT of natural gas line network by nitrogen on 7 bar.
Plant air network air blowing with target inspection on PMT presence & LPTT on 7 bar. Co2 & Ar storage tank & their evaporator LPTT by nitrogen on 7 bar.
Co2 & Ar tank shell vacuum checking with Torr meter.
Ar tank shell vacuum creating by portable vacuum pump up to 350 torr. First fill in Ar & Co2 tank according vendor procedure.
Chiller pipe line HPTT up to 25 bar by nitrogen with chiller vendor.
NH3 charging in chiller preparation & execution in presence of chiller vendor Potable, cooling & process water network flushing & passivation.
Cooling water emergency overhead tank flow adjustment. Water cooling plant flushing & passivation.
Ingot casting vendor BEFESA, pre commissioning machine adjustment mechanical support, pneumatic
network air blowing & adjustment for cylinders movement.
Weighing scales & overhead cranes inside CAST HOUSE calibration work support to VELOSI & SASO. Billet casting vendor HEARWITCH hydraulic network tuning & pneumatic network mechanical work support.
Hydraulic valve stand rectification work according vendor S/V.
Slab casting VDC vendor WAGSTAFF pre commissioning work support. Billet holding furnace refractory dry out-up to 800 degree Celsius.
Billet holding furnace entry blind list preparation & LOTO. Blind list preparation for client hand over.
Chlorine gas line network chemical cleaning according to chlorine institute standards. Purple tag walk down punch list preparation & closing.(Mechanical Completion).
Grey tag walk down punch list preparation & closing.9practical completion). Hot Commissioning in cast house by ALCOA supporting work.
Spare part list for Operation handover to Ma’aden Operation.
LOTO preparation & application for initial energization of gasline, waterline, airline. Maintaining LOTO practice according PMT BECHTEL procedure.
Co-ordination for punch clearing with construction & client.
Reviewing of pre-commissioning scenarios and material list for pre-commissioning such as sacrificial valves, quick opening valves, temporary spools, temporary silencers, temporary strainers, etc.
Checking for readiness of mechanical completion dossiers of systems, accordingly with QA&OC system, in collaboration with others departments and client representatives.
Review of pre Commissioning sequence detailed pre commissioning activities like leak test, pump solo run, cooling tower fan solo run-in collaboration with others departments and vendor’s representatives. Support vendor’s representative to carry of pre commissioning test and during start-up.
Reviewing & updating pre commissioning plan accordingly with QA&QC system and client standards. Preparing inspection and test reports for pre-commissioning activities and forwarding to Pre comm. Manager and QA&QC Manager for review, comments, approval and integration in QA&QC plan for pre- commissioning.
Estimation of manpower, equipment’s and materials necessary for each activity. Forwarding to management for approval and to construction contractor.
Reviewing and checking of materials, chemicals inventory for pre commissioning activities and spare parts from equipment suppliers.
Developing database of punch item for commissioning department; update and tacking of it; forwarding of items to Punch List Coordinator for integration in Project Punch System,
Assure technical assistance for commissioning and start-up of units on request of client operation
[26 JAN 2012 TO 18 APR 2012] DESCON UAE. Position: MECHANICAL SUPERVISOR
Project : TAKREER TURNAROUND
Key Accountabilities:
Pre-Shutdown Planning — preparation of schedules, Tools & Tackles, materials (including spares), blinds (boiler makers), test fittings & gauges, assessment of manpower requirement, scaffolding requirement, provision of identification tags for repair / replacement, etc. Execution of pre-shutdown overhauling of stand-by machineries/ equipments.
Shutdown Planning — preparation of daily job list, manpower planning, job's follow up, preparation of Daily Report, updating the Master Schedule & Schedule Charts, attending shutdown review meetings, preparation of daily report, preparation of Actual Schedule, etc.
Shutdown Maintenance Activities — execution of maintenance activities as per schedule and daily job list, fixing up the priorities, continuous follow up of jobs, materials arrangement (spares, tools, etc.), coordinating with the other service departments for fabrication, machining, etc.
Post Shutdown Reporting — preparation of shutdown reports, actual schedule charts & master schedule, delay analysis for the delayed activities, review of spares consumed, failure analysis reports for major.
Hands-on experience in Blind to Blind maintenance of exchanger including, blinding, opening of covers, tube pulling, tube expansion, tube insertion, leak testing, tube plugging by seal weld/hammering, box-up and DE blinding.
Fabrication/Erection of Steel structures.
Experience in hydro testing/pneumatic/nitrogen testing of tubes. Exposure to DP Testing and Other types of NDT Test.
Able to read process drawings (PID/PFD), MIG and Arc welding.
Preparing Job Completion Report & Site Handover to Project/Plant Personnel. Ability to supervise a multi-national workforce.
[5 NOV 2010 to 02 FEB 2011] RADIANCE UAE. Position: MECHANICAL SUPERVISOR COMMISSIONING Project : QATAR SHELL GAS TO LIQUID (QSGTL)
Key Accountabilities:
Carried out inspection for MRT of pumps with client. Preservation of pumps up to handover to company. Pre MRT checklist preparation.
Document preparation for inspection. Condition monitoring within pump MRT. Spring support adjustment & released.
[27MAY 2010 to 26 JUNE 2010] TOCO OMAN. Position: MECHANICAL SUPERVISOR
Project : OMAN LNG (SUR PLANT) S/D
Key Accountabilities:
Handling technique of technical worker.
Spading means isolation for reciprocating compressor for its maintenance Preparation lockout & tag out for maintenance job.
Conducting bump test for piston. Conducting run out test for piston rod
Checking gap between piston rings & cylinder head Replacement of crosshead sliding plates
Suction & discharge valves replacement
[1st April 2009 to 31 March 2010] Al-Hugayet Contracting KSA. Position: Commissioning Mechanical Engineer
Project : Saudi Armco with KAUST Project
Key Accountabilities:
Coordinating construction of the project on site and ensure smooth running of all on site tasks. Acting as a link between the on-site project team subcontracted operatives.
Coordinating the construction of the project on site on a daily basis.
Interacting and have regular communication/updates with the commissioning Armco engineer on site progress, raising any issues of concern, etc.
Reviewing all drawings, RFI’s where required, via the contractor, to establish sufficient information to construct.
Site Diary is updating and reviewing on a daily basis.
Implementing strict adherence to safety rules and regulations on a daily basis. Dialoguing with all subcontractors to ensure the program is complied to.
Providing input to the Armco commissioning engineer on Weekly Progress reports and assessing them against the project schedule.
Inspecting requests for work completed.
Checking of work is executed according to contract specifications, approved design drawings, agreed procedures, and method statements.
Checking all installations in preliminary stage.
Reviewing all documentation and drawings to ensure all documentation is kept up to date on site.
[11th MAY 2008 to 11th JAN 2009] LAHOUD ENGG. Position: MECHANICAL SUPERVISOR
Project : BOROUGE-1 ADNOC