J*.Proposed Position
Construction Supervision Expert
2.Name of Firm
KIST Medical College & Teaching Hospital
3.Name of Expert
Pradeep Lal Malla
4.Current Residential Address
Kalanki -14, Kathmandu Municipality
Telephone No.
977-9841343622
Fax No.
N/A.
Email Address
*********@*******.***, ***************@*****.***
5.Date of Birth
January 14, 1961
Citizenship
Nepalese
Type of government ID and ID Number
ID No. 324-***-****
6.Education
Degree
M.E. in Disaster Management – June 2018, The Global Open University,Nagaloand, India
B.E. in Civil Engineering in 1989 from Institute of Engineering, Pulchowk Campus, T.U., Nepal
7.Membership in Professional Associations:
-Nepal Engineering Council – (725 Civil ‘A’ Category)
-Member, Nepal Engineers Association (NEA) No.2008
8.Other Trainings:
-Participation in Training in Micro Tunneling conducted by Nepal Engineers Association for 3 weeks, 1992
-Participation in Training Course in "Arc GIS [Arc view8, Arc editor8, & Arc Info8] Conducted by Kathmandu Engineering College, Kalimati, Kathmandu, Nepal for 3 weeks, 2006
-Training on Urban Planning Approach, Organized by ICA Nepal, Kathmandu, 6 weeks, 2001
-Training on Construction Administration and Management from KIIT Institute, Orrisa, India–2 months -2001
9.Countries of Work Experience
Nepal.
10.Languages (Proficiency: Good, Fair, Poor)
Language
Speaking
Reading
Writing
English
Excellent
Excellent
Excellent
Nepali
Excellent
Excellent
Excellent
Hindi
Good
Good
Good
11.Employment Record
From
To
Employer
Position Held
Nov 2021
Till Date
CIS Pvt.Ltd, Patan
Resident Engineer (Expert)
June 2021
Oct 2021
Shrestha Consultant,Ekanta Kuna Specal Economic Zone (SEZ),Dhangadhi Industrial Complex,Kailali
Water supply and Sanitary Engineer (Expert)
December 2020
May 2021
Cage consultant / Soil Test P. Ltd. JV
Water supply and Sanitary Engineer (Expert)
November 2019
November 2020
Building Design Authority Pvt. Ltd, (BDA), Kamaladi
WASH Engineer
May 2019
October 2019
Building Design Authority Pvt. Ltd, (BDA), Kamaladi
Construction Supervision Engineer (CSE)
Nov 2018
April 2019
ERMC (P) Ltd.
Civil and Utility Engineer/ WASH Engineer
April 2018
October 2018
Innovative Createers P. Ltd.
Consultant Engineer
June 2017
March 2018 (10 man month)
ERMC (P) Ltd. Poverty Alleviation Fund (PAF),
Water Supply and Sanitation Engineer
March 2017
15th June 2017 (16 months)
East West Engineering Consultant
District Resident Engineer
December 2013
Feb 2017
ERMC (P) Ltd
Construction Supervision Engineer/ Water Supply Engineer
April 2012
March 2014 (24 man month)
Kathmandu Medical College (KMC), Building Design Authority Pvt.Ltd..Ghantaghar
Construction Supervision Engineer (CSE)
January 2012
March 2012 (14 man month)
SAARC Secretariat
Construction Supervision Engineer (CSE)
February 2011
December 2011 (11 man month)
Building Design Authority Pvt.Ltd..Ghantaghar
Construction Supervision Engineer (CSE)
May 2010
January 2011 (9 man month)
Building Design Authority Pvt.Ltd..Ghantaghar
Construction Supervision Engineer (CSE)
March 2008
April 2010 (25 man-months)
Building Design Authority Pvt. Ltd,
Construction Supervision Engineer
February 2008
December 2008 (11 man-months)
Indian Embassy
Construction Supervision Engineer (CSE)
December 2006
February 2008 (27 man-month)
We-link Consultant
Construction Engineer
April 2005
November 2006 (7 man-month)
Udaya Consultant
Water Supply Engineer / Construction Supervision Engineer (CSE)
August 2004
April 2005 (8 man months)
Udaya Consultant
Water Supply Engineer
January 2003
October 2003 (8 man months)
Udaya Consultant
Water Supply Engineer/Construction Engineer (CSE)
July 2001
June 2002
Urban Development through Local Effort (UDLE)
Construction Supervision Engineer (CSE)
July 2000
Oct 2003
Mutual Engineering Consultant (P) Ltd.
Water Supply Engineer / Construction Engineer
Jan 1997
July 2000
Multi-Disciplinary Consultant/Design Consortium JV
Resident Engineer
June 1995
December 1996
SILT/Multi/Soil Test Consultant JV
RE/Asst. Resident Engineer (ARE)
July 1989
May 1995
Global Engineering Consultant
Civil Engineer
12.Detailed Tasks Assigned:
-As Per ToR.
13.Work Undertaken that Best Illustrates Capability to Handle the Tasks Assigned:
1.Name of assignment or project
Nepal Bharat Maitri Polytechnic Institute, Hetauda-6
Month & Year
Nov 2021 to Till Date
Location
Hetauda-6
Client
Nepal Bharat Maitri Polytechnic Institute, Hetauda-6
Position Held
Resident Engineer (Expert)
Main project features: Survey, Design and Construction supervision, monitoring, Quality control
Activities Performed: Construction supervision of entire project (370 Ropani, 27 no. of blocks, road) ; Survey, Design and Construction supervision, monitoring, Quality control, Progress review, conducting monthly meeting, weekly meeting, daily report, weekly report, environment report, safety report, schedule track submittal, billing of IPC Payment, request for inspection.
2.Name of assignment or project
Kailali industrial complex
Month & Year
June 2021 to Oct 2021
Location
Kailali
Client
Dhangadhi Industrial Complex,Kailali
Position Held
Water supply and Sanitary Engineer (Expert)
Main project features: Survey and design of storm drain, sewerage drain, perforated pipe drain, water supply system
Activities Performed: Survey and design of storm drain, sewerage drain, perforated pipe drain, water supply system, water proofing in underground basement and management of all storm water and sewerage system of Kailali industrial complex premises
3.Name of assignment or project
Dharahara Reconstruction Project, Nepal Reconstruction Authority, Sundhara
Month & Year
December 2020 to May 2021
Location
Sundhara, Nepal
Client
Nepal Reconstruction Authority
Position Held
Water supply and Sanitary Engineer (Expert)
Main project features: Survey and design of storm drain, sewerage drain, perforated pipe drain, water supply system
Activities Performed: Survey and design of storm drain, sewerage drain, perforated pipe drain, water supply system, water proofing in underground basement and management of all storm water and sewerage system of new Dharahara complex premises.
4.Name of assignment or project
Construction supervision for Charikot, 2nd Water Supply and Sanitation Fund Development Project, Charikot. Dolakha district.
Month & Year
November 2019 to November 2020
Location
Dolakha, district
Client
World Bank/DWSS
Position Held
Construction Supervision Engineer (CSE)
Main project features: As per technical design drawing, tender documents and technical specifications construction supervision & quality control works for water supply project.
Activities Performed: Major responsible for construction supervision of works consisting, data verification, survey and monitoring of water supply scheme, MIS data verification, preparation of social map and lay out map, sustainability survey, meeting with WSUC and municipality member, preparation of business plan, back stopping and SOP, preparation of monthly report, weekly report etc.
5.Name of assignment or project
Chainpur Small Town Water Supply & Sanitation Sector Project
Month & Year
May 2019 to October 2019 (6 man month)
Location
Chaunpur, Bajhang district
Client
DWSS/ADB
Position Held
Construction Supervision Engineer (CSE)
Main project features: Detailed engineering design and construction supervision of water supply project
Activities Performed: Construction of works consisting:
-Development of motor able tracks (road for construction) to the intakes area and treatment plan.
-Re-instate of the concrete and gravel road and re-sealing of the track topped road.
-Construction of collection sump well.
-Construction of retaining wall, thrust blocks and concrete saddles for pipe mains
-Construction of water treatment plants which include Roughening Filters and Slow Sand filter.
-Construction of Water Storage Tanks, Break Pressure Tanks.
-Construction of Valve Chamber, Surface Valves, Boundary Wall, Fencing, Guard Quarters and other buildings.
-Supply and laying of DI, GI and PE pipes and fittings for proposed transmission and distribution lines.
-Supply and erection of LT electrical transmission lines and other electrical.
-Supply and installation of Fire hydrant and house connections.
-Demolishing of redundant structures.
-Design, supply, Installation, testing, commissioning and maintenance of Automation System of Chainpur Town Water Supply System based on SCADA software comprises of three Transmission lines, three reservoir (DMA) systems and two numbers of WTPs including instrumentation control valve, bulk water meter, pressure level transducer, etc. and comprehensive operation and maintenance for one year.
6.Name of assignment or project
Gautam Buddha International Airport Project
Month & Year
November 2018 to April 2019 (6 man month)
Location
Bhairahawa Airport-4, Rupandehi District
Client
CAAN/ADB
Position Held
Civil and Utility Engineer/WASH Engineer
Main project features: Detailed engineering design and construction supervision.
Activities Performed: Survey, design and construction supervision of toilet and Bath room in Arrival, Departure section, control tower, Admin. Section, Fire Rescue section, Septik tank, and soak pit, laying of soil pipe, laying of sewer pipe, laying of water pipe, laying of rain water pipe, fitting of commode and urine set, laying of sewer outlet chamber, water outlet chamber, Rain outlet chamber, 450 cum and 200cum Over Head Tank, 100mm dia. distribution DI Pipe laying, Slow sand filter, pressure filter, Under Ground Tank, construction of pump house 4nos.,Dis-infection unit, 3km. 600mm/700mm sewer hume-pipe laying, construction of Manhole, sewer treatment plant by pumping system of 5nos., mixing of sewage to Ghagra river by primary treatment.
7.Name of assignment or project
Construction supervision of Kanya Mandir Secondary School, Nhyokha, Kathmandu
Month & Year
April 2018 to October, 2018 (7 months)
Location
Kathmandu
Client
Kanya Mandir Secondary School
Position Held
Consultant Engineer
Main project features: As per technical design drawing, tender documents and technical specifications Construction supervision & quality control works.
Activities Performed: Survey, design and construction supervision, monitoring, quality control, progress review, conducting monthly meeting, weekly meeting, daily report, weekly report, environment report, safety report, schedule track submittal, request for inspection, excavation of 15m. depth pile by auger mud pump boring and stone compaction 2m.c/c distance.
8.Name of assignment or project
Rural Water Supply and Sanitation Fund Development Board (RWSSFDB)
Month & Year
June 2017 to March 2018 (10 man month)
Location
Bajhang, Mugu, Bajura, Achham, Humla, Dadeldhura, Doti, Jajarkot, Kapilvastu, Baitadi, Kanchanmpur, Kailali, Darchula, Bara, Gorkha, Myagdi, Parbat, Salyan, Dang, Rolpa, Bajura, Dailekh, Districts
Client
WB/RWSSFDB
Position Held
Water Supply and Sanitation Engineer
Main project features: As per technical design drawing, tender documents and technical specifications construction supervision & quality control works.
Activities Performed: Survey, design and construction supervision, monitoring, quality control, progress review, design review, verification of intake, transmission line, anchor block, air valve, Inception tank, Break pressure tank, water quality test, measurement of alignment of transmission line and distribution line checking of different loss between intake to reservoir pipe line quality and quantity of used material.
9.Name of assignment or project
Construction supervision of School Building
Month & Year
March 2017 to 15th June 2017 (16 months)
Location
Gorkha
Client
EEAP/ADB
Position Held
District Resident Engineer
Main project features: As per technical design drawing, tender documents and technical specifications construction supervision & quality control works.
Activities Performed: Survey, Design and Construction supervision, monitoring, Quality control, Progress review, conducting monthly meeting, weekly meeting, Co-ordination with DLPIU, Overall responsibility of 28 nos. of school building and 6nos. of package with 28no. of school. Gorkha district, JICA Project. Monthly Progress Report, Monthly meeting. Over all responsibility of all district wise responsibilities.
10.Name of assignment or project
Second Small Town Water Supply and Sanitation Project, Baitadi financed by ADB
Month & Year
April 2014 to January 2015 (14 man month)
Location
Baitadi, Nepal
Client
STWSSSP/ADB Loan 1755-NEP (SF)
Position Held
Construction Supervision Engineer (CSE)
Main project features: As per technical design drawing, tender documents and technical specifications construction supervision & quality control works, water supply project.
-Activities Performed: Responsible for supervision of construction;
-Carry out joint survey, check line and level, layout of construction & verify and propose if any changes required as per project requirements.
-Implementation of guidelines given in contract administration manuals.
-Implementation of QA/QC manual to confirm works as per Quality Assurance Plan (QAP)
-Overall construction supervision, measurement of completed works to verify the bills for payments.
-Assess and enforce, as per standard Construction Management System, the adequacy of contractors' inputs in terms of material, equipments, construction machinery, workers, and construction approach and methodologies.
-Monitor & enforce contracts to take safety measure for the works, workers & general public as per safety manual.
-Furnish detailed drawings, with revisions as necessary, to the contractor, check contractors' design and drawings for lump sum turnkey contracts (Design/Build contracts).
-Review and examine the process of passing of contractors' bills and payments to contractors with special emphasis on minimizing the time taken in submission of a bill by the contractor and payment received by the contractor against such a bill.
-Attend third party inspections as necessary and provide certification on the quality of the supplies based on such inspections.
-Work as the engineer or employer's representative within the context of conditions of the construction contracts.
-Regularly monitor physical and financial progress against the milestones as per the contract so as to ensure completion of contract in time.
-Monitor and enforce, as detailed out in Quality Assurance and Quality Control (QA & QC) Manual, the quality of inputs, processes, and outputs during all activities of construction to ensure the highest quality of works conforming to the specifications and drawings.
-Assist to examine contractors' claims for time extension, variations, additional compensation etc and recommend appropriate decisions.
-Assist the Implementing Agency in resolution of various other contractual issues and overall contract management.
-After physical completion of contract, Assist to prepare planned maintenance procedures; check installation and commissioning; monitor preparation of the "as built" drawings.
-Identify training needs, organize training courses, train WUSC members and staff on the job in order to ensure effective O&M post construction period.
-Proactively anticipate and carry out any other activity as per the scope of works; Total Project Cost (approx): NRs. 30 Million.
11.Name of assignment or project
Construction of Kathmandu Medical College (KMC) at Duwakot, Bhaktapur
Month & Year
April 2012 to March 2014 (24 man month)
Location
Bhaktapur
Client
KMC
Position Held
Construction Supervision Engineer (CSE)
Main project features: 8 storied building domestic water supply, treatment unit, electrical & AC works.
Activities Performed: Construction supervision of project, review quality assurance plan and quality control plan (QA QP) supervise and monitor construction, review contractors bill, monitor and enforce safety manual, monitor physical & financial progress, examine contractor's claim, check installations and commissioning, monitoring preparation of as built drawings for water supply, sewerage, treatment plant and other civil components. The project was implemented and managed under ICB contracts; Total Project Cost: NRs. 8.2 Million.
12.Name of assignment or project
Construction of SAARC Secretariat
Month & Year
January 2012 to March 2012 (14 man month)
Location
Kathmandu
Client
SAARC Secretariat
Position Held
Construction Supervision Engineer (CSE)
Main project features: 6 storied building domestic water supply, treatment unit, electrical & AC works
Activities Performed: Construction Supervision of project, review quality assurance plan and quality control plan (QA QP) supervise and monitor construction, review contractors bill, monitor and enforce safety manual, monitor physical & financial progress, examine contractor's claim, check installations and commissioning, monitoring preparation of as built drawings; Total Project Cost: NRs. 41.61 Million.
13.Name of assignment or project
i) Waste Water Treatment Plant at Sallaghari & Kodku, (KUKL/DNI/-02/-13A) ii) Construction of Laboratory Building at Mahankalchaur, Kathmandu (KUKL/DNI/-02/10)
Month & Year
February 2011 to December 2011 (11 man month)
Location
Kathmandu, Lalitpur, Bhaktapur
Client
PID/KUKL/GoN
Position Held
Construction Supervision Engineer (CSE)
Main project features: i) Cleaning of existing waste water treatment plants, boundary fencing, retaining walls, lining works, gabion works etc ii) 2 storied laboratory building for testing of water quality.
Kodku Capacity (Million liter/day) - 25.192
Sallaghari Capacity (Million liter/day) – 7.284
Activities Performed: Construction Supervision of project, review quality assurance plan and quality control plan (QA QP) supervise and monitor construction, review contractors bill, monitor and enforce safety manual, monitor physical & financial progress, examine contractor's claim, check installations and commissioning, monitoring preparation of as built drawings. The project was implemented and managed under ICB contracts; Total Project Cost: i) Rs 24.20 million ii) Rs 20.8 million.
14.Name of assignment or project
Water Supply Tubewell Boring and Installations at 5 Places of Kathmandu Valley (KUKL/DNI/-02/03) Financed by ADB
Month & Year
May 2010 to January 2011 (9 man month)
Location
Kathmandu, Lalitpur, Bhaktapur
Client
KUKL/GoN
Position Held
Construction Supervision Engineer (CSE)
Main project features: As per technical design drawing, tender documents and technical specifications Construction supervision & quality control works, 250 /200 mm tubewell (150 to 200m deep), pump installations, discharge of 21-25 lps etc.
Activities Performed: Construction Supervision of project, review quality assurance plan and quality control plan (QA QP) supervise and monitor construction, review contractors bill, monitor and enforce safety manual, monitor physical & financial progress, examine contractor's claim, check installations and commissioning, monitoring preparation of as built drawings. The project was implemented and managed under ICB contracts; Total Project Cost: Rs 41.50 million.
15.Name of assignment or project
Feasibility study and detail engineering design & construction supervision of Urban Environmental Improvement Project Finance by ADB Loan No 1966-NEP (SF)
Month & Year
March 2008 to April 2010 (25 man-months)
March 2008 to April 2011 (35 man-months
Location
Hetauda Municipality
Client
DUDBC, UEIP, PIU Hetauda
Position Held
Construction Supervision Engineer (CSE)
Main project features: Urban Water Supply, Gravity/Pumping Systems, 8000 H/H, 50,000 Population,120 lps discharge, treatment plant – Auto wash filters, 2487 house connection, Sewerage 12,472 m, RBTP-3 nos, Road, 500M3 underground reservoir & 450m3 OHT, 53KM pipeline distribution.
1)Water Supply Sub-project (ICB-Contract): Detail engineering design and construction supervision of gravity flow water supply system / 3 nos. of overhead water tank, two nos. of ground water tank, 2 nos. of water treatment plant, stream intake, 2 nos. of deep boring, 75 km of distribution pipe line with DI, HDPE and GI of varying sizes of 300 mm to 40mm, financial and economic analysis etc. The total sub-project cost is Rs. 192,433,634.94
Main Town Scheme (This scheme serves ward no. 1, 2, 3, 4, 5 and 10): The sub-project includes the rehabilitation and extension of the existing water supply schemes to improve the overall water supply situation of the Hetauda Municipality. The scheme comprises detailed engineering survey, design and construction supervision of infiltration gallery, 500 m3 capacities ground tank, water treatment plant, transmission main, distribution pipe etc.
2)Sanitation & Sewerage Sub-project: It involves detail survey, design and construction supervision of three nos. of combined sewerage system, there are three schemes name as Rapti-1, Rapti-2 and Karra system of 13km length with 1500mm to 300 mm dia. RCC hume pipe with Waste Water (reed bed) treatment plants each on the banks or Rapti and Karra rivers serves wards 1, 2, 4, 5 and 10 of Hetauda Municipality. The sub-project includes construction of 3 nos. of sewerage system. The total sub-project cost is Rs. 145,080,402.83
3)Supply of Sewer Cleaning Equipment Sub-project: There are sewer cleanings equipment like jetting machine, suctions machine, di-silting machine, 2 nos. of tripper, one no. of tractor etc. The total sub-project cost is 17,495,878.14
4)Waste Water (Reed Bed) Treatment Plant Sub-project: It involves detail survey, design and construction supervision of three scheme of Waste Water (Reed Bed) Treatment Plant sub-project name as Rapti-1, Rapti-2 and Karra system. The total sub-project cost is Rs. 42,124,197.65
5)River Training Works Sub-project (Rapti and Karra River Bank Protection Work): It involves detail survey, design and construction supervision of river embankments to protect against flood, erosion, from Rapti & Karra rivers in wards 1, 11 & 4 respectively. The total project cost is 9,168,350.37
Activities Performed: Construction Supervision of project, review quality assurance plan and quality control plan (QA QP) supervise and monitor construction, review contractors bill, monitor and enforce safety manual, monitor physical & financial progress, examine contractor's claim, check installations and commissioning, monitoring preparation of as built drawings. The project was implemented and managed under ICB contracts; Total Project Cost: NRs. 459 Million. Water Supply NRs. 192.433 Million, Sewerage-NRs 145.08 Million, RBTP 42.124 Million, Supply of Sewerage cleaning equipment NRs.17.49 Million.
16.Name of assignment or project
Indian Embassy Construction and Renovation Project
Month & Year
February 2008 to December 2008 (11 man-months)
Location
Kathmandu Metropolitan City, Lainchour
Client
Indian Embassy
Position Held
Construction Supervision Engineer (CSE)
Main project features: 3 kms Long PCC pavement, Waste water treatment unit-1 #, Compound wall, landscaping, etc.
Activities Performed: Construction Supervision of project, review quality assurance plan and quality control plan (QA QP) supervise and monitor construction, review contractors bill, monitor and enforce safety manual, monitor physical & financial progress, examine contractor's claim, check installations and commissioning, monitoring preparation of as built drawings. The project was implemented and managed under ICB contracts; Project Cost: NRs 40 million.
17.Name of assignment or project
Bheri Zonal Hospital Rehabilitation and Extension Project (GTZ/KFW funding)
Month & Year
December 2006 to February 2008 (27 man-month)
Location
Nepalgunj Municipality
Client
GTZ/KFW funding
Position Held
Construction Engineer
Main project features: Compound wall, construction of 1st floor of hospital building, water supply networks, and electrification works.
Activities Performed: Construction Supervision of project, review quality assurance plan and quality control plan (QA QP) supervise and monitor construction, review contractors bill, monitor and enforce safety manual, monitor physical & financial progress, examine contractor's claim, check installations and commissioning, monitoring preparation of as built drawings of Hospital building sewerage and water supply works. The project was implemented and managed under ICB contracts; Project Cost: NRs. 42.5 million.
18.Name of assignment or project
Gurung Gaun Water Supply Project
Month & Year
April 2005 to November 2006 (7 man-month)
Location
Gulmi District
Client
DWSS/ADB
Position Held
Water Supply Engineer / Construction Supervision Engineer (CSE)
Main project features: Detail design and survey
Activities Performed: Detail design and survey of source selection and construction supervision Intake structure, collection chamber, washout valve chamber, air relief valves, reservoir tank, ferro-cement tank, transmission pipe lines, distribution pipe lines alignment, school toilets, community toilets in Gulmi District; Project Cost: NRs.6.0 million.
19.Name of assignment or project
Magar Gaun Water Supply Project (ADB funded)
Month & Year
August 2004 to April 2005 (8 man months)
Location
Arghakhanchi District
Client
DWSS/ADB
Position Held
Water Supply Engineer
Main project features: Detail design and survey
Activities Performed: Detail design and survey of source selection and construction supervision Intake structure, collection chamber, washout valve chamber, air relief valves, reservoir tank, ferro-cement tank, transmission pipe lines, distribution pipe lines alignment, school toilets, community toilets in Arghakhanchi District; Project Cost: NRs.6.0 million.
20.Name of assignment or project
Gumba Village Water Supply Project (ADB funded)
Month & Year
January 2003 to October 2003 (8 man months)
Location
Palpa District
Client
DWSS/ADB
Position Held
Water Supply Engineer/Construction Engineer (CSE)
Main project features: Detail design and survey
Activities Performed: Detail design and survey of source selection and construction supervision Intake structure, collection chamber, washout valve chamber, air relief valves, reservoir tank, ferro-cement tank, transmission pipe lines, distribution pipe lines alignment, school toilets, community toilets in Palpa District; Project Cost: NRs.7.0 million.
21.Name of assignment or project
Arughat Bazar (Small Town) Water Supply Project
Month & Year
January 2003 to October 2003 (10 Months)
Location
Gorkha District
Client
DWSS/ADB
Position Held
Water Supply Engineer/Construction Engineer
Main project features: Detail design and survey
Activities Performed: Detail design and survey of source selection and construction supervision Intake structure, collection chamber, washout valve chamber, air relief valves, reservoir tank, ferro-cement tank, transmission pipe lines, distribution pipe lines alignment, school toilets, community toilets in Arughat, including sanitation facilities within the project area; Project Cost: NRs. 6.0 millions.
22.Name of assignment or project
Urban Sewerage and Infrastructure Project with Heritage Construction Area National Heritage Conservation Project (UDLE/GTZ funded)
Month & Year
July 2001 – June 2002 (12 man month)
Location
Madhyapur Thimi Nagadesh Municipality, Bhaktapur and Patan Municipality, Lalitpur
Client
UDLE/GTZ
Position Held
Construction Supervision Engineer (CSE)
Main project features: Construction supervision
Activities Performed: Construction supervision of renovation work of monument, temple, community buildings, toilet blocks, stone pavement, drainage and sewerage system including waste water in urban places of Madhyapur Thimi Nagadesh Municipality, Bhaktapur and Patan Municipality, Lalitpur. The project was implemented and managed under ICB contracts; Project Cost: NRs. 10.0 millions.
23.Name of assignment or project
Upper Tamakoshi Hydro-electric Access Road (35KM),
Month & Year
July 2000 to July 2001 (13 man month)
Location
Dolakha
Client
NEA/Upper Tamakoshi Hydro-electric Project
Position Held
Construction Supervision Engineer (CSE)
Main project features: Construction supervision
Activities Performed: Construction supervision of project, review quality assurance plan and quality control plan (QA QP) supervise and monitor construction, review contractors bill (IPC), monitor and enforce safety manual, monitor physical & financial progress, examine contractor's claim, check installations and commissioning, monitoring preparation of as built drawings. The project was implemented and managed under ICB contracts; Project Cost: NRs. 10 millions.
14.Certification:
I, the undersigned, certify to the best of my knowledge and belief that
(i)This CV correctly describes my qualifications and experience;
(ii)I am not a current employee of the Executing or the Implementing Agency;
(iii)In the absence of medical incapacity, I will undertake this assignment for the duration and in terms of the inputs specified for me in Form TECH-6 provided team mobilization takes place within the validity of this proposal;
(iv)I was not part of the team who wrote the terms of reference for this consulting services assignment;
(v)I do not have conflict of interest in accordance with ITC 3.0;
(vi)I am not subject to any national or international sanctions, temporary suspension or debarment by ADB or other multilateral development banks (MDB);
(vii)I certify that I have been informed by the firm that it is including my CV in the Proposal for the Design, Supervision and Contract Management Consulting Services