Kishore
Buyer Oil&Gas/Power
Resume
Page *
Personal Information:
Nationality : Indian
Passport No : Z6713190 –Valid upto 10/08/2032
Date of Birth : September 14,1980
Mob: 0091 630-***-****
Email :adzxjy@r.postjobfree.com, adzxjy@r.postjobfree.com SUMMARY
17 years of combined experience in Procurement, Expediting and Logistics Coordination. EXPERIENCE
2018-August–
Till Date
2015–2018
DGM, Larsen & Toubro Limited, Vadodara, India.
Responsible for Post Order Management for:
DHDT Project for IOCL-Panipat – Ongoing Project
Residual Up-Gradation Facility (RUF) for HPCL, Vizag - Completed
Atmospheric Vacuum Unit (AVU) for IOCL, Barauni - Completed
Guru Gobind Singh Polymer Addition Project for HPCL-Mittal Energy Limited, (Completed Project) – Completed
Conducting kick-off meeting and record the minutes of meeting.
Follow up with vendors for submitting documents as per agreed dates in VDRL.
Coordinating with Engineering and quality team for review and approve of documents.
Arranging face to face meetings for closure of documents if required.
Reviewing of Monthly Progress Reports against Manufacturing Schedule.
Follow up of sub-ordering status and monitoring components manufacturing progress.
Visiting vendors and sub-vendors for progress review meetings.
Coordinating with quality team and Third-party Inspectors to ensure timely inspections.
Coordinating with logistics team for review of transportation drawings and packing & preservation procedures.
Coordinating with logistics team for timely arrangement of transportation of materials.
Ensure timely delivery of materials and spares as per Purchase Order requirements.
To perform analysis on vendor performance and recommends those most desirable.
Preparation and issuing of weekly Procurement Status Report and Materials Delivery Status Report for management review.
Issue escalation to vendor’s top management for any hold ups.\ Buyer, WorleyParsons Arabia Ltd., Riyadh, KSA
Fuel Gas Pipeline Project for Saudi Electricity Company PP13 & 14 Power Plants,
(EPCM Project):
Responsible for Procurement, Expediting and Logistics Coordination of Project Materials:
Issuing ‘Invitation to Bid’ documents to approved Bidders,
Ensure bidder understands the bidding documents and replying to any technical and commercial queries through Pre Bid Clarifications. Kishore
Buyer Oil&Gas/Power
Resume
Page 2
2010-2014
Ensure bidders submit their bids on or before bid closing date.
Opening the bids in presence of client and preparing the ‘Bid Opening Report’
Sharing the bids with Engineering for technical evaluation.
Ensure bidders reply to all technical and commercial clarifications in time.
Preparation of Commercial Bid Evaluation and Award Recommendation for Client’s approvals.
Ensure all the agreed commercial terms and technical specifications are incorporated in the Purchase Order.
Issuing the Purchase Order to successful bidder and ensure receiving acknowledgment.
Informing the unsuccessful bidders.
Conducting the kick-off meeting and record the minutes of meeting.
Chasing bidders for submitting the GA drawings and Inspection test plan within the agreed period and coordinating with Engineering and Quality department to get them approved.
Coordinating in arranging of Pre Inspection Meetings.
Coordinating with Third party Inspectors and ensure the inspections are done in time at various locations.
Issuing Shipping Release upon receipt of approved Inspection Report.
Coordinating the logistics operations.
Ensure vendor submits Final Documentation.
Processing the invoices and ensure vendors are paid in time.
Ordering for 2 year Operational spare Parts.
Coordinating with vendors for mobilization of trainers if any training is required.
Coordinating with vendors for mobilization of vendor site supervisors for installation and commissioning activities.
Preparation and issuing of weekly Procurement Status Report and Materials Delivery Status Report.
Ensure all safety procedures are followed throughout the process. Buyer, WorleyParsons Oman Engineering, Oman
Petroleum Development of Oman(PDO) - Amal Steam Surface Facilities Project (EPCC Project) –
Issuing ‘Invitation to Bid’ documents to approved Bidders,
Ensure bidder understands the bidding documents and replying to any technical and commercial queries through Pre Bid Clarifications.
Ensure bidders submit their bids on or before bid closing date.
Opening the bids in presence of client and preparing the ‘Bid Opening Report’
Sharing the bids with Engineering for technical evaluation.
Ensure bidders reply to all technical and commercial clarifications in time.
Preparation of Commercial Bid Evaluation and Award Recommendation for Client’s approvals.
Ensure all the agreed commercial terms and technical specifications are incorporated in the Purchase Order.
Issuing the Purchase Order to successful bidder and ensure receiving acknowledgment.
Informing the unsuccessful bidders.
Processing the invoices and ensure vendors are paid in time.
Ordering for 2 year Operational spare Parts.
Coordinating with vendors for mobilization of trainers if any training is required. Kishore
Buyer Oil&Gas/Power
Resume
Page 3
Coordinating with vendors for mobilization of vendor site supervisors for installation and commissioning activities.
2007-2010
Sr. Procurement Engineer, Dodsal Engineering & Constructions Pte.Ltd. Qatar Petroleum - Common Cooling Seawater System Project – Phase- II
(EPC Project)-
Procurement of Project Piping Materials, Structural Steel, Rebar, Mechanical, Electrical and Instrument materials and civil consumables.
Estimating the cost and preparation of budget against each budget-head for higher management approvals.
Request For Quotation, getting quotations, getting Engineering approvals, tracking TBE, arranging negotiation, making Comparison Statements, Order awarding. delivery follow-up, arranging TPI/FAT, liaise freight forwarder, freight documentation Responsible for Obtaining Custom Exemption Certificates, supplier payments, LC opening and LC tracking, ABG/PBG tracking.
Generating reports and graphical representation of estimated and actual budgets.
Generating price charts over a range of period.
2006-2007
Procurement Engineer, Galfar Engineering and Contracting L.L.C. Petroleum Development of Oman (PDO) – Off-Plot Delivery Contract.
Request For Quotation, getting quotations, getting of Engineering approvals, tracking TBE,
Negotiation, making Comparison Statements, Order awarding. delivery follow-up,
Logistics Coordination
2002-2006
Project Engineer – Matrix Pharmaceuticals Pvt. Ltd., India.
Erection and Commissioning of Process plant.
Expediting the Ordered materials.
Engineering and Logistics coordination.
Involvement in day-to-day production activities. EDUCATION
B.Tech. (1998 – 2002) : Bachelors of technology in Chemical technology Madras University
SPECIFIC TECHNICAL EXPERTISE/SPECIALIST COURSES
HSE Trainings
H2S Awareness,/Fire Fighting
First aid
Incident reporting and investigation.