NAWAF MANDAGATHINGAL

QA/QC Engineer- Civil and Architectural

MMUP/UPDA No.29464

Qatar LMV

Local Address: Building No. 40, St. No.

***, **** **,

FEREEJ ABDUL AZIZ

Doha, Qatar

Email Address: adzn32@r.postjobfree.com

Mobile No.: +974-********

OBJECTIVE:

6+ years of over-all working experience as a QA/QC-Engineer in Qatar To obtain a challenging position in a high-quality engineering environment where my resourceful experience and academic skills will add value to organizational operations. EDUCATIONAL ATTAINMENT:

2013-2017-College

Anna University, Chennai

B.E in Mechanical Engineering

2011-2013-Secondary

MMMHSS, Kuttayi

WORK EXPERIENCE:

COMPANY: MIDMAC MIC CONSTRUCT

ADDRESS:

LUSAIL, DOHA

PROJECTS

HANDLED:

a) LUSAIL PLAZA TOWERS– (MIDMAC MIC CONSTRUCT)

POSITION: QA/QC-Engineer- Civil and Architectural

INCLUSIVE DATE: JUNE 15, 2021 up to PRESENT

JOB DESCRIPTION

For CIVIL WORKS AND UHPC, OPAQUE VISION PANELS & GRP INSTALLATION AND FINISHING

DUTIES & RESPONSIBILITIES:

Follow ITP (Inspection and Test plan)

Check the quality of delivered material on the site

Ensure the standards of material with material submittal

Ensure quality and finishing of materials

checking the Survey setting out before installing

Checking the tightening of the bolt after installation of brackets

Ensure the Alignment of the material and check the grid line marking

Monitoring of schedule through daily, weekly and monthly progress reports

Coordinating and updating the QC head about the quality

Responsible for management of material and human resources on sites

Check the material quality as per prescribed standards

Responsible for crew training and internal scheduling

To supervise daily log of inspection activities and compare progress reports.

Providing technical guidance to contractor personals.

Monitoring the Contractor’s adherence to plans, once approved implementing effective record systems

Perform witness and record tests

Personally handles main contractors and client concerns

Handles good work progress with the quality

Performs WIRs and RFMIs

SAMPLING AND TESTING:

Civil works:

Concrete Sampling and Testing

Soil Sampling and Testing

Steel Sampling and Testing

Water Sampling and Testing

Bitumen Sampling and Testing

Aggregate Sampling and Testing

Facade works:

Visual Inspection

Non-destructive testing (NDT)

Water Infiltration Testing

Air Leakage Testing

Thermal Performance Testing

WORK EXPERIENCE:

COMPANY: DOHA EXTRACO

ADDRESS:

New Industrial Area Building 242, Street No. 4. Zone 81, Green Zone PROJECTS

HANDLED:

b) COMMERCIAL BOULEVARD LUSAIL– (REDCO ALMANA.)

POSITION: QA/QC-Engineer-

INCLUSIVE DATE: FEBRUARY 10, 2019 up to JUNE 15, 2021 JOB DESCRIPTION

(For GRC PANELS INSTALLATION AND FINISHING)

DUTIES & RESPONSIBILITIES:

Conducting regular inspections of facades and identifying any defects or issues that need to be addressed.

Developing and implementing quality control procedures for facade construction and installation.

Working with project managers, architects, and construction teams to ensure that facades are designed and installed according to specifications and standards.

Reviewing shop drawings, mockups, and material submittals to ensure compliance with project requirements and industry standards.

Conducting testing and analysis of facade materials and assemblies to ensure that they meet performance criteria.

Providing technical expertise and guidance to construction teams regarding facade installation and maintenance.

Developing and maintaining documentation related to facade inspections, testing, and quality control procedures.

Coordinating with third-party testing and inspection agencies to ensure compliance with regulatory requirements and project specifications.

Collaborating with other members of the QA/QC team to develop and implement best practices for quality control in facade construction.

Keeping up-to-date with industry standards and regulatory requirements related to facade construction and testing.

Civil and Architectural

GRC (SETTING-OUT/LEVELLING) & INSTALLATION:

PREPARATION

Checks & reviews carefully the approved Shop Drawings (Plans, Elevations, Sections & Typical Details), as per Survey & Measurements in actual installation at Site.

Check & ensure that prior to installation works, approved MEP clearances are provided and handover of the areas in writing as required for installation to proceed.

Rockwool and MEP clearance must be required prior to the installation of brackets

Checks internally, any installation-inspection to be raised officially coordinated with all MEP Services, Other Trades/Discipline, as clearances, pertinent to the quality of works installed & related workmanship issues that needs to be rectified immediately, before inspections shall be raised officially.

For Brackets Installation.

- Checks & ensures, that 3rd Party Test for the anchorage supports (pull-out test & torque test) had been conducted-implemented as witnessed by the Consultant via official inspections.

- Checks & ensures, that brackets installed are as per approved shop drawing, survey, structural calculation and Project Specifications. Bracket material shall be weld able structural steel, to comply with the tolerances on dimensions and shapes and comply with the technical delivery conditions of hot-rolled products for structural steel.

- Ensure bracket is hot-dip galvanized and no cutting drilling of holes and welding to be done after galvanizing.

- Ensure design of brackets allows for vertical and horizontal movements after fixing.

- Ensure brackets fix in steel pipe are with adjustment in three directions to overcome dimensional variations such as slotted holes and site-drilling or welding after positioning of components (for final fixing after initial fixing with slotted holes).

- Ensure to combine with serrated surfaces to prevent further movement after adjustment.

- Check & ensure that safety line for securing any personnel and equipment are there at the area of inspection as required.

- Checks & ensures, that the installed-fixed brackets are in accordance to the approved shop drawing layout plan and section as reference for the setting-out. And Structural shims

(plastic/fibre) should be used as German standard to maintain the level of the brackets.

- Checks & ensures that the position and level are in accordance to survey markings and key bracket.

- Check & ensures, that all bolts are tightened using torque wrench. Torque are to be adjusted as per Design requirement (frequency as per ITP) & 3rd party inspections are raised officially.

Attends Inspection for Installation (IRW) officially with AEB-CSC, as coordinated, in the presence of the Subcontractor’s QC Engineer/Inspector representative, in strict compliance with the approved ITP.

Checks & ensures that proper approved scaffoldings/ladders are provided across the perimeter of the building over the total height were the curtain walls are installed & full body harnesses and 100% tie off is available as required & mandatory.

Rejects any inspections-work installations, raised by the Subcontractor, that are not satisfactorily acceptable as per actual installation, with poor quality of works or any other related issues unacceptable. And/or documents attachments (as approved by AEB-CSC) are incomplete.

Responsible for the Work Entire Quality Assurance, quality control & inspection programs & for overseeing the Quality Requirements and Quality Control measures for the Project in coordination with the Site Engineers & Subcontractors.

INSTALLATION

- Check and ensure the installation of GRC panels as per the survey setting out and alignment with finishing as per the project specification

- Checks & ensures, after installation of GRC Panels are properly aligned & accessories are

- Checks & ensures, that all installations are carried out in conformity and approved shop drawings as per the recommendation.

-

- Checks & ensures, as verified & confirmed at site, that proper adjustment had been obtained for its required vertical and horizontal alignment, before final fixation

- Checks & ensures, as verified & confirmed at site, ironmongery such us handle and lock assembly, panic devices (if required), door closers & access control devices are completely fixed, prior to raise official inspection to CSC

- Checks & ensures, for doors with access control device, that openings/provision for the installation of cables/wirings (provision shall be coordinated and agreed with the Engineers and Electrical Works INSPECTION & HANDING OVER:

The inspection must be raised upon the completion of work and cleaning the area before. And ensure the required quality meets the certain work

Checks & ensures, upon QC’s Architect/Engineer/Inspector’s satisfactory acceptance with the completed works, Inspection Request Works (IRW) shall be raised immediately as official to CSC, considering the time frame allocated within the inspection procedure of the project.

Checks & ensures, following the inspection process, any defect (workmanship issues) or non-conformance is to be noted & notification to be given to the Subcontractor, with a time frame allocated for its due time action in doing the rectification works. Upon completion of rectification works, immediately the inspections will be resubmitted.

Checks & ensures, that the temporary protective tape had been removed. This will only be implemented- commence could, to those Zones with clearance given, certifying that all other works are totally completed

& no other work activities from other trades/disciplines (Architectural, MEP Services) are still on-going at any rooms/areas to be handed over.

For Final Cleaning:

- Checks & ensures, that the cleaning manual document is available as approved by the Consultant in accordance to the Manufacturer’s recommendation & Project Specifications.

- Checks & ensures, that the cleaning of all surfaces should & must be in accordance with the approved cleaning manual. Abrasive materials are strictly not to be used & any metallic tools of any kind. With water only to be used with a light non-acid detergent and soft cloth. FOR TECHNICAL REVIEW/CHECKING OF DOCUMENTS:

Prepares Method Statement (MS) & Inspection Test Plan (ITP).

Reviews, checks, edit, make comments, rejects, revise & re-submits, Method Statements (MS) submitted by Sub-Contractors/Suppliers, prior for submission to Consultant/Client, in order to obtain approval.

Reviews, checks & edit, rejects, revise & re-submits, Inspection Test Plans (ITP’s) submitted by Sub- Contractors/Suppliers prior for submission to Consultant/Client, in order to obtain approval.

Evaluates, check & reviews proper submittal of Technical Material Proposals-(Pre-Qualifications, Material Submittals, shop drawings, etc.)

Evaluates, check & reviews proper submittal of Technical Mechanical shop drawing plans. As to be in accordance with the Design criteria/codes, standards, project specifications as primarily required.

Review Material Test Certificates, Inspection and Test Reports, and Manufacturer’s Data Records.

Ensure calibration and maintain calibration records for inspection, measuring and test equipment for the Company, Project and that of the Sub-Contractors.

Verify product for its compliance to approved data sheets drawings, witness testing as approved by ITP.

Coordinate with the Sub-Contractor’s department, testing units, equipment division and AUTOCAD department to oversee the work for speedy implementation of planning.

Review, check, study and familiarization with Contract documents, scope of work, codes, standards and Project Specifications provided by the Consultant/Client to ensure identification and comprehension of quality requirements.

Identify specific requirements in the contract, which require to be addressed separately and need to be controlled through specific procedures.

Review plans & report to the Consultant for any discrepancy or conflicts that will occur during the construction procedures based on actual site condition.

Reviews & approve documentation reports, contractor audits & other official reports to keep as final records.

Issues Internal Non-Conformance Report (NCR), to anyone-(Sub-Contractors) violating & not following the requirements as per Project Specifications, QCS 2010/2014, all pertinent Codes, Standards, etc.

Controls all Non-Conformance Reports (NCR), Site Observation Reports (SOR) & undertake remedial action. (Internally & as per issuance by the Consultant/Client)

Prepares Corrective Actions (CA) prior to closure of all NCR’s & SOR’s. FOR SITE RELATED WORKS DESCRIPTION:

(Coordination, Monitoring, Implementation, Progress, etc.)

Monitors & check testing inspection criteria and coordinate all inspection requirements.

Witness qualifying tests & determine the validity in accordance with regulations, codes, Project Specifications & procedures.

Monitors all quality related activities on the project.

Supervise other Sub-Contractors work activities & QA/QC personnel.

Implement Project inspection and test plans, collate inspection results, coordinate field inspection activities of and 3rd Party inspection agencies.

Prepare accordingly documents relevant to data control, inspection reporting procedure, technical queries and procedures for concessionary reports.

Identify quality problems, raise non-conformity report and liaise with various departments in identifying root causes for taking appropriate corrective and preventive actions and ensure their implementation.

Assist the Sub-Contractor to any problems encountered on-site basis

Supervision of all Architectural activities in the site with proper coordination on HVAC works, Plumbing, Drainage, Fire Fighting, Painting, Welding, Irrigation, LPG, BMS, Structural & Electrical works installation in coordination with the finishing works.

Monitoring, verifies, planning and interpret plans of project to see from every item of work is executed in accordance with the approved shop drawing plans, sections & details & approved coordination drawings.

Overall implementation & close supervision with regards to the quality completion & proper installation of all Architectural Works at site.

Monitor the progress & effectiveness of the project quality system. Recommend & implement improvements when required.

Coordinate with all the Quality Site inspections through the Consultant’s inspector.

Identify problems, pose plausible solutions & implement those solutions to achieve objectives for each project as assigned to.

Ensures that Quality Control Plans as per Contractor/Client’s expectations are followed religiously.

Attends all Architectural/Civil inspections, Operational, Functionality & Testing, etc. WORK EXPERIENCE:

COMPANY: TBK STAINLESS STEEL

ADDRESS: Street 48, Industrial Area

PROJECTS HANDLED: a) Burj Almana, Doha

b) Vendome mall, Lusail

c) Olympic Museum, Aspire Zone

d) AL NAKHEEL TOWER-West Bay, Doha, Qatar

POSITION: QA/QC- Engineer - Architectural & Fit-out INCLUSIVE DATE: NOVEMBER 20, 2017 up to FEBRUARY 2, 2019 JOB DESCRIPTION

Monitoring compliance to applicable codes, practices, QA/QC policies, performance standards and specifications

Interacting daily with the clients to interpret their needs and requirements and representing them in the field

coordinate, monitor Engineering process in line with main target programme of work

Preparation of method statement submittals in with safety standards and company HSE plan

Manage preparation of material submittals process in line with contract specifications

Internal and external aluminum, stainless steel, Steel, glass, ACP works

To monitor QA/QC related activities of the projects during the execution of Aluminum Curtain Walls, Skylights, Aluminum Composite Panels, Doors and Windows.

To ensure that all installed Aluminum, Stain less steel Accessories, Gaskets and etc. are accordance with the specified material.

Preparing, scheduling, coordinating and monitoring the assigned engineering projects.

Monitoring compliance to applicable codes, practices, QA/QC policies, performance standards and specifications

Interacting daily with the clients to interpret their needs and requirements and representing them in the field

Raising all site related correspondences with the contractor. FOR TECHNICAL REVIEW/CHECKING OF DOCUMENTS:

Prepares Method Statement (MS) & Inspection Test Plan (ITP).

Reviews, checks, edit, make comments, rejects, revise & re-submits, Method Statements (MS) submitted by Sub-Contractors/Suppliers, prior for submission to Consultant/Client, in order to obtain approval.

Reviews, checks & edit, rejects, revise & re-submits, Inspection Test Plans (ITP’s) submitted by Sub- Contractors/Suppliers prior for submission to Consultant/Client, in order to obtain approval.

Evaluates, check & reviews proper submittal of Technical Material Proposals-(Pre-Qualifications, Material Submittals, shop drawings, etc.)

Evaluates, check & reviews proper submittal of Technical Mechanical shop drawing plans. As to be in accordance with the Design criteria/codes, standards, project specifications as primarily required.

Review Material Test Certificates, Inspection and Test Reports, and Manufacturer’s Data Records.

Ensure calibration and maintain calibration records for inspection, measuring and test equipment for the Company, Project and that of the Sub-Contractors.

Verify product for its compliance to approved data sheets drawings, witness testing as approved by ITP.

Coordinate with the Sub-Contractor’s department, testing units, equipment division and AUTOCAD department to oversee the work for speedy implementation of planning.

Review, check, study and familiarization with Contract documents, scope of work, codes, standards and Project Specifications provided by the Consultant/Client to ensure identification and comprehension of quality requirements.

Identify specific requirements in the contract, which require to be addressed separately and need to be controlled through specific procedures.

Review plans & report to the Consultant for any discrepancy or conflicts that will occur during the construction procedures based on actual site condition.

Reviews & approve documentation reports, contractor audits & other official reports to keep as final records.

Issues Internal Non-Conformance Report (NCR), to anyone-(Sub-Contractors) violating & not following the requirements as per Project Specifications, QCS 2010/2014, all pertinent Codes, Standards, etc.

Controls all Non-Conformance Reports (NCR), Site Observation Reports (SOR) & undertake remedial action. (Internally & as per issuance by the Consultant/Client)

Prepares Corrective Actions (CA) prior to closure of all NCR’s & SOR’s. FOR SITE RELATED WORKS DESCRIPTION:

(Coordination, Monitoring, Implementation, Progress, etc.)

Follow, monitor and perform material as well with work inspection and ensure that inspection and tests are carried out as per the approved ITP and approved procedures.

Monitors & check testing inspection criteria and coordinate all inspection requirements.

Witness qualifying tests & determine the validity in accordance with regulations, codes, Project Specifications & procedures.

Monitors all quality related activities on the project.

Supervise other Sub-Contractors work activities & QA/QC personnel.

Implement Project inspection and test plans, collate inspection results, coordinate field inspection activities of and 3rd Party inspection agencies.

Prepare accordingly documents relevant to data control, inspection reporting procedure, technical queries and procedures for concessionary reports.

Identify quality problems, raise non-conformity report and liaise with various departments in identifying root causes for taking appropriate corrective and preventive actions and ensure their implementation.

Liaise with Third Party Inspection/Certification agencies and external labs for inspection, testing and audits.

Discuss and resolve any problem that may arise during work. Attending and discussing with the Consultants any particular design problem that arises in conflict from the actual condition.

Checks thoroughly all Architectural installations from time to time in adherence to the approved shop drawing plans, materials & standard codes.

Assist the Sub-Contractor to any problems encountered on-site basis

Supervision of all Architectural activities in the site with proper coordination on HVAC works, Plumbing, Drainage, Fire Fighting, Painting, Welding, Irrigation, LPG, BMS, Structural & Electrical works installation in coordination with the finishing works.

Monitoring, verifies, planning and interpret plans of project to see from every item of work is executed in accordance with the approved shop drawing plans, sections & details & approved coordination drawings.

Overall implementation & close supervision with regards to the quality completion & proper installation of all Architectural Works at site.

Monitor the progress & effectiveness of the project quality system. Recommend & implement improvements when required.

Coordinate with all the Quality Site inspections through the Consultant’s inspector.

Identify problems, pose plausible solutions & implement those solutions to achieve objectives for each project as assigned to.

Ensures that Quality Control Plans as per Contractor/Client’s expectations are followed religiously.

Attends all Architectural/Civil inspections, Operational, Functionality & Testing, etc. PROJECTS HANDLED IN QATAR

(UNDER MMJV, DOHA EXTRACO AND TBK STAINLESS STEEL) MIDMAC MIC CONSTRUCT

LUSAIL PLAZA TOWER

DOHA EXTRACO

Commercial Boulevard Lusail

TBK STAINLESS STEEL

Burj Almana



Contact this candidate