Robert Helou

Electrical Engineer

With more than 25 years of electrical engineering experience, I reached the level of Senior MEP project manager in the construction field. Starting as site electrical engineer, I used to develop shop drawings and follow up with the teams on site. As MEP coordinator, I elaborated the Composite drawings after deep coordination with all subcontractors to insure smooth installation for all MEP systems. I have lead QA/QC MEP team in scrutinizing, monitoring, and verifying quality control. I acquired expertise in testing and commissioning of diverse systems. I guaranteed hand- over of completed project to clients and relevant authorities within agreed schedules. Moreover, I followed trainings in Safety Fire Alarm Systems NFPA72, Hazard Identification & Risk Assessment and Environmental Aspect & Impacts, ERP from Microsoft Dynamics 360 and Project Management Professional (PMP). I am confident in delivering impeccable results through my dedication to handling multiple functions and activities under high-pressure environments & tight deadlines. Contact Professional Experience

Address: Doha, Qatar

Phone: +974-**-******

Email: adz59n@r.postjobfree.com

LinkedIn: robert-helou-8290121

Nationality: Canadian /Lebanese

Resident Visa: Qatar

Education

2012 – Present

Advanced Engineering for Maintenance & Contracting (AEMC) Qatar Senior Electrical Engineer/ MEP Project Manager

Streamline project management operations from inception to conception and attain set targets. Create strategic plans to control construction expenses, administer change control requests, and oversee commercial activities without comprising project integrity. Direct value analysis, draft documents by leveraging AutoCAD, MEP, and different software formulating technical reports regarding material. Attend meetings with owner to discuss product/services features.

Formulated preventive sheets for maintenance in line with NFPA and civil defence standards. Collaborated with civil defences department to execute new regulations and resolved escalated technical issues.

Scrutinizing subcontractors’/suppliers’ proposals, samples, submittals, shop drawing, method statements and technical data to sustain quality standards and eliminate problems, suggesting improvements and escalating unresolved issues for timely solutions.

Leading QA/QC MEP team in scrutinizing, monitoring, verifying quality control as per the project requirement, specification, optimizing installations and conducting material inspections as per acceptance criteria and international standards.

Testing and commissioning of diverse systems: Fire Alarm, PA system, CCTV, Wi- Fi active and passive, Nurse call, Queue management, parking management, SMATV and IP tv, Bus duct, Switch Gear, Transformers, power and lighting, lightning and earthing system, Aviation lighting, HVAC, fire protection, plumbing & drainage. Superintending hand-over of completed project to client & relevant authorities within agreed schedules.

Operation & Maintenance of various projects, preparing of preventative maintenance schedule & reports, supervising, training & assigning responsibilities for the maintenance team, assigning staff according to project requirements, coordinating and supervising of corrective maintenance team, on-site inspections for maintenance works to ensure quality.

Master of Science

Electrical & Electronic Engineering:

Lebanese University Faculty of Genie-

Lebanon

Professional Development

Training on Safety Fire Alarm Systems

as per the NFPA72

Hazard Identification & Risk

Assessment and Environmental

Aspect & Impacts

ERP from Microsoft Dynamics 360

Installation of a Station of Relay

between Aarbanieh Station

Programming out of Card ADA

Supplying Multiplexer of Scanner

Memberships

Member, Order of Engineers, Beirut,

Lebanon

Member, UPD Grad-A Engineer and Fire

alarm Certified Engineer Civil defence,

Qatar

Certificates:

Key Projects

AL Waab Dialysis and Diabetes Hospital. Budget of QR: 80 M Lusail Mosque, Masjed Lusail: Budget of QR: 9M

AL MANAA HOTEL: Budget of QR: 20M

Marina Com27 Lusail: Budget of QR: 45M

Marina Res11 Lusail: Budget of QR: 50M

Al Manaa Headquarter: Budget of QR: 25M

01 Mall, and 03 Mall: Budget of QR: 15M each

Centro Mall: Budget of QR: 65M.

PMP, Project management professional

Technical Proficiencies 2008-2012

JSL E&M Engineering, Lebanon (Electrical Engineer Project Manager) Iraqi Embassy, Lebanon

Budget: $350K • Team Size: 1 Site Engineer & 50 Labours, Methodology/Tools: Auto- CAD

Drove electrical work installation as well as devised and implemented effective fire alarm system strategy for telephones, FIDELIO, and control of medium voltage groups.

Co-ordinated with trade, mechanical, civil co-ordinators, and client representative engineers for managing electrical work and delivering to consultant. Windows

Microsoft office

AutoCAD

Ecodial

Internet Explorer

Microsoft Outlook

Outlook Express

Primavera

MS Project MCSE

ERP

Languages

2007-2008

LIMA Immobilier, France (Project Manager)

In charge of many sites, for a Budget: € 1.5M • Team Size: 2 Engineers and more than 50 Labours. Roles: Manage renovation tasks of buyers’ property, including electrical, plumbing, gypsum boards, painting, windows, and doors Arabic: Native

French: Proficient

English: Proficient

Areas of Expertise

2004-2007

RCG International Global company, (Freelancer Engineer)

Providing an efficient & specialized services of handing over and maintenance in: 1- Saudi Arabia (2005 High Voltage Substations handing over), 2- France (2004 Rail Transport Alstom testing and commissioning),3- Canada (2006-2007 Marine Electrical Propulsion maintenance).

Staff Building & Leadership

Contract Negotiations

Electrical Control Development

Project Management

Strategic Planning & Analysis

Project Life-cycle Management

Electrical Engineering

Health & Safety Standards

Risk Identification & Mitigation

Budgeting & Cost Reduction

Preventive Maintenance

Commissioning Engineering

2000-2002

MID contracting, Lebanon (MEP coordinator)

Royal Hotel & Aqua Park,

Budget: $1.5M Team Size: 5 Engineers & 6 Sub-Contractors • Methodology/Tools: Auto- CAD

Headed elaboration of MEP coordinated drawings.

1998-2000

Charles Khoriaty & Co, Lebanon (Site Electrical Engineer) Hotel at Mouawad Village Bourmana

Budget: $400K Team Size: 1 Site Engineer and 50 Labours • Methodology/Tools: Auto-CAD

Co-ordinated with others, mechanical & civil, co-ordinators, to elaborate the Electrical shop drawings as well as following on site the progress and material purchasing.