Post Job Free

Resume

Sign in

Project Manager Treatment Plant

Location:
Al Dafna, Qatar
Posted:
August 09, 2023

Contact this candidate

Resume:

Curriculum Vitae

Mail: adyta5@r.postjobfree.com Ph:974-********

Name:

Nanda Gowdar Lokeshwarappa

Age:

** *****

Nationality:

Indian

Personal Profile/Overall experience:

With over 29 years of experience and a highly talented, results-driven

Engineering Professional as a Process & Mechanical engineering with exposure to EPC contracts. Experienced in preparing Basic & Detailed Engineering Design in the field of Storm/TSE/Potable water & Wastewater Pump station, Reverse Osmosis, Sewage Treatment, Industrial waste water treatment Plant, Utility &Desalination. Knowledge of HVAC & firefighting Building services

Start up and commissioning and Management Skills in managing all aspects of engineering & project coordination.

Recognized for excellent communication, management, and leadership skills.

Over 28 year experience within the field of Engineering & Projects, including:

Process & mechanical Design

Presentations

Follow up Structure of works

Start up and commissioning.

Training

Technical Consultancies

SKILLS & ABILITIES

Experience in working with Project management Including Budget Development, Project planning & Finance.

Demonstration of excellent communication skills verbal & writing.

In depth Knowledge of Project execution /Goals /strategies/risks & opportunities.

Presentation skills for interaction with client & Internal team

Ability to interact with people.

Excellent Computer Skills strong Knowledge of MS word/Excel/Auto Cad/Navis work/Cad works.

Excellent Technical Skills with problem solving & creativity

Strong Organizational skills to balance & prioritize skills & ability to work Under pressure

Role in Metito: 2008-2023

Project Engineer & Engineering Coordination – 4years

Project Manager – 6 Years

Engineering & Design Team Leader – 5 years

Location:

Qatar, Doha

Key Responsibilities:

Project Management + Engineering Coordination under Project Department.

Design Team Leader under design Department

Length of Service in Metito:

15 years

Education:

Bachelor in Mechanical Engineering

Functional Experience:

2008-2021

K-PACK SYSTEM PVT.LTD 1993- 2008

Apply sound engineering principles in the development and documentation of the product.

Experience in Process Design Calculation & System design of API/CPI/TPI/DAF (CIRCULAR & RECTANGULAR) Separators. Preparation of Assembly GA & fabrication Drawing.

Experience in Process design Calculation & System design of Lamella Separators. Preparation of Assembly GA & fabrication Drawing.

Experience in Process design Calculation & System design of IGF Separators. Preparation of Assembly GA & fabrication Drawing.

Preparation of Process &controls description for API/CPI//TPI/DAF/Lamella/IGF.

Experience in Testing & commissioning for API/CPI/TPI/DAF/Lamella/IGF oil in water separator.

Experience is process & mechanical design of Air saturation Pressure vessels for DAF System.

Experience is Process Design Calculation & System design & Mechanical design Flash Mixers/Tank Flocculators /Pipe Flocculator for primary treatment plants.

Experience on rotating Equipment’s like pumps (submersible Pump (Wet well & dry well Installation)/Horizontal centrifugal pumps & Positive displacement pumps) Compressors, Blowers, Agitator or Mixers, Gear Boxes & Motors.

Experience on static such as Pressure vessels /heat exchangers, storage tanks, heaters, Piping systems, Valves & other package equipment.

Responsible for preparation of specification /Drawings & technical data sheet, requisition for quotation, review of vendors offers, Technical queries, technical bid Analysis, approval of vendor & contractor drawing/Documents.

Well acquainted with National and International Codes and Standards like ASME, ASTM, API, AISC etc.

Roark’s Formula for Stress & Strain Calculations for rectangular tanks

Review of 3D model & Piping stress Analysis Reports & calculations

Provide direct instruction and guidelines for team of designers to ensure effective delivery of projects and tasks to meet the deadlines and to design in compliance with international standards, project specifications, QHSE requirements and local regulation.

Study project specifications and drawings and prepare summary of key points for quick reference during detailed design.

Review of Design &Deliverables prepared by engineers & ensure its compliance with Project specification& QCS 2014 requirements.

Provide technical support to external and internal customers.

Support sales team in pre-sales technical concept and budgeting activities.

Interpret client requirements, identify and address design parameters and engineering problems and ensure solutions are implemented accurately and in budget.

Analyse project requirements and perform technical calculations supporting design.

Create accurate Bill of Materials.

Define equipment and parts from external suppliers.

Conduct cost estimation.

Preparation of training Manual & presentation to operating team.

Specialized in oil in water treatment process Equipment’s.

Process & Mechanical design of primary treatment plant.

15 years, experience in Process Design Calculation & System design of oil in water separators, Preparation of Mechanical design calculations, GA & Fabrication drawing, Installation, Testing & commission of API/TPI/CPI/Lamella/DAF/IGF separators.

Experience in Process Design Calculation & System design of oil in water separators, GA & Fabrication drawing, Installation, Testing & commission of

Flash Mixers/Tank Flocculators /Pipe Flocculator / Air Saturating Pressure vessel /Screw Conveyors.

Experience in Process Design Calculation & System design of oil in water separators, GA & Fabrication drawing, Installation, Testing & commission of Course & Fine Screens (Rectangular & Basket /Drum screen).

Review of Rotating Equipment such as Gear box, Motors, oil skimmers, Screw Conveyors, Belt Conveyors, Pump’s & Compressors.

Working Experience on preparation of technical data sheet for static equipment /rotating & Valves

Preparation of proposals for sales.

Negotiation & Finalization of sales prices with client.

Presentation of primary treatment plant & Oil Separation equipment to client before sales.

Preparation of Process & Mechanical Design & Drawings.

Negotiation & Finalization of rates with subcontractor & fabricators & Equipment suppliers.

Site visits to facilitate Installations and commissioning of the equipment.

Preparation of Training Manuals & Presentation

Quality control & preparation of MDBR (Manufacturers Data Book Records)

RASLAFFAN PETROCHEMICAL PROJECTS(RLPP)

Client : RLIC

Location : Raslaffan (Qatar)

Process : Extended Aeration (SBR)

Sewage Treatment Plant Capcity : 4350 m3/day

Responsibility : Project Engineering Manager

Leading the Technical /Design Review meetings.

Leading Engineering progress Meetings & Responsibility on the project schedule.

Review & finalizing of all Engineering Documents

Review of Offers & finalizing the offer technically & Suggestion.

On the prizes to project department.

Review of Purchase Orders and sign off from Engineering side.

Leading & taking the responsibility to answer the questions raised by the client during the HAZID/HAZOP/SAPOFF study.

Review & leading the close out meetings of HAZID/HAZOP/SAPOFF documents issued from 3rd party consultants.

Leading the 3D modelling review and suggesting the way out for the clarification raised during the meeting

Technical & Commercial Coordination with Project team/Vendors.

Finalization of technical offer & Review of Purchase Order with the project engineers.

BARWA CITY SEWAGE TRETMENT PLANT

Client : ASHAGAL

Location : Doha, Qatar

Sewage Treatment Plant Capcity : 4392m3/day & 8760m3/day

Process : Extended Aeration (SBR)

Responsibility : Team Leader Engineering

& Design & Project Engineering

Attend Technical /Design Review meetings.

Review of Design & Technical Submittal as per Project specification.

Preparation of equipment Layout & Civil out line drawings.

Preparation & Review of engineering deliverable & Schedule.

Review of piping layout, review of Isometric drawing.

Attend meeting with manufacturer finalize equipment technical issues.

Responsibility to solve issue at site during construction & Commissioning.

Technical & Commercial Coordination with Project team/Vendors.

Finalization Of offer & Review of Purchase Order

QP MESAIEED DRAINAGE PHASE-1 (Surface Water Drainage System)

Client : Qatar Energy

Location : Mesaieed Industrial Area (QATAR)

Pump station Capacity GWPS1 : 9720 m3/day

Pump station Capacity GWPS2 : 11,712 m3/day

Pump capacityof 405m3/hr. for GWPS1 & 488 m3/hr. GWPS2

Responsibility : Team Leader Mechanical Engineering

& Design Coordination with Design Consultant QDC

Review of Detail Design & Drawings

Review

Preparation on & review of Design Speciation for all Equipment/Pipes/Valves/ Pumps Etc..

Pump design, Manufacture Construction & installation as per QCS 2014 Section 9 Part 2

Preparation of data sheet & Technical review of :

-Submersible Pump Capacity 140 l/sec (2Duty & 1Stand By )

-DI Pipes & fittings as per BS EN 545complying to QCS 2014 Section 8 Part 3 Pipe size ranging from 200- 900 Dia.

-Valves as per BS EN 593 complying to QCS 2014 Section 8 Part 5.

-Air release valves double orifice complying to QCS 2014 Section 8 Part 5.

-Penstock technical submittal Review & Installation details complying to QCS 2014 Section 8 Part 5.

Technical & Commercial Coordination with Project team/Vendors.

Finalization Of offer & Review of Purchase Order

SMELTER PLANT

Location : INDONESIA

Desalination Plant capacity : 3891m3/hr.

Responsibility : Team Leader Engineering

& Design& Project Engineering

Review of Design & Deliverables as per Project specification.

Attend technical /Design Review /3D Model review meetings.

Preparation of equipment Layout & Civil out line drawings.

Preparation of engineering deliverable & Schedule.

Review of Technical data sheet for Static equipment’s like gravity multimedia filters /lamella clarifier RO system/Energy Recovery system/Cartridge filters /Pumps/Blowers /mixers & valves

Attend progress meetings take decision on the schedule.

WASTE WATER TREATMENT (RLOC)

Client : RLOC

Location : RASLAFFAN (QATAR)

Grey Water Treatment Plant Capacity : 4350 m3/day

Process : MBBR

Responsibility : Team Leader Engineering & Design& Project Engineering

Process, System & mechanical design of DAF & Pipe Flocculator System.

Review of Design & deliverables as per Project specification.

Attend technical /Design Review /3D Model review meetings.

Preparation of equipment & Civil out line drawings.

Preparation of engineering deliverable & Schedule.

Preparation & review of Technical data sheet for Static equipment’s /Pumps/Blowers /mixers & valves

Preparation of Technical data sheet & review of Horizontal centrifugal Pump in accordance to ANSI B 73.1

Preparation of Technical data sheet & review of Progressive Cavity pump Design, Manufacturing Standard API 676 & API 675

Guiding the engineering team in the preparation of the Gate valve & Butterfly valve data sheet as per API 600 & ASME B16.34/API 609

Review of vendor proposals as per the technical requirement & Specification

3D Model Review

Coordination with contractor for technical approval of engineering Documents.

UM AL HOLUL FREE ZONE

Client : Manatec Real Estate

Location : Um Haloul Free Zone

-Sewage Lift Station

-Firefighting Pump station.

-TSE Water Pump Station

-Potable water Pump station

Responsibility : Project Engineering Manager & Design Coordination with Design Consultant KEO.

Review of Detail Design & Drawings

Pump design, Manufacture, Construction & installation as per QCS 2014 Section 9 Part 2

Preparation of data sheet & Technical review of :

Submersible Pump Capacity 60 l/sec (2Duty & 1Stand By )

Split Casing Horizontal centrifugal pump Capacity 150 l/sec & 215 lts./sec (3 Duty & 1Stand By ) complying to QCS 2014 Section 9 Part 4

DI Pipes & fittings as per BS EN 545complying to QCS 2014 Section 8 Part 3 Pipe size ranging from 200- 900 Dia.

Butterfly valves as per BS EN 593 complying to QCS 2014 Section 8 Part 5

Air release valves double orifice complying to QCS 2014 Section 8 Part 5

Penstock technical submittal review & installation details complying to QCS 2014 Section 8 Part 5

Preparing engineering deliverables schedule.

Review of hydraulic calculation.

Review of Pump technical submittal

Guiding mechanical engineer responsible in preparation of Detailed Mechanical Layout Drawings, Piping drawings Etc...

Managing to resolve technical issues during engineering & during installation.

Preparation of operation & Maintenance training manual & presentation on site to operation team.

Technical & Commercial Coordination with Project team/Vendors.

Finalization Of offer & Review of Purchase Order

WASTE WATER REDUCTION & RECYCLE PROJECT

Industrial Waste Water Treatment Plant

1.Sand filtration System

2.ACF & RO(Reverse Osmosis) System.

3.Nutshell filter

4.MBR system

5.Sludge treatment system (Oily sludge & Bio Sludge)

6.ZLD (Zero discharge Unit for Qatar Gas)

Client : RLIC

Location : RASLAFFAN (QATAR)

WWTP : Different Capacities

Responsibility : Project Engineering Manager

Review of Design &deliverables as per Project specification.

Attend technical /Design Review /3D Model review meetings.

Preparation of equipment & Civil out line drawings.

Preparation of engineering deliverable & Schedule.

Preparation & review of Technical data sheet for Static equipment’s /Pumps/Blowers /mixers & valves

Preparation of Technical data sheet & review of Horizontal centrifugal Pump capacity 330 m3/hr to 63 m3/hr. Design & manufacture in accordance to ANSI B 73.1

Preparation of Technical data sheet & review of Progressive Cavity pump ranging from 10 m3/hr. to 5 m3/hr. Design, Manufacturing Standard API 676 & API 675

Guiding the engineering team in the preparation of the Gate valve & Butterfly valve data sheet as per API 600 & ASME B16.34/API 609

Review of vendor proposals as per the technical requirement & Specification

3D Model Review

Review of Piping stress calculations.

Coordination with contractor for technical approval of engineering Documents.

Technical & Commercial Coordination with Project team/Vendors.

Finalization Of offer & Review of Purchase Order

EAST INDUSTRIAL AREA (Al Rayan Stadium) Pump Station

Client : Ashghal

Location : Doha, Qatar

Capacity : 110 m3/hr.

Responsibility : Project Engineering Manager

Review of Design & deliverables

Pump design, Manufacture, Construction & installation in accordance QCS 2014

Preparation Data sheet & Technical review

Review of Design &deliverables

Preparing engineering deliverables schedule.

Review of hydraulic calculation.

Review of Pump technical submittal

Guiding mechanical engineer responsible in preparation of Detailed Mechanical Layout Drawings, Piping drawings Etc..

Manging to resolve technical issues during engineering & during installation.

Preparation of operation & Maintenance training manual & presentation on site to operating team.

Attend technical & Project related meetings.

Preparing engineering /project deliverables schedule.

Issue of Contractual letters

Preparation of Budget for the project.

Review of vendor proposals as per the technical requirement

Release of PO to the Vendors /suppliers Manufacturer

Review of Piping GA drawing

Finalize designs to meet project requirements.

Coordination with contractor& Consultant for technical approval of the engineering & equipment deliverable.

Site Installation coordination.

Manging to resolve technical issues during engineering & during installation.

Technical Assistance & Coordination with commissioning team during Testing & Commissioning

Preparation of Invoices.

LUSAIL PUMPING STATION

SW4/RPS1/RPS4/IR3

IR4/SW1

Client : Ashghal

Location : Lusail, Qatar

Capacity : Pumping station 6 Nos

-SW4 – Storm water Pump Station+ raising main out fall to the sea Capacity 600lts/sec.

-SW1- Storm Water Pump Station + raising main out fall to the sea Capacity 1750 lts /sec.

-IR3&4 –Irrigation Pump Station Capacity 150lts/sec

-RPS1 & 4 PW Pump Station Capacity 125 to 250lt/sec

Responsibility : Project Manager & Design Engineering Coordination with Design consultant

Review of Design &deliverables.

Pump Design, Manufacture, Construction & installation as per QCS 2014 & Project Spec.

Preparation of data sheet & Technical review of all Equipment’s.

Attend technical & Project related meetings.

Preparing engineering /project deliverables schedule.

Issue of Contractual letters

Preparation of Budget for the project.

Review of vendor proposals as per the technical requirement

Release of PO to the Vendors /suppliers Manufacturer

Review of Piping GA drawing

Finalize designs to meet project requirements.

Coordination with contractor& Consultant for technical approval of the engineering & equipment deliverable.

Site Installation coordination.

Manging to resolve technical issues during engineering & during installation with design consultant Hal crow.

Technical Assistance & Coordination with commissioning team during Testing & Commissioning

Preparation of Invoices.

MESSAIEED IPP A PROJECT

Sewage (STP)treatment plant

Client : Iberdrola/ Messaieed Power station

Location : Doha, Qatar

Capacity : 70 m3/hr.

Process : MBBR

Responsibility : Project Manager & Engineering Coordination

Attend Project & Engineering Technical Review Meeting

Preparing Engineering & Project Deliverable schedule

Review of Design & deliverables as per QCS 2014

Coordination for equipment deliverable with Suppliers

Finalizing with suppliers and issuing purchase orders.

Assisting site Installation team

Technical Assistance & Coordination with commissioning team during Testing & Commissioning

Preparation of Invoices.

WASTEWATER TREATMENT PROJECT

Grey water treatment Plant & RO (Reverse Osmosis) unit

Client : UDC/St. Reghis Hotel

Location : Doha, Qatar

Capacity : 50 m3/day.

Responsibility : Project Manager & Mechanical Engineering lead

Attend Project & Engineering Technical Meeting

Preparing Engineering & Project Deliverable schedule

Review of Design & deliverables as per QCS 2014

Coordination for equipment deliverable with Suppliers

Finalizing with suppliers and issuing purchase orders.

Assisting site Installation team

Technical Assistance & Coordination with Commissioning team during Testing & Commissioning

Preparation of Invoices.

STP TREATMENT PLANT

Client : MANATEQ

Location : Um Halul, Qatar

Capacity : 800 m3/day.

Process : MBBR

Responsibility : Project Manager & Mechanical Engineering lead

Review of Design &deliverables as per Project specification.

Preparation of equipment & Civil out line drawings.

Preparation of engineering deliverable & Schedule.

Review of vendor proposals as per the technical requirement & Specification

Preparation of static & Rotating & Piping & Valves equipment technical data sheet

Coordination with contractor for technical approval of engineering Documents.

INDUSTIRAL WASTE WATER TREATMENT SYSTEM

Primary treatment plant for oil water Seperation

Client : Cairn Energy

Location : Rajahmundry INDIA

Capacity : 200 m3/hr..

Responsibility : Senior Executive Engineer

Prepration of Proposals & attending Negotiation with client

Fianlizing of order with the client

Attend Project & Engineering Technical Meeting

Preparing Engineering & Project Deliverable schedule

Review of Design & deliverables as per project specification

Coordination for equipment deliverable with Suppliers

Finalizing with suppliers and issuing purchase orders.

Assisting site Installation team

Technical Assistance & Coordination with commissioning team during Testing & Commissioning

INDUSTIRAL WASTE WATER TREATMENT SYSTEM

Primary treatment plant for oil water Seperation

Client : Bechtel /OGD-3

Location : UAE- Designed in India under K-Pack

Capacity : 150 m3/hr..

Responsibility : Senior Design Engineer

Prepration of Proposals & attending Negotiation with client

Fianlizing of order with the client

Preparing Process design Calculations

Equipment sizing Calculations.

Review of P&ID & Equipment data sheets

Preparing Engineering & Deliverable

Attend Engineering Technical & Project Meeting

Review of Design as per Project Specification

Preparation of static & Rotating & Piping & Valves equipment technical data sheet

Coordination for equipment deliverable with Suppliers

Finalizing with suppliers and issuing purchase orders.

Assisting site Installation team

Technical Assistance & Coordination with commissioning team during Testing & Commissioning

INDUSTIRAL WASTE WATER TREATMENT SYSTEM

QCLNG Primary treatment plant for oil water Seperation

Client : Bechtel/ Queens lands Curtis LNG

Location : Australia Designed India Under K-PACK

Capacity : 150 m3/hr..

Responsibility : Senior Design Engineer

Prepration of Proposals & attending Negotiation with client

Fianlizing of order with the client

Preparing Process design Calculations

Equipment sizing Calculations.

Review of P&ID & Equipment data sheets

Mechanical design calculations & related equipment Drawings.

Layout drawings Preparation of static & Rotating & Piping & Valves equipment technical data sheet

INDUSTIRAL WASTE WATER TREATMENT SYSTEM

Primary treatment plant for oil water Seperation

Design/ Supply & Testing Commissioning of Equipemts

Client : ONGC / HPCL/ CAIRN ENERGY/GAIL

INDIAN OIL PLATFORM AREA

UEM Delhi

Hindustan Dorr Oliver (Chennai/Mumbai)

Vatch Wabag (Chennai)

Veatech (Poona)

Location : All project sites in India

Capacity : 150 m3/hr.

Responsibility : Senior Design Engineer

Prepration of Proposals & attending Negotiation with client

Fianlizing of order with the client

Preparing Engineering & Deliverable

Attend Engineering Technical & Project Meeting

Review of Design as per Project Specification

Preparation of static & Rotating & Piping & Valves equipment technical data sheet

Coordination for equipment deliverable with Suppliers

Finalizing with suppliers and issuing purchase orders.

Assisting site Installation team

Technical Assistance & Coordination with commissioning team during Testing & Commissioning



Contact this candidate