* * * * * R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N

Ts. MOHD YUSOF BIN RAHMAD TULAHAN, P.Tech (BC)

Professional Technologist (Building and Construction Technology) BACHELOR OF DEGREE OF MECHANICAL ENGINEERING (HONOURS) UNIVERSITY OF TECHNOLOGY, MALAYSIA

Date of graduated : 27th August 1994

HOD-M & E, Salary : RM15,000

Membership status :

Professional Technologist, (Malaysia Board of Technologists) Mechanical Engineer, Graduate (Board of Engineers, Malaysia) Mechanical Engineer, Graduate (The Institution of Engineers, Malaysia) Mechanical Engineer (Construction Industrial Development Board, Malaysia) Competent Wireman, PW1 (240V) (Suruhanjaya Tenaga, Malaysia) Permanent address:

Lot 771, Jalan Besar, Kampung Jaya Setia, Bestari Jaya, 45600 Batang Berjuntai, Selangor, Malaysia.

Email: adyrzu@r.postjobfree.com

Mobile Phone: +6-016-***-****

Identity Card (Malaysia): Current 700***-**-****, Previous A1584939 International Passport (Issued from Malaysia): A54676771 Age: 53 years old.

Updated: 16th July 2023

Registration to government and institution:

1. Mechanical Engineer at Board of Engineers, Malaysia - Graduate Reg.: GE24346A

(1995)

2. Mechanical Engineer at The Institution of Engineers, Malaysia – Graduate Reg.: G64791

(2014).

3. Mechanical Engineer, CIDB, Malaysia– ID: W41170520020019 Valid until 9 July 2023 4. Electrical Competent Wireman (ST), JBE No: PW-T-1-B-0721-2001 2 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N 5. Professional Technologist, Malaysia. Certificate No. PT22040013 Education:

Bachelor of Degree of Mechanical Engineering (Honors). Universiti Teknologi Malaysia

(1989-1994)

Experiences

1. Five years in Project Management of M&E, nineteen years in Project Engineering of M&E, three years in Consultation of M&E, Architectural and Civil for building services and infrastructural and one year in Lead Consultant (Khairi Consult Sdn Bhd) since 1994 until 2023. Preparation of Tender Drawings, Specification, Cost Estimation, Design Calculation used MS-Excel and software (Carrier Room Heat Load Calculation - E20-ii / HAP), (Daikin Heat Load Calculation - DS-HL2),, Cold and Hot Water Plumbing, Sprinkler and Hose reel System (Hazen & Williams), Services Coordination between Architectural, Civil, Mechanical and Electrical & Execution, Preparation of Shop Drawings & Coordination Drawings, Drafting (AutoCAD 2019), and supervision of installation Building Services Mechanical, Electrical (240V, 415V, 11KV and 33KV), Extra Low Voltage (24V), Architectural and Structural. Teach the building management team and maintenance team for familiarization of the services in the building and infrastructural.

2. Hand-on design and drafting, installation, testing and commissioning of Sub-Switch Board (SSB), Distribution Board (DB), Switch-Fuse (SF) 60 Amperes, 30 Amperes, Residual Current Circuit Breaker (RCCB), Miniature (MCB), 10 Ampere, 16 Ampere, 32 Ampere, light fittings, fan, 13A SSO, 15A Air Conditioner point. Cable sizing and circuiting for single phase, 240V.

3. Coordination, design, installation, testing, commissioning, integration and handover of Heating System, Mechanical Ventilation System, Air Conditioning System (HVAC), Cold and Hot Water Plumbing, Irrigation, Sanitary Plumbing, Fire Alarm and Fire Fighting Systems, Lifts & Escalators (Kone, MS-Elevator, Schindler and Sword ), Building Security System & Building Automation (Johnson Control and Trane), Telecommunication (TM, Maxis, Celcom, Digi, Time.Com), Gas Piping (Petronas), Electrical Power Distribution 33 KV, 11 KV, 415 V, 240 V and ELV (24V) for Buildings and Infrastructure.

4. Value Engineering review and proposal (VE), Heat Load Calculation for Air- Conditioning system, preparation of shop drawing and submission to main contractor and M&E Consultant. Coordinated and supervised commercial buildings projects in mechanical, electrical, architectural and civil.

5. Coordination and liaison with the Authorities, Clients, Architects, Quantity Surveyors, Engineers, Project Management Consultants, Main-Contractors, Sub-Contractors, 3 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N Suppliers and workers for the works execution and solving of any technical and contractual issues.

6. Heat Load Calculation and Design of air conditioning system for three (3) storey boy primary school used air-cooled package system direct expansion Air Handling Unit

(AHU) to Condensing Unit (CU) 40 Tons.

7. Proposed MEP services for buildings for air conditioning system, mechanical ventilation system, fire alarm, fire protection, vertical transportation, Telco, ICT, ELV, LV and HV, cold and hot water plumbing, water tanks and pumping, LPG piping, BCS and BAS. 8. Coordinated of Civil and MEP infrastructural inclusive SCADA (Supervisory Control and Data Acquisition). Site inspection of installed gates etc. for Kuala Lumpur Flood Mitigation project under Department of Water and Irrigation. My Offer

1. To work for an established Employer for Building Developer, Project Management Consultant, Project Delivery Partner, Detail Design Consultant or Supervising Consultant for Design, Coordination and Supervision of Mechanical, Electrical and Plumbing Services. It is inclusive Engineering Calculations (E20 MS-Excel, Daikin DS-HL2, Daikin Xpress and Carrier E20-ii / HAP, Review InEight TeamBinder), standard proposal, produce tender drawings in AutoCAD 2019 and Cost estimation. The services are HVAC, Fire Alarm & Fire Fighting Systems, Lift & Escalator, Electrical & Electronics, Cold & Hot Water Plumbing, Sanitary Plumbing, Water Reticulation, Rain Water Harvesting Systems and Irrigation.

2. To interface or coordinate between external, structural, architectural and M&E [(Inclusive Design of Heating, Ventilation, Air Conditioning and Refrigeration system) Fire Alarm System, Fire Fighting System (Sprinkler, Hose Reel, Dry Riser & Wet Riser), Vertical Transportation System (Lift, Escalator & Travelator), ELV (Building Automation System, Audio Visual System, Close Circuit Television (CCTV), Information Communication Technology System, Wi-Fi, Public Addressable System, High Voltage System (33 KV Switch Gear, 11 KV & Transformers), MSB and LV Distribution (Lighting and Small Power), Telecommunication, Earthing & Lightning Protection System (ELP), Cold and Hot Water Plumbing Systemand, Sanitary Plumbing System, Rain Water Harvesting System, Kitchen Equipments, Liquefied Petroleum Gas System (LPG)] 3. To prepare engineering calculation by Heat Load Calculation and Psychrometric chart, Equipment Selection, Duct and Pipe sizing.

4. To coordinate the Combined Services Drawing (CSD) at RCP and rearrange as BOMBA’s law, camera’s best view, lighting lux equal distribution and achieveable clearance ceiling to structural.

4 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N 5. To complete the tasks given by Employer within schedule, budget and approved material’s quality and method statement and ITP.

6. To advise Employer the standards for Mechanical & Electrical Systems, Technical Specification (BS / AS / EN / MS / JKR / Local Authorities / Service Provider etc) 7. To liaise with all the Local Authorities (Fire Protection Authorities - BOMBA, Water Supply – AIR SELANGOR, Sewerage - IWK, Electric - TNB, Safety Department - DOSH / JKKP, Telecommunication-TM, Maxis, Celcom, Digi, Time. Dot. Com and Gas- Petronas) for Mechanical & Electrical approval.

8. To coordinate with all level of internal staffs, architects, engineers, quantity surveyors, land surveyors to solve any issues raised by any division. 9. To estimate the cost of Mechanical, Electrical and Plumbing systems, and prepare evaluation report and presentation.

10. To participate in the progress and technical discussion and meeting with main-contractor, PMC, consultant and developer and to provide solutions and prepared report to management.

11. To make preliminary design, coordination, discussion, detail designs, bill of quantities, tender, negotiation, construction drawings, progress meeting, integration, testing and commissioning for the following:

a. FA (Fire Alarm) and FP (Fire Protection System) b. AC (Air Conditioning System)

c. MV (Mechanical Ventilation)

d. H (Heating System)

e. L&E (Lift and Escalator)

f. CHW (Cold and Hot Water Plumbing, Hydraulic Calculation and Pump) g. SP (Sanitary Plumbing)

h. RWHS (Rain Water Harvesting System)

i. E (Electrical Power Distribution System 240V-11kV) j. ELV (Extra Low Voltage Card Access CCTV Projector and Screen Public Addressable Sound Reinforcement)

k. ICT (Information and Communication Technology)

l. LPG (Kitchen Equipment and Liquefied Petroleum Gas) m. SCADA (Supervisory Control and Data Acquisition) n. BMS (Building Management System)

12. Hand-on wiring of light fittings, 13A SSO, DB, SSB and maintenance. 5 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N 13. To coordinate and supervise sub-ordinates, sub-contractors and works. 14. To prepare reports of heat load calculation (room by room), and zoning via Daikin software DS-HL2 Version 1.1.0

15. To assist Architect and Engineers for draft architectural, civil and structural drawings in AutoCAD 2019.

16. To assist Quantity Surveyor for taking off, prepare a bill of quantity and monthly valuation report.

17. To coordinate and supervise water reticulation service tapping via Hot Tapping and Line Stopping.

18. To review submission by Contractor (Profile Company, Material for Approval, Work Method Statement, Shop Drawing), comment and reject or approved / approved with comment.

Engineering’s equipment (personal owned):

1. Laptop computer 10TH GEN, CORE i3 with installed Daikin Heat Load Calculation DS-HL2 and Xpress

2. Drafting: AutoCAD 2019

3. MS-Office: Word, Excel.

4. Smartphone: Samsung Galaxy Note 20 Ultra 5G (WhatsApp and Telegram) My Skills

Engineering Calculation.

- 1. Room Heat Load Calculation, E20 -ii by Carrier / HAP

- 2. Room Heat Load Calculation, DS-HL2 by Daikin

- 3. Equipment Selection, Xpress by Daikin

- 4. Mc Quay Air conditioning.

- 5. Cold water plumbing transfer system, booster system and Distribution, Hazen & Williams formula.

- 6. Fire protection system, hose reel and sprinkler, Hazen

& Williams formula.

- 7. Electrical 240 Volts calculation for Total Connected Load and Maximum Demand, limited to 60 Amperes, 1 phase and 50 hertz and draft schematic 6 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N inclusive final fittings circuit, cable size, Miniature Circuit Breakers, Residual Current Circuit Breakers and Switch Fuses, IEE

- 8. VTS (Vertical Transportation System) – Lift and Escalator, EN My Computer Skills

Daikin DS-HL2, Daikin Express, Carrier E20-Excel, Autodesk-AutoCAD2019, MS-Office, InEight TeamBinder

Mechanical Engineer certified by Construction Industry Development Board (CIDB), Malaysia as follow:

1. Prepare sub-work programs and manage material schedule on-site. 2. Manage contract documents, organization and site preparation. 3. Implement, organize and monitor the works program. 4. Coordination of mechanical works.

5. Supervising preliminary works.

6. Oversee of mechanical construction works.

7. Organize mechanical method of statement.

8. Control time, cost and quality of mechanical works. 9. Involve in safety, health and environment policy. 10. Record and compile work progress, verify work compliance and prepare report. 11. Participate in site and technical meetings.

12. Coordinate site testing and commissioning of works. 13. Liaison with other site personnel, consultants and relevant authorities. 14. Monitor personnel performance and attend personnel discipline and welfare. My Involvement in Projects

26th September 2022 to current (14th July 2023) ( 11 months ) Company: Mega Jati Consult Sdn. Bhd.

Head office: No. 25-2-1, Jalan Medan Putra 3 (3/62D), Medan Putra Business Centre, Bandar Manjalara, Kepong, 52200 Kuala Lumpur, MALAYSIA

Tel : +603-****-**** / 96 Fax: +603-****-**** email : adyrzu@r.postjobfree.com Seconded to Khairi Consult Sdn Bhd.

Khairi Consult Sdn Bhd. SC Project Site Office, Block A, 2nd Floor, 1784, Jalan Storey, Bukit Chagar, 80300 Johor Bahru, Malaysia

Project: PROJECT RAPID TRANSIT SYSTEM LINK (RTS LINK) BETWEEN JOHOR BAHRU, JOHOR, MALAYSIA AND SINGAPORE

7 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N Project: Supervision Consulting of RTS ( Rapid Transit System ) from Station Bukit Chagar, Johor Bahru, Malaysia to Woodlands, Singapore (inclusive Depot Wadi Hana at Malaysia) and Viaduct for MRTS Sdn Bhd. Designation : Resident Engineer ( M & E)

1. Daily standing supervision of utilities relocation (TM, TNB, DiGi, Maxis, Fibercomm, Fiberail and TIME.dot.com)

2. Coordination of RFI (Request of Information) with Main-Contractor (Adil Permata Sdn Bhd), Sub-Contractor (Gadang Engineering Sdn Bhd) and Client, MRTS Sdn Bhd.

3. Respond to Main Contractor (Adil Permata Sdn Bhd) and Sub-Contractor queries. 4. Participate in the weekly technical meeting with main contractor (Adil Permata Sdn Bhd) Sub-Contractor (Gadang Engineering Sdn Bhd) and Client (MRTS Sdn Bhd). 5. Review the documents (PRF, MSA, MST, SD, CSD & SEM) via InEight TeamBinder, comments and accept or reject depend on the compliance to specification. 6. Attend and involve in discussion of CSD & SEM of TNB SSU Depot. 7. Issue NCR to the Contractor who has used unapproved material (UPVC) for underground sanitary plumbing and drainage system. 8. Present to Client, MRTS Sdn Bhd pertaining the QAQC issues, site issues, monthly progress, delay status etc.

9. Witness normal tapping MSCL 150mm and 250mm to the existing SAJ water reticulation piping.

10. Participate in the VTS workshop (EITA).

11. Participate in the site hurdle or site walk to expedite the site progress or QAQC matter. 12. (9Apr23)Review submission from the contractor and check the propose sub- contractor company profile with the registeration of CIDB, Suruhanjaya Tenaga, Telecom, Syarikat Air Johor, Fiberail, Fibercom, etc. 13. (21/4/23) Review submission from the contractor of Company Profile (PRF), Materials for Approval (MSA), Work Method Statement (MST), Shop Drawing (SD) and (CSD/SEM) Combined Services Drawing / Structural, Electrical & Mechanical Drawing Via InEight TeamBinder.

25th July 2022 to 15th September 2022 ( 2 months ) Company: Suhati Sdn. Bhd.

Head Office: Wisma Suhati, Unit1-0, No.2, Jalan 1/38J, Taman Sri Sinar, 51200 Kuala Lumpur, Malaysia. Tel: +603-****-**** Fax: +603-****-**** Site Office: Part of Lot 52722, Persiaran Dutamas, Mukim Batu, Kuala Lumpur, Malaysia. Project: Proposed Construction of New Pump House and 11KV TNB Sub-Station For 8 nos of Pumpset [each Head = 26m and Flowrate ( Q ) = 2268m3 / hr ] 4 duty and 4 standby from existing Batu Reservoir to Segambut Reservoir.

8 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N Designation: Project Manager / Site Agent

Experience:

1. Coordination of Work Program by use Primavera P6. 2. Site walkabout with previous contractor prior clear existing cabin. 3. Arrange Machinery ( Excavator ) for site clearing ( trees etc ) 4. Site coordination with License Surveyor to peg points of pump house and TNB Sub- station.

5. Update Client ( Pengurusan Air Selangor Sdn Bhd ) the daily site activities. 6. Plan and coordination of temporary site structures ( cabins, store, wash trough, diesel storage etc )

7. Attend Client, Consultant and Contractor Monthly meeting and present the Monthly Progress Report. Answer issues.

16th April 2021 to 30th June 2022 (14 months), Khairi Consult Sdn Bhd. Head Office: No. 76, Jalan SG 4/8, Taman Sri Gombak, 68100 Batu Caves, Selangor. Tel: 03-6184 1652/2 email: adyrzu@r.postjobfree.com www.khairiconsult.com Site Office: No.2, Jalan U3/6 (BK), Seksyen U3, 40150 Shah Alam, Selangor. Company: Consultancy Design and Supervision of Proposed New Elevated Highway for DASH (Damansara-Shah Alam) Package A (10KM), Toll Plaza 1 (Denai Alam) and Toll Plaza 2 (DASH Kwasa Land)

Designation: Resident Engineer – M & E

Experience:

1. Chaired meetings which involved 3 packages of Contractor (Sinar Widuri Sdn Bhd., Suhati Sdn. Bhd and Cantilever Bumi Sdn Bhd) with Civil and Structural teams. 2. Instruct Main-Constructors to submit QAQC matter for project such as material to be used, work method of statement inclusive testing, commissioning and checklist, work programs, safety etc

3. Review and comment the Contractor’s submission (Materials Approval Request / Work Method of Statement) etc.

4. Review Utilities Detector Equipments, monitor actual on-site detection and interfacing AutoCAD report of Existing Ground Level (EGL) and Utilities Detection Mapping (UDM) with new other services.

5. Utilities (Celcom, Digi, TM, Maxis, Water Reticulation and Gas Piping) and C&S

(Road and Drain) interfacing of position X & Y and level Z. 6. Site coordination Maxis due to and repair one – to – one (2KM). 9 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N 7. Cross-check the balance of work of water reticulation pipe 100mm dia, 200 mm dia, 300 mm dia, 1200mm dia and 1400mm with Contractors and Client (Turnpike Synergy Sdn Bhd).

8. Presented the Utilities Detection, Approval prior to Relocation, Testing & Commissioning to office staff especially Inspector of Work (M&E) as their scope of work.

9. Reviewed and commented Mechanical and Electrical Shop Drawings submitted by Contractor for Supervision Building at Tol Plaza Kwasaland. 10. Particapated in site walk for Maxis Cables Detection and locate Manholes. 11. Involved in workshop for Solar Panel orientation and support bracket on the roof of buildings.

12. Cross-checked the Contractor claim of payment of temporary lighting (AQEEM DB Sdn Bhd).

13. Cross-check and comment the Contractor’s RFI (Request For Inspection) forms for Utilities, Electrical and Mechanical. Some rejected due to incomplete works at site, some without proper checklist and some wrong attachment of drawings. 14. Solve interfacing issue between TNB ICT Fibre Optics Cable, TNB 33KV and road construction.

15. Liaised with Contractor, Designer and Authority of Water (AIS) for Water Reticulation issues (relocation).

16. Lead a site coordination between Power Transmission Company (TNB) and General Contractor for the lay of new duct 150mm diameter under-ground 1,000 MM from FRL. Prepared a Bill of Quantity for Contractor to price. 17. (7-8 Dec 2021) Lead interfacing lighting, pedestrian bridge and bus shelter for layout, schematic, elevation between Contractor Sinar Widuri and Suhati. Set-up file submission to the Local Authority future maintenance (JKR). Liaision with Water Reticulation Authority for trial hole to confirm life or abandon pipe 200mm dia MSCL and 300mm dia MSCL.

18. (21 Dec 2021) Coordination with Client (DASH), Contractor (Cantilever, Suhati and Sinar Widuri) for issue balance of work utilities (water reticulation, telecommunication and lighting).

19. (22 Dec 2021) Presentation to Water Supply Authority (Pengurusan Air Selangor Berhad), Wisma Goshen for the tapping of 1200mm and 1400mm diameter pipe MSCL via hot tapping and line stopping method.

20. (5-6 Jan 2022) HTLS (Hot Tapping and Line Stopping) for MSCL 150mm and 200mm at CH+1250 until CH+1300 LHS to avoid ramp to elevated highway. 21. (20 Jan 2022) Preparation of Hot Tapping and Line Stopping for pipe 1200mm at CH+1350 LHS Sinar Widuri.

22. (24 Jan 2022) Supervision of drilling water reticulation pipe by cutter 1080mm. 23. (25 Jan 2022) Liaise with Telecommunication Malaysia for Permanent Restoration of Temporary Cable.

24. Laision with authority of water (Air Selangor Wilayah Petaling and HQ, Wisma Goshen) for Relocation of 1200mm, 1400mm, 450mm and 300mm via method of Hot Tapping and Line Stopping.

10 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N 25. (27 Jan 2022) Jointly inspection with Water Authority (Air Selangor) for ductile iron 150mm diameter ultrasonic gauge tester, visual inspection of pressure reducing valve and sluice valve.

26. (10 Feb 2022) Site Coordination with Telekom Malaysia ( TM ) and Civil Consultant

/ Contractor for duct route below drain, avoid Reinforced Soil wall and open cut method.

27. (10 Feb 2022) Supervise coring of 1200mm MSCL water reticulation pipe by hot tapping and line stopping.

28. (March 2022) Coordination with Telecommunication Utility Owner ( TM ) for infrastructure and cable restoration which has been damaged by Main Contractor Sinar Widuri during the excavation of OSD (Onsite Stormwater Detention) Number 5. 29. Everyday cross-checked and draft reply for Material Approval Request, Method of Statement, Shop Drawing, Request For Information and Request for Inspection. 30. (April 2021 to 30Jun2022) Site walk, coordination and inspection to solve Utilities, Mechanical and Electrical issues (if critical).

31. (April2021-9Jun2022) Advance Works (Utilities Relocation). 32. (9Jun2022) Tender coordination of building.

33. (28Jun2022) Chair a coordination meeting of Kwasa Land’s utilities service (new development) which will cross ROW DASH via pipe jacking and HDD. (Sewer, 132KV etc)

20 August 2020 to 6 October 2020 (4 months), CMED Construction Co., Ltd. Cambodia Office: 252-254, Street 63, Corner Street 400, Boeung Keng Kang 1, Chamkarmon, Phnom Penh, Kingdom of Cambodia. Tel: +855-**-***-*** Website: www.cmedcc.com Company: Design and Build / Turnkey

Designation : Assistant MEP Design Manager

Project 1: General Department of Taxation (GDT), Phnom Penh, Kingdom of Cambodia Design experience:

1. Programmed room heat load calculation of Podium, Basement 1 to 6th floor, shopping complex and tower, 7th floor to 32th floor, office and mall by input known data and assumptions such as room design temperature (degree Celsius), RH, usage of room (people activity), room area, ceiling height, above ceiling height, infiltration, operating time, lighting, internal equipment operating heat, occupancy, indoor air intake, fresh air requirement, roof, wall type, window type, floor type, personal heat gain, radiant time factor consideration, next room condition, weather data, airflow calculation, enclosure structure setting, overall heat transfer coefficient, individual U- factor, Cooling Calculation Report Hourly. Software used is DS-HL2 by Daikin. 11 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N 2. Equipment selection of VRF System FCU indoors and outdoors, and electrical power requirement as written from the ecatalogue of Daikin were based on the cooling capacity per area. Software used is Express.

3. Compared heat load calculation Daikin DS-HL2 with Carrier E20-ii / HAP. 4. Prepared specification and bill of quantity of air conditioning system. 5. Main reference standard is ASHRAE.

6. Liaised with suppliers (Daikin, LG, Hisense, Carrier etc.) for cross-checked design and current model offered.

7. Liaised with MEP Cambodian Sub-Contractors for scope and brief of works. 8. Liaised internally within CMED Construction for new General Department of Taxation (GDT) supervision project.

13rd January 2020 to 1st Jun 2020 (6 months), Builtron Builders Sdn. Bhd. Head office: VSQ & PJ City Centre, 5-08-06, Block 5, Jalan Utara, 46200 Petaling Jaya, Selangor. Tel: +603-***-**** Website: www.builtron.my Company: Design & Build Contractor Civil Contractor Designation : M & E Manager (Mechanical and Electrical) Project 1:

Mix Development of Satori Residences contain semi basement for semi basement, four storey retails, 5 storey carpark, 1 storey swimming pool, jacuzzi, spa, Block A 21 storey hotel (300 units) and Block B 18 storey 100 units apartments at Melaka Tengah for Prolific Properties Sdn. Bhd, subsidiary of Hatten Group

Experiences:

1. Attended meeting with client Project Manager, M & E Engineer and Quantity Serveyor for start the construction.

2. Follow-up with client for obtain software of drawings, specification and bill of quantities for estimation and M & E contractors tender.

3. Coordinated with M & E contractors for presentation and brief of construction project. Project 2:

Proposed construction of link houses phase 2 & 3 at Bandar Penawar, Pengerang, Johor for Koperasi Pengerang Kota Tinggi, Johor.

Experiences:

1. Attended meeting with Developer (Kopeti), Project Management Consultant (Mirmas) for kick off the site for building construction.

2. Interviewed candidates for M & E Engineer.

12 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N Project 3:

Proposed construction 1 basement, ground floor, 1st to 4th floor hotel 119 bedrooms 3 stars at Melaka for Bumijaya.

Experiences:

1. Attended the kick-off meeting with Client (Bumijaya) for project briefed and planning. 2. Discussed with the M&E consultant (ABS Technique Consults Sdn Bhd) that Mechanical Services to be designed and supervised by me (Mohd Yusof Bin Rahmad Tulahan), and it to be used for submission to The Instituition of Engineers, Malaysia for Professional Interview (PI).

3. Discussed with the M&E sub-contractors for their company availability and strength to responsible of building construction under Builtron. 4. Discussed with the lift sub-contractor (MY Elevator supply for Shanghai Mitsubishi Elevator) 3 units, 6 stops and 1.0m/s.

5. Heat Load Estimation for Coffee House, Walkway, Reception and Lobby Area at ground floor. Refrigeration Load is 330,000 Btu/hr, Air Flow is 7,300 CFM sa and Velocity 2,000 FPM.

6. Designed the air duct, and coordinated with architectural plan layout, structural elevation and estimated highest ceiling height 2950mm and the lowest is 2800mm. Clearance between soffit beam to the highest ceiling is 900mm for M&E Services installation (electrical cable tray, trunking, ACMV duct, sprinkler and hose reel piping).

7. Obtained main duct sizes thru cross checked the Total Air Flow, Q = 7,300 CFM and Air Velocity, V = 2,000 FPM. Rectangular duct size 2,100mm width x 500mm height, and friction loss = 0.1WG/100ft. Sketched SAD to suit reflected ceiling plan, and select SAD 150 CFM.

8. Discussed with the Mechanical Consultant (ABS Technic) and Air Con supplier

(Carrier/Toshiba) for Heat Load Estimation (HLE), Outdoor Air weather Malacca, room set parameters, Psychrometric Chart, VRF/VRV AHU, Outdoor unit compressor 3 pipes (gas, liquid and hot pipe for water heather in hotel) and duct design. 9. Designed and drawn the air distribution (duct, diffuser and grill) and VRV/VRF piping.

10. Prepared the tender drawings, specifications, bill of quantities and cost estimate. 11. Discussed online thru WhatsApp Group with Carrier Air Conditioning (Malaysia) and ACMV contractor for the Coffee House and Main Lobby heat load estimate E20 and duct design (27.4.2020).

1st Jun 2018 until 8th January 2020 (19 months), DKLS Construction Sdn. Bhd. Head Office: 16th Floor & Penthouse, Ipoh Tower, Jalan Dato’ Seri Ahmad Said, 30450 Ipoh Perak, Malaysia.

Company: Main Contractor (Civil Contractor, PKK G7) 13 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N Contract type: Conventional

Site Office: Phase 3B, Parliament of Malaysia, Jalan Ledang, Kuala Lumpur. Designation : M & E Coordinator (Mechanical and Electrical) Project:

Phase 3B, a Block of Members of Parliament contain a Basement, Ground Floor, 1-4 Floor and Rooftop for M&E Services and a Multipurpose Hall for Parliament, Malaysia. Experiences:

1. Coordinated and supervised work of Mechanical and Electrical services air i.e conditioning and mechanical ventilation, sprinkler system, hose reel system, fire alarm conduit and wiring, lift components installation, electrical and telephone trunking installation, CCTV, card access and coordination with architectural dry wall, wet wall, ceiling etc.

2. Chaired internal discussions and meetings with nominated sub-contractors and sub- contractor (ACMV, Fire Protection, Lift, LV, ELV and ICT) for coordination above ceiling, at ceiling and below ceiling inclusive obtained height of pipes, trunkings and ducts. As the result, CSD (Combined Services Drawing) and RCP (Reflected Ceiling Plan) printed thru AutoCAD 2019 and submitted to JKR to obtain acknowledgement. 3. Made the ceiling’s drawing as based layout, and moved lightings to center by Edit Block in-place. Change colors to use Edit Block, and similar and isolate object to clean the drawing. Move objects in block by Edit Block in-place. Moved objects in between two points. These for making the M&E Reflected Ceiling Plan (RCP) drawing.

4. Prepared Reflected Ceiling Plan (RCP) inclusive ceiling patterns, levels, air con supply air diffuser, return air grills, cassette type air conditioner, sprinkler points and CCTV.

5. Inserted blocks ceiling and lighting into RCP drawings. Exploded some blocks which were unnecessary and erase it to make a clearer RCP (Reflected Ceiling Plan). Software AutoCAD 2019 was used.

6. Coordinated the Mechanical and Electrical services at wall in M&E Control Room for BAS (Building Automation System), Mimic Panel, Lift Control Panel and Lighting Control Panel.

7. Amended locations of Mechanical and Electrical services on the RCP (Reflected Ceiling Plan) as per Interior Designer and Architect comments. 8. Participated in the Project Management (JKR) meeting and answer for Mechanical and Electrical issues, progress and planning.

9. Liaison with Project Management (JKR) for inspection of materials, installation of Mechanical Services and testing of pressure of cold-water piping, sprinkler piping and VRF piping.

14 P a g e R E S U M E : T s . M O H D Y U S O F B I N R A H M A D T U L A H A N 10. Scheduled and witnessed the Fire Protection (Sprinkler System) piping pressure test at 150 PSI (Ib/



Contact this candidate