Post Job Free

Resume

Sign in

Power Plant Unloader

Location:
Caloocan, Philippines
Posted:
June 11, 2023

Contact this candidate

Resume:

NOLIBERT B. ELIGAN

** ********* ***. ******* ********

adxnc8@r.postjobfree.com

+639*********

Position Applied: Pre and Startup Electrical Commissioning

PROFESSIONAL SUMMARY

Proficient in Control and Instrumentation P&IDs, Schematic Diagram, Loop checking, Experience of Alstom Alspa P320 (DCS) RS-Logic, Allen Bradley PLC’ Motorized Actuators (MOV) Limitorque & Bernard, Auma, Pneumatic actuators, Siemens Sipart PS2, Pressure Transmitters, Flow Transmitters, Level Transmitters, Voltage Transducer, Current Transducer, Addressable Fire Alarm System, Temperature Sensors, RTD, PTC, TE, pH and Conductivity Analyzers, Land flow gas monitoring, I am capable of executing Electrical System, Three Phase and Single Phase, AEG DC-DC/AC-DC converters, UPS System, Variable Frequency Drive, Varispeed E7, Industrial Motor Controller, Electric Motors Rewinding, ABB Switchgear, Schneider Switchgear, LS Switchgear, Siemens Switchgear, Schneider MV/LV switchgear, PI (polarity index) test of 6.6KV electric motor Preventive and Corrective Maintenance, Being a primary experience, Start-up, Pre Commissioning and Commissioning, Water Treatment & Coal Handling Control Room Operator, Work experience mainly in Power Plant Industry.

PERSONAL DATA

Period : 15 May 2017 to 31 May 2020

Position : Start-up and Pre Commissioning Electrical

Company : Black and Veatch International Company

Address : Duyen Hai 3 Tra Vinh Province Vietnam

Project : Extension Project 688 MW, Supercritical Coal Fired Power Plant Project

Perform Pre Commissioning, Start-up Commissioning and Commissioning. Gather all documents Check list, P&IDs Single Line Diagram, Wiring Diagram, Schematic Diagram, Commissioning Procedure (CP), Internal Commissioning Procedures (ITP),

Perform Pre Commissioning, Commissioning, Start-up Commissioning. Balance of Plant (BOP), Water Treatment Plant and Waste Water Plant, Coal Handling System, Coal Ship Unloader, Coal Stacker Reclaimer.

Perform Site Acceptance Test (SAT), Factory Acceptance Test (FAT) cold loop check point to point check to confirm that all cables are terminated. All wiring errors must be corrected.

Perform Cubicles Energization, LV/MV switchgear and Motor Control Cabinet. Before the energization confirm all the cables terminated. Power is not supply. Megger test all the Cables and Bus Bur individually. Execute Rotation test after the energization to confirm all the 3Phases are correct.

Perform Hot Loop Checks, after the Mechanical Construction Completion and the following energization. Hot Loop Check must be confirm the control loop of the system from HMI/PLC, to the end device.

Perform Transformer checks and energization. Oil sample must be taken before and after energization. Take winding resistance test. Ratio Test Primary winding to secondary winding.

Perform Protection Relay testing. To monitor Voltage and Current provide rapid response to safe the system if there be any fault detected. PTs and CTs transformer measure/monitor voltage and current. The relays sense fault/disturbances of the system and react accordingly.

Perform Interlocking Test of Two line up switchgear and Bus tie to prevent damage the equipment. Interlocks to be confirm, Function test must be execute prior to energization.

Perform Induction Motor Test. Test Sheet are intact initial checks include Visual Checks, Gathered all the data of the Motor name plate, Manual rotation check of the shaft to confirm is there is damage, Proper Termination of the cable must be check, Motor winding continuity and resistance test, Winding Insulation Resistance test, PI test for large Motor, Phase to ground insulation resistance test. Motors ready to energized, Rotation checks, Motor Uncouple Run no load, Motor Couple Run with load.

Perform AC/DC hi pot test and Battery Discharge Tests. Hi pot test to insure the dielectric to withstand rated transient voltage. Battery Discharge test. check battery voltage individually, cycle testing and load testing,

Perform Electrical Turn over Package, Start-up and Commissioning of the system. Adheres safety and quality standards as applicable to duties and accountabilities. Assist the Commissioning Manager for the implementation of Lockout/Tag out (LOTO) program.

Execute Coal handling CCR operator and Coal Stacker Recamier operator.

Period : 29 January 2014 to 26 July 2015

Position : Start-up and Pre Commissioning Electrical

Company : Black and Veatch International Company

Address : Binugao Toril, Davao City 8000 Philippines

Project : 2x150 MW Coal Fired Power Plant Therma South Energy Project

Perform Pre Commissioning, Start-up Commissioning and Commissioning. Gather all documents Check list, P&IDs Single Line Diagram, Wiring Diagram, Schematic Diagram, Commissioning Procedure (CP), Internal Commissioning Procedures (ITP),

Perform Pre Commissioning, Commissioning, Start-up Commissioning. Balance of Plant (BOP), Water Treatment Plant and Waste Water Plant, Coal Handling System, Coal Ship Unloader, Coal Stacker Reclaimer.

Perform Site Acceptance Test (SAT), Factory Acceptance Test (FAT) cold loop check point to point check to confirm that all cables are terminated. All wiring errors must be corrected.

Perform Cubicles Energization, LV/MV switchgear and Motor Control Cabinet. Before the energization confirm all the cables terminated. Power is not supply. Megger test all the Cables and Bus Bur individually. Execute Rotation test after the energization to confirm all the 3Phases are correct.

Perform Hot Loop Checks, after the Mechanical Construction Completion and the following energization. Hot Loop Check must be confirm the control loop of the system from HMI/PLC, to the end device.

Perform Transformer checks and energization. Oil sample must be taken before and after energization. Take winding resistance test. Ratio Test Primary winding to secondary winding.

Perform Protection Relay testing. To monitor Voltage and Current provide rapid response to safe the system if there be any fault detected. PTs and CTs transformer measure/monitor voltage and current. The relays sense fault/disturbances of the system and react accordingly.

Perform Interlocking Test of Two line up switchgear and Bus tie to prevent damage the equipment. Interlocks to be confirm, Function test must be execute prior to energization.

Perform Induction Motor Test. Test Sheet are intact initial checks include Visual Checks, Gathered all the data of the Motor name plate, Manual rotation check of the shaft to confirm is there is damage, Proper Termination of the cable must be check, Motor winding continuity and resistance test, Winding Insulation Resistance test, PI test for large Motor, Phase to ground insulation resistance test. Motors ready to energized, Rotation checks, Motor Uncouple Run no load, Motor Couple Run with load.

Perform AC/DC hi pot test and Battery Discharge Tests. Hi pot test to insure the dielectric to withstand rated transient voltage. Battery Discharge test. check battery voltage individually, cycle testing and load testing,

Perform Electrical Turn over Package, Start-up and Commissioning of the system. Adheres safety and quality standards as applicable to duties and accountabilities. Assist the Commissioning Manager for the implementation of Lockout/Tag out (LOTO) program.

Execute Coal handling CCR operator and Coal Stacker Recamier operator.

Period : 06 October 2013 to 20 November 2013

Position : Electrical Commissioning

Company : YTL Power Services Sdn Bhd / Siemens

Address : Kerteh Malaysia

Project : Petronas Gas Berhad UENICS CUF Kerteh Project

Performs Commissioning and protection relay retrofitting.

Period : 26 April 2013 to 24 June 2013

Position : Electrical Commissioning

Company : YTL Power Services Sdn Bhd / Samsung C&T

Address : Jurong Island Singapore

Project : GMR Energy 2x400 MW Combined Cycle Power Plant (CCPP) Project

Perform Pre Commissioning, Start-up Commissioning and Commissioning. Gather all documents Check list, P&IDs Single Line Diagram, Wiring Diagram, Schematic Diagram, Commissioning Procedure (CP), Internal Commissioning Procedures (ITP),

Perform Pre Commissioning, Commissioning, Start-up Commissioning. Balance of Plant (BOP), Water Treatment Plant and Waste Water Plant, Coal Handling System,

Perform Site Acceptance Test (SAT), Factory Acceptance Test (FAT) cold loop check point to point check to confirm that all cables are terminated. All wiring errors must be corrected.

Perform Cubicles Energization, LV/MV switchgear and Motor Control Cabinet. Before the energization confirm all the cables terminated. Power is not supply. Megger test all the Cables and Bus Bur individually. Execute Rotation test after the energization to confirm all the 3Phases are correct.

Perform Hot Loop Checks, after the Mechanical Construction Completion and the following energization. Hot Loop Check must be confirm the control loop of the system from HMI/PLC, to the end device.

Perform Transformer checks and energization. Oil sample must be taken before and after energization. Take winding resistance test. Ratio Test Primary winding to secondary winding.

Perform Protection Relay testing. To monitor Voltage and Current provide rapid response to safe the system if there be any fault detected. PTs and CTs transformer measure/monitor voltage and current. The relays sense fault/disturbances of the system and react accordingly.

Perform Interlocking Test of Two line up switchgear and Bus tie to prevent damage the equipment. Interlocks to be confirm, Function test must be execute prior to energization.

Perform Induction Motor Test. Test Sheet are intact initial checks include Visual Checks, Gathered all the data of the Motor name plate, Manual rotation check of the shaft to confirm is there is damage, Proper Termination of the cable must be check, Motor winding continuity and resistance test, Winding Insulation Resistance test, PI test for large Motor, Phase to ground insulation resistance test. Motors ready to energized, Rotation checks, Bump test, Motor Uncouple Run no load, Motor Couple Run with load.

Perform AC/DC hi pot test and Battery Discharge Tests. Hi pot test to insure the dielectric to withstand rated transient voltage. Battery Discharge test. check battery voltage individually, cycle testing and load testing,

Perform Electrical Turn over Package, Start-up and Commissioning of the system. Adheres safety and quality standards as applicable to duties and accountabilities. Assist the Commissioning Manager for the implementation of Lockout/Tag out (LOTO) program.

Period : 22 February 2012 to 30 April 2013

Position : Start-up and Pre Commissioning Electrical / EBNI

Company : Areva Nuclear Power

Address : Finland -27160 Olkiluoto

Project : OL3 1600 MW European Pressurized Reactor (EPR) Nuclear Power Plant Project

Startup Pre Commissioning and Commissioning in Nuclear Island Division 1, 2, 3&4 Electrical Systems.

Perform Pre Commissioning, Start-up Commissioning and Commissioning. Gather all documents Check list, P&IDs Single Line Diagram, Wiring Diagram, Schematic Diagram, Commissioning Procedure (CP), Internal Commissioning Procedures (ITP),

Perform Cold loop check point to point check to confirm that all cables are terminated. All wiring errors must be corrected.

Perform Cubicles Energization, LV/MV switchgear and Motor Control Cabinet. Before the energization confirm all the cables terminated. Power is not supply. Megger test all the Cables and Bus Bur individually. Execute Rotation test after the energization to confirm all the 3Phases are correct.

Perform Protection Relay testing. To monitor Voltage and Current provide rapid response to safe the system if there be any fault detected. PTs and CTs transformer measure/monitor voltage and current. The relays sense fault/disturbances of the system and react accordingly.

Perform Interlocking Test of Two line up switchgear and Bus tie to prevent damage the equipment. Interlocks to be confirm, Function test must be execute prior to energization.

Perform Induction Motor Test. Test Sheet are intact initial checks include Visual Checks, Gathered all the data of the Motor name plate, Manual rotation check of the shaft to confirm is there is damage, Proper Termination of the cable must be check, Motor winding continuity and resistance test, Winding Insulation Resistance test, PI test for large Motor, Phase to ground insulation resistance test. Motors ready to energized, Rotation checks, Motor Uncouple Run no load, Motor Couple Run with load.

Perform AC/DC hi pot test and Battery Discharge Tests. Hi pot test to insure the dielectric to withstand rated transient voltage. Battery Discharge test. check battery voltage individually, cycle testing and load testing,

Perform Adheres safety and quality standards as applicable to duties and accountabilities. Assist the Commissioning Manager for the implementation of Lockout/Tag out (LOTO) program.

Period : 07 February 2011 to 22 June 2011

Position : Electrical & Control Instrument Commissioning Technician

Company : Black and Veatch International Company

Address : Tanjung Jati Jepara Indonesia

Project : 2x660 MW Coal Fired Power Plant Unit 3&4 Project

Commissioning through to start-up & system handover units 3 & 4 a Coal Fired Power Plant of PLN (Perusahaan Listrik Negara) under Black & Veatch in Tanjung Jati Jepara, Indonesia Includes Fly Ash Disposal System, FGD (Fuel Gas Desulfurization), EP (Electrostatic Precipitator), System

Performs testing and calibration of Electrical and Instrument devices, Loop checking, Insulation test, Continuity test, Micro Ohm Test, Field calibration, Verifies set points per design of Instrument devices, function test, interlock test, loops checking, Electric motors no-load test and load run test, functional testing of equipment and system, Perform test records sheet, documentation of equipment and subsystem turnover to the client, Supports plant operation during startup and initial operations, Adheres safety and quality standards as applicable to duties and accountabilities. Assist the Commissioning Manager in the implementation of Lockout/Tag out (LOTO) program

Period : 04 January 2010 to 15 May 210

Position : Electrical & Control Instrument Commissioning Technician

Company : Doosan Heavy Industries

Address : Cebu Philippines

Project : 2x103 MW Coal Fired Power Plant Project

Performed Loop checking, Continuity check, Pre-Commissioning/Commissioning 2x103megawatts coal fired power plant, GIS 13.8kv Gas Insulated Switchgear Hyosung, 6.9MV, Switchgear 48LV Switchgear LS, GCB Generator Circuit Breaker Areva, UPS system Borri, LS MCC 100MVA main transformer 31.5MVA Aux Transformer Fortune Electric, Logic test from field to system cabinet for DCS, Equipment and subsystem turnover documentation, Electric motor test, Solo test, Load test, Electric Motor Insulation test Resistance test, Execute Control and Instrumentation, Siemen Electronic/pneumatic PS2 Calibration, Start-up Pre Commissioning / Commissioning of Water Treatment Plant, corrective/preventive maintenance, instrument calibration of SMART pressure transmitters, SEGNET flow transmitters, Seojin Instech level transmitters, Temperature sensor test RTD,TC PTC, Vibration test. Interfacing with Allen Bradley PLC Rslogix 5000, HMI, Varispeed E7 frequency inverter, UF, SWRO, BWRO, CDI system Ion pure, Endress+Hauser pH and conductivity analyzer. Full understanding of the equipment, P & ID, manuals, technical data and spare part specifications.

Period : 12 March 2008 to 30 January 2009

Position : Chief Electrician

Company : WJ Ground Water Limited

Address : Duabai, UAE

Project : Dewatering Project

Perform Commissioning and Installation of Electrical Control Panels Instrument device, Loop checking, Insulation test, Continuity test, Control level switch, DOL and Soft start STAR DELTA, Grundfos MP204 CU3 motor controller, Grundfos pump, Franklin Submersible Electric motor, Automatic Transfer Switch(ATS ) Motor control alarm system, Check and Test Electrical Equipment before putting into service, Routine Maintenances Troubleshooting and Repair of Generators 300 KVA 430 VOLTS PERKINS Diesel Generator, SDMO Diesel Generator, Disassembles Electrical and Mechanical equipment and perform test using measuring equipment, Demonstrates knowledge of Electrical and Instrumentation system functions including maintenance work practices and divisional safe work practices. Full understanding of the equipment, P & IDs, manuals, technical data and spare part specifications Assist in the training and development of new technicians, emergency response activities as required, general housekeeping functions as necessary Implement basic guidelines for working safely with electricity.

Period : July 2007 to October 2007

Position : Electrical Supervisor

Company : Alstom Japan KK

Address : Villanueva Cagayan de Oro City, Philippines

Project : 2x205 MW Coal fired Plant, Power Shutdown Project

In Charge in all Modification, Commissioning troubleshooting and repair work as per required by Alstom designers handling manpower tools equipment, PTW to execute daily schedules and progress to meet the deadline before the plant re- started, replacements of bearings for mixers and hydrators, initiate installations of additional machine and process line troubleshooting and implement corrective action to avoid recurrence of the problem, Practice of working safely in carry out his duties and responsibilities.

Period : 02 February 2003 to May 2006

Position : Cellphone Technician / Trainor

Company : Celtecs Cellphone Repair Training Center

Address : Lingayen, Philippines

Sole Owner

Engage of mobile phone repair through software and hardware troubleshooting Conduct proper hands on training and develop new skills.

Period : 10 May 2001 to 14 December 2002

Position : Control & Instrument Commissioning Technician (BOPM)

Company : Alstom Power Plants Services Ltd.

Address : Hoping Taiwan R.O.C.

Project : 2x660 MW Coal Fired Power Plant Project

Perform Start-Up Pre-Commissioning / Commissioning and Maintenance Balance of plant (BOPM) Execute Control and Instrumentation, loop checking, Logic test from field to DCS, Field Calibration and sitting of Pneumatic valve, Motorized Actuator Limitorque, Bernard, Auma, Level Transmitters, Flow Transmitters, Pressure Transmitters, Temperature monitoring sensors like RTD, TE, UV detector, IR detector, UV-IR detector, Smoke detector, Ionization, How Fire System, BENTLY NAVADA 3500 series condition monitoring system for field equipment measuring axial, radial speed and temperature system, Alstom ALSPA 320 Distributed Control System (DCS) ALLEN BRADLEY PLC 5/30 to PC’S Man machine interfaces with Citic Graphic Software for water treatment plant, Sensors to Controllers interfacing, Performance testing and reliability trials prior to client takeover of the 2x660MV Coal Fired Power Station, Full understanding of the equipment, P&ID, Schematic diagram and manuals, technical data and spare parts specifications, Demonstrate knowledge of the purpose and function of plant electrical equipment and control systems.

Period : 15 June 1998 to 09 May 2001

Position : Control & Instrument Commissioning Technician (BOPM)

Company : Alstom Power Plants Services Ltd.

Address : Sual Power Station Brgy. Pangascasan Sual Pangasinan Philippines

Project : 2x609 MW Coal Fired Power Plant Project

Perform Start-Up Pre-Commissioning / Commissioning and Maintenance Balance of plant (BOPM) Execute Control and Instrumentation, loop checking, Logic test from field to DCS, Field Calibration and sitting of Pneumatic valve, Motorized Actuator Limitorque, Bernard, Auma, Level Transmitters, Flow Transmitters, Pressure Transmitters, Temperature monitoring sensors like RTD, TE, UV detector, IR detector, UV-IR detector, Smoke detector, Ionization, How Fire System, BENTLY NAVADA 3500 series condition monitoring system for field equipment measuring axial, radial speed and temperature system, Alstom ALSPA 320 Distributed Control System (DCS) ALLEN BRADLEY PLC 5/30 to PC’S Man machine interfaces with Citic Graphic Software for water treatment plant, Sensors to Controllers interfacing, Performance testing and reliability trials prior to client takeover of the 2x660MV Coal Fired Power Station, Full understanding of the equipment, P&ID, Schematic diagram and manuals, technical data and spare parts specifications, Demonstrate knowledge of the purpose and function of plant electrical equipment and control systems.

Period : 21 July 1997 to 26 May 1998

Position : Electrical Lead Man / Sub Con

Company : Ecco Asia

Address : Sual Power Station Brgy. Pangascasan Sual Pangasinan Philippines

Project : 2x609 MW Coal Fired Power Plant Project

Performed Layout and Installation of Panel, Cable Trays, termination of Instrument cable low voltage cable

Period : 08 April 1997 to 21 July 1997

Position : Electrician 3

Company : GEC Alstom

Address : Sual Power Station Brgy. Pangascasan Sual Pangasinan Philippines

Project : 2x609 MW Coal Fired Power Plant Project

Performed Layout and Installation of Panel, Cable Trays, termination Instrument cable low voltage cable.

Period : 01 October 1996 to 07 April 1997

Position : Electrical Technician

Company : Southern Company & Construction

Address : Sual Power Station Brgy. Pangascasan Sual Pangasinan Philippines

Project : 2x609 MW Coal Fired Power Plant Project

Perform Preventive and Corrective Maintenance Electrical of all process machines in a safe manner and procedure troubleshooting repair overhead cranes which consist of Three Phase Motors 480VAC, Routine Maintenance activities Industrial Motor Control, Electric Motor Rewinding Single Phase Three Phase Induction Motor 230/430volts.

Period : 01 July 1994 to 16 September 1994

Position : Industrial Electrician

Company : MCEI Asphalt Plant and Crusher

Address : Binalonan, Pangasinan Philippines

Perform Preventive Corrective maintenance of Control and Instrument/Electrical System, Asphalt plant and Crusher, Electric Motor Rewinding Single Phase Three Phase Induction Motor 230/430volts, Routine troubleshooting activities Industrial Motor Controls.

Period : 25 January 1994 to 25 June 1994

Position : Production Operator

Company : Star Light Company

Address : Quezon City Philippines

Perform vacuum fluorescent tube Viking, charging argon gas and mercury.

Period : 23 January 1992 to 08 December 1993

Position : Industrial Electrician / OJT

Company : MCEI Asphalt Plant and Crusher

Address : Binalonan, Pangasinan Philippines

Perform Preventive Corrective maintenance of Control and Instrument/Electrical System, Asphalt plant and Crusher, Electric Motor Rewinding Single Phase Three Phase Induction Motor 230/430volts, Routine troubleshooting activities Industrial Motor Controls.

EDUCATION

Electrical Technology Two Years Course Apr 1990 - Mar 1992

Pangasinan School of Arts and Trade Specialized Lingayen, Philippines

Specialized in Electrical Technology

SKILLS

Knowledge in Induction Motor Rewinder, Variable Frequency Drives,

Trouble shooting and Repair wiring circuit

Knowledge Single line Diagram, Schematic Diagram, Ladder.

Knowledge of safety standards and procedures OSHA Certificate, Safety at Electrical work SFS6002, G3 NFPA 70E for Manager and Electricians 2015

Installing electrical conduits, cables, tubing, and cable termination.

Knowledge of National Electric Code and local electric codes

Knowledge of Programmable Logic Controllers (MHI PLC SCADA)

Installing and maintaining electrical systems, equipment and devices

Power plant experience, construction experience and industrial experience

Knowledge of LV/MV switchgear, Motor Control Cabinet, Distribution Box.

Using and maintaining hand and power tools, such as screwdrivers, pliers and drills

Testing equipment, instruments and systems basic (Multi Meter, Insulation Tester, 4-20ma injector)

Knowledge and experience in Commissioning, Startup Commissioning Pre Commissioning

PERSONAL DATA

Date of Birth November 22, 1967

Place of Birth Guihulngan Negros Oriental

Nationality Filipino

Sex Male

Civil Status Married

SSS No 02-0991849-8

Tin 198-760-344

Passport No. P2429749A Date issue 17 December 2021 Expired 16 December 2031

Driver’s License A079315700

PROFESSIONAL CREDENTIALS

•Pangasinan School of Arts and Trade Specialized In Electrical Technology

AWARDS AND HONOURS

National Manpower Youth Council 1991

•Third Class Building Electrician

•Electrician Trade Skills Examination

•Pass Certificate No. 013*******

National Manpower Youth Council - San Fernando, La Union 1991

•Outstanding Electrician Award

•School Year 1990 - 1991

•Pangasinan School of Arts and Trade

Youth Skills Olympics Building Wiring 1991

•School Representative

•Third Regional Skills Olympics

EDUCATION AND TRAINING RECORDS

Zeversolar Training

Jiangsu Zeversolar Solar New Energy Co., Ltd

Quezon City, Philippines August 2015

Basic Technology of PV system and PV inverter

Introduction of Zeversolar string inverters

Monitoring solution for residential and commercial application

Inverter selection and PV system design

Inverter installation, commissioning, daily maintenance and troubleshooting

Click Safety

G3 NFPA 70E for Managers and Electricians 2015

Serial Number: 13722467 Completed: June 3, 2015

Safety at Electrical Work SFS6002 Training

Winnova Electrical and Automation Technology

Pori Finland, Ulasoorinatie February 2012

Occupational Safety Card Training

Hotel Cumulus Rauma, Finland March 2012

Construction OSHA 10 Hour Outreach Program

2X660 Megawatts Coal Fired Power Plant

Coal Fired Power Plant Unit 3&4 Tanjung Jati Jepara, Indonesia 17-23-24, March 2011

2008 Submersible Motor Workshop

Franklin Electric’s Practical and Theoretical Submersible Motor Workshop and Application, Installation and Maintenance

Franklin Tech training Center Wittlich Germany November 3-7, 2008

R3 Fire Detection System Network

Sual Power Plant, Philippines September 1, 1999

Land Combustion Flue Gas Monitoring

Sual Power Plant October 1999

Pangasinan National High School

Lingayen, Pangasinan S.Y. April 1, 1990-1992

CHARACTER REFERENCE:

Gaudencio Flores

Electrical Instructor

Pangasinan School of Arts and Trade Lingayen

Pangasinan, Philippines

Halt Whull

Deputy Commissioning Manager

Black and Veatch International

Email address: adxnc8@r.postjobfree.com

+1-509-***-****

Stuart Miles

Startup Commissioning Manager

Black and Veatch International

Email address: adxnc8@r.postjobfree.com

Nolibert B. Eligan

Applicant



Contact this candidate