SUMARDI NGADIMAN
Address: Perumahan Bumi Lestari Blok H 50 No. 22 Mangun Jaya, Tambun Selatan, Bekasi, Indonesia-17517
Place / Date of Birth: Palembang, South Sumatera / August 25, 1964 Passport No / Date of Expiry: B 570 8218 / December 13, 2021 Religion: Moslem
Status: Married with one daughter (24 years old) and two sons (23 years and 15 years old) Contact No.: Mobile:+62-813-****-**** / 813-****-****, Home:+62-21-883-***-** Email Address: adxipq@r.postjobfree.com or adxipq@r.postjobfree.com; Linked:http://id.linkedin.com/pub/sumardingadiman/10/3b6/7b EDUCATION
University of Indonesia, Social Faculty, Graduated in 1989Senior High School– Yogyakarta, Marsudi Luhur, Science Department, Graduated in 1983. TRAININGS
Training on the Implementation Procedures of Procurement of Goods / Materials for the Purposes of Oil and Gas (December, 2005), PTK-007, Certificate. Training of Logistic by Direktorat Jenderal Minyak dan Gas Bumi (March, 2000), Certificate.
Course part time at East Kalimantan Melamine College held by the Royal Aeronautical Society the Institutions of Mechanical Engineers and Production Engineers in conjunction with the Department of Education and Science (October, 1996), Certificate.
SKILLS AND EXPERIENCES
- In Contractual
- SAP Knowledge
- Good English Communication; other is German
- Have dealt with Piping, Mechanical, Structural, Electrical & Instrumentation Manufacturers.
- Expediting, Master List, Local Content
Page 2 of 6
WORK EXPERIENCES
June 2022– Present, PT. RUNINCO BUMI LESTARI / RBL Assignment as: PROCUREMENT MANAGER
Responsible to: Director
Project Handling: 1. PERTAMINA EP, Tambun, 2. Mining Gold Beringin, Puruk Cahu, Muara Teweh, Kalimantan Tengah, 3. AMMAN Mineral Nusa Tenggara, West Sumbawa, Nusa Tenggara.
August 2021– June 2022, PT. KAEFER / KAEFER PROSTAR PTE. LTD. Assignment as: BUYER cum LOGISTIC
Responsible to: Procurement Manager / Technical Manager Project Handled: 1. LNG Tangguh Train 3 Offshore &Onshore, Has 6 Wells in Block Wiriagar Berau and Muturi, with Capacity 3.8 Million Metric Ton Per Annum / MTPA.Teluk Bintuni, West Papua, Client: BP Berau Ltd., Scope of Work: Sand, Blasting and Painting
- September 2019– October 2020, CSTS – Chiyoda, Saipem, Tripatra, SAE Joint Operation
Assignment as: CONSTRUCTION BUYER / PROCUREMENT ENGINEER
(From Tripatra)
Responsible to: Procurement Manager
Project Handled: 1. LNG Tangguh Train 3 Offshore &Onshore, Has 6 Wells in Block Wiriagar Berau and Muturi, with Capacity 3.8 Million Metric Ton Per Annum / MTPA.Teluk Bintuni, West Papua, Client: BP Berau Ltd.,
- May 2019–Sep 2019, PT. MEINDO ELANG INDAH – Engineering, Procurement, Construction, Installation for Oil and Gas Sectors Assignment as: PROJECT BUYER / PROCUREMENT ENGINEER Responsible to: Procurement Manager
Project Handled:: 1. Project Jawa – 1, Combined Cycle Gas Turbine Power Plant (1760 MW), Cilamaya, Karawang, West Java, Client: Pertamina, Marubeni Sojitz, Black & Veath; 2. Panen Sub-Trunklineand Main Pipeline Project,
Betara Complex Development,Tj. Jabung, Jambi Province, Client: PetroChina International Jabung Ltd.
- August 2016 –May 2019 SELF EMPLOYED – VARIOUS CONTRACT ROLES, in Self Employed Independent People Soft Consultant (Review and consult the various contract roles such as: sourcing material / equipment for oil & gas project, procurement plan, and selecting the potential subcontractors)
- March 2015 –July 2016 SIEMENS PTE. LTD, SINGAPORE (For Batam Based @ Elnusa Batam Fabrication Yards) - Engineering, Procurement for Oil & Gas Division. Assignment as: PROJECT EXPEDITOR SITE
Responsible to: Procurement Manager
Project Handled: Yamal LNG Project (Onshore, 29 Modules), For E/Power House, Client: YamGaz Russia, Location: Siberia Peninsula. North Russia. Page 3 of 6
- July 2014 – March 2015 SELF EMPLOYED – VARIOUS CONTRACT ROLES, in Self Employed Independent People Soft Consultant (Review and consult the various contract roles such as: sourcing material / equipment for oil & gas project, procurement plan, and selecting the potential subcontractors)
- September 2013 – June 2014 PT. RAGA PERKASA EKAGUNA / RPE(Home Office- Jakarta) - Engineering, Procurement, Construction & Commissioning for Oil & Gas Sectors.
Assignment as: PROCUREMENT MANAGER
Responsible to: Procurement Director
Packages Handled: All Packages
Project Handled: 1.Onshore Receiving Facility, Bukit Tua Project, Gresik, East Java, Consortium with Krakatau Engineering. Client: Petronas (Malaysia) Carigali Ketapang II Limited. 2. Mila & Asti and Banuwati Offshore Platform, Monopod with Bracings, including Pipeline and Modified Banuwati Platform, Consortium with Bakrie Construction, Client: CNOOC. 3. Onshore Plant Pondok Makmur Development Project, Cabangbungin, Pondok Makmur, Bekasi, West Java, Client: PT.Pertamina EP.
- July 2012 – July 2013, PT. RAJAWALI SWIBER CAKRAWALA / SWIBER(Home Office-Jakarta) - Engineering, Procurement for Oil & Gas Sectors. Assignment as: PROCUREMENT MANAGER
Responsible to: Snr. Procurement Manager
Packages Handled: All Packages
Project Handled: 1. South Belut Field Development Project (Modified North Belut Topside
& PLEM (Pipe Line End Manifolds) / Subsea, 8 Wells, in Natuna Islands, Indonesia. Client: ConocoPhillips Indonesia Inc (COPI). 2. (Temporary) Naga & Pelikan Development Project (2 Tripod Jackets & Decks), in Natuna Island, Consortium with Sembawang Marine Offshore Engineering (SMOE), Client: Premier Oil Natuna Sea B.V (PONSBV). 3. (Temporary) Sisi Nubi 2 B & Peciko 7 B Development Project (Sisi Nubi 2 Tripod Jackets & Decks, one with 15 Slots capable of handling 200 Million cubic feet per Day of Gas,and the other with 9 Slots that will be designed to receive 150 MMcfd of Gas / another Tripod Jacket & Deck is needed for Peciko Phase 7 B. This 9 Slots Structure will be designed to receive 170 MMcfd of Gas. Water Depth at this Project is 45 Meters), East Kalimantan, Consortium with Guna Nusa Fabricator, Client: Total Indonesie.
- April 2011 – April 2012, PT. TRIPATRA ENGINEERS AND CONSTRUCTORS / TPEC(Home Office-Jakarta) - Engineering, Procurement, Construction & Commissioning for Oil & Gas Sectors.
Assignment as: PROCUREMENT COORDINATOR / DEPUTY
PROCUREMENT MANAGER
Responsible to: Procurement Manager
Packages Handled: All Packages.
Project & Proposals Handled: 1.Project South Sumatera NGL Project
(SSNP), in South Sumatera Province, Indonesia.
Client: PertaSamtan Gas (PT. PERTAMINA – SAMSUNG, JOB) Pipelines, Onshore Project, Project Value USD150M),
Page 4 of 6
2. Proposal for MEDCO Senoro – Central Processing Plants (Pipelines, Onshore Project), Central Celebes Province, Indonesia (Won Tender USD600M, Prominent in Local Content), Client: MEDCO Energi E & P Malaka, 3. Proposal for Compressed Natural Gas (CNG) Power Plants, Sei. Gelam, Muaro Jambi, Jambi Province, Indonesia, Client: PT. PLN (Persero), 4. Proposal for Development Facility Gas in Donggi (Pipelines, Onshore Project), Banggai District, Central Celebes Province, Indonesia,(Estimated Value USD185M, Client: PT. PERTAMINA, EP, 5. Proposal for MEDCO Block “A” – Central Processing Plants(CPP Alur Siwah), East of Aceh, Aceh Province, Indonesia,
(Estimated Value USD135M) Client: MEDCO Energi E & P Malaka.
- July 2010 - March 2011, PT. NIPPON STEEL CONSTRUCTION INDONESIA / NISCONI (Home Office-Jakarta) – Engineering, Procurement, Construction & Commissioning for Oil & Gas Sectors.
Assignment as: SNR. BUYER/PROCUREMENT ENGINEER
Responsible to: Procurement Manager
Packages Handled: Tagged Item Packages (Mechanical, Piping). Project Handled: ”Su TuTrang” (White Lion) Wellhead Platform (WHP / 4 Jacket Legs) and Subsea Pipelines Project in Socialist Republic of Viet Nam. Client: Joint Operation between Cuu Long Joint Operation Company (CLJOC) and Petro Viet Nam, Technical Support of Mechanical (PTSC).
- October 2008 – April 2010, PROSAFE PRODUCTION SERVICES PTE. LTD. / PPL(Home Office-Singapore) – FPSO & FPSDO / Floating Production Storage/Drilling Off-Loading.
Assignment as: SNR. BUYER / PROCUREMENT ENGINEER
Responsible to: Sr. Procurement Manager
Packages Handled: Miscellaneous (Mechanical, Piping, Electrical and Structural). Projects Handled: 1.ESPOIR IVOIRIEN Upgrading FPSO Project in Abidjan, Ivory Coast, West Africa. 2. AZURITE Development Project/FPDSO, Republic of Congo, West Africa. Client: Murphy Oil, 3.PetrobrasBrasil / FPSO 4. Apache Ningaloo Vision, West Australia / FPSO.
- August 2007 – August 2008, KELLOGG BROWN & ROOTS (KBR) ASIA PACIFIC PTE. LTD., (Home Office-Singapore) – Engineering & Procurement for Oil & Gas Sectors
Assignment as PURCHASING SPECIALIST for EOS Oil & Gas Services Joint Venture (between Worley Parsons Services Pty. & KBR E&C Australia Pty Ltd) Responsible to: Procurement Manager
Represent Company to held Kick-Off Meeting for Commercial Clarifications with Suppliers After Place Order in New Castle (U.K.), Aberdeen (Scotland), Milan (Italy) and Perth (Australia). Packages Handled:
Mechanical, i.e.:Phase One Accommodation (KPI/Key Performance Indicator), Bunkering Hoses & Hose Reel Station.
Structural, i.e.: Self Extinguishing Aluminum Helideck (KPI), Safety, Instrumentation.
Project Handled: PLUTO LNG Development Project, Karratha, Western Australia – Topside Deck & 4 Jacket Legs. Client: Woodside Energy Limited Burrup Australia. Page 5 of 6
- January 2007 – August 2007, RAMUNIA FABRICATORS SDN BHD / RFSB (Johor Bahru, Malaysia) Engineering, Procurement, Construction & Commissioning for Oil & Gas Sectors
Assignment as SNR. BUYER / PROCUREMENT ENGINEER
Responsible to: Procurement Manager
Packages Handled: Piping,Electrical and Spare Parts for Commissioning and Operating Two (2) Years.
Projects Handled: 1. East Belumut – A Topside, Malaysia, Client: Newfield Peninsula Malaysia Inc., 2. F13E SC DR- A Topside, Malaysia, Client: Serawak Shell Berhad, 3. Vasai Development Project, Malaysia, Client: Samsung Korea.
- January 2005 – January 2007, P.T. TECHNIP INDONESIA / PTTI (Head Office Jakarta, Indonesia) – Engineering, Procurement and Construction for Oil & Gas Sectors Assignment as SNR. BUYER / PROCUREMENT ENGINEER
Responsible to: Procurement Manager
Packages Handled: All packages including Long Lead Delivery, i.e.: Pedestal Cranes, Compressors, Gas Turbines, Generator Packages. Projects Handled: - “Kerisi” Wellhead Platform (WHP / 4 Jacket Legs), and
“Kerisi” Central Processing Platform (CPP / 8 Jacket Legs), Natuna Islands, Indonesia, Client: ConocoPhillips Indonesia Inc. (COPI).
- September 1998 – January 2005, P.T. ISTANA KARANG LAUT / IKL (Head Office Jakarta, Indonesia) – Engineering, Procurement and Construction for Oil & Gas Sectors Assignment as SNR. EXPEDITOR cum BUYER
Responsible to Procurement Manager
Packages Handled: Expedite all disciplines / packages. Projects Handled: 1. CO2 Removal Skid (Lawe-Lawe Terminal, East Borneo, Indonesia), Client: UNOCAL, 2. Chemical Injection and CO2 Removal Skid (Cikarang, West Java, Indonesia), Client: Ellips Energy, 3. Hang Tuah HVAC Package Natuna Islands, Indonesia). Client: ConocoPhillips Indonesia Inc. (COPI), 4. Tunu 8 Project (Handil, East Borneo, Indonesia). Client: TOTAL Finaelf, 4. Chemical Injection Package (Musi Banyu Asin, South Sumatra, Indonesia). Client: Musi Banyu Asin Energi.
- February 1997 – May 1998, P.T. BOUYGUES OFFSHORE INDONESIA / BOI
(Pendingin Base – Samarinda, East Borneo, Indonesia) – Procurement, and Construction for Oil & Gas,
Assignment as MATERIAL CO-ORDINATOR
Responsible to Procurement Manager
Project Handled: Tunu 1 Project / Client: TOTAL Indonesie.
.
- February 1995 – October 1996, ABB LUMMUS CREST B.V. / ABB (Bontang, East Borneo, Indonesia) Construction Company for Power Plant, Petrochemical, Mechanical
& Electrical.
Assignment as MATERIAL CONTROL SUPERVISOR
Responsible to Construction Control Manager
And OFFICE ENGINEER / SENIOR DOCUMENT CONTROLLER
Project Handled: DKM Melamine Project / Client: PUPUK Kalimantan Timur, Bontang, Indonesia.
Page 6 of 6
- August 1991 – June 1994, P.T. GEMA SEMBROWN / GSB (Sunda Strait Fabrication Yard, Cilegon, West Java, Indonesia) Fabricator, Construction Contractor. Assignment as SNR. DOCUMENT
CONTROL
Responsible to Control Manager
Projects Handled: “Belida” Wellhead Platform – B (WHP-B, 4 Jacket Legs), Lift Gas Platform (LGP, 4 Jacket Legs) / Client: ConocoPhillips Indonesia Inc. (COPI).
- September 1989 – August 1991, P.T. McDERMOTT INDONESIA / PTMI (Batam Base
– Batam Islands, Indonesia) Fabricator, Construction Contractor. Assignment as QA/QC DOCUMENT CONTROLLER
Responsible to QA / QC Manager
Projects Handled: 1. DPP – A Drilling Platform (8 Jacket Legs), Natuna Islands, Indonesia, Client: ConocoPhillips Indonesia Inc. (COPI), 2. BNA & BG Platform, Java Sea, Indonesia, Client: ARCO, 3. Bongkot Wellhead Platform (Bongkot, Thailand), Client: TOTAL Thailand, 4. ARAMCO’s Compressor (Kingdom of Saudi Arabia), 5. Enterprise Bawean Oilfield’s Skid (Java Sea, Indonesia), and 5. Amerada Hess Jacket (North Sea).
THANK YOU