CURRICULUM VITAE (CV) OF REAZ UDDIN AHMED
*. Proposed Position As Applicable
2. Name of Staff Reaz Uddin Ahmed
3. Date of Birth 15 October 1980 Nationality Bangladeshi (NID 511-***-****) 4. Contact Number +880********** Email address ***********@*****.***.** 5. Present Address House No. 05 Road No. 11, Gulshan Badda Link Road, Badda, Dhaka 1212 6. Permanent Address Village: Jalakandi, PO: Gopaldi, Thana: Araihazar, District: Narayangonj 7. Education • Bachelor Degree in Mechanical Engineering, National University of Singapore, Singapore, 2013
• Diploma in Mechanical Engineering, Ngee Ann Polytechnic, Singapore, 2008
• Diploma in Marine Engineering, Bangladesh Institute of Marine Technology, Bangladesh, 2000 8. Membership of Professional
Associations
• CSWIP 3.1-Certified Welding Inspector - Level 2 (License No. 91835/2), TWI, United Kingdom
• COC - Certificate of Competency in (Steam Boilers), Singapore Maritime Academy, Singapore 9. Other Training • Work Health and Safety, Learning and Development Team, Bangladesh, 2020
• Risk Management Implementation Plan, Association of Singapore Marine Institute, Singapore, 2018
• Management Training, Sembcorp Marine Integrate Yard, Singapore, 2017
• Basic Concept in Construction Productivity Enhancement, Building and Construction Authority, 2016
• ISO 9001:2008 Internal Auditor Training, Joel Management Consultant, Singapore, 2014
• Enhanced Take 5, Keppel Shipyard Pte. Ltd, Singapore, 2013
• Advanced Quality Control & Assurance Inspector in Action, SMI Centre of Excellence Asia, 2013
• Understand Contracts, Exploiting Innovation, Spreadsheet Math, Interpersonal Skills, NUS, 2012
• Effective Personal Skills, Time/Stress Management, Writing for Results, NUS, Singapore, 2011
• Problem Solving and Decision Making (Operation), Kaplan City Campus, Singapore, 2011
• Expanding Mindsets, Lateral Thinking Skills, Entrepreneurial Skills, National University of Singapore 2010
• IT for Business Application, 3D Solid Works Primer, National University of Singapore, 2010
• Personal Effectiveness (Supervisory), Kaplan City Campus, Singapore, 2010
• Lifting Supervisor, Ministry of Manpower, (MOM) Singapore, 2009
• 3D Design (Pro-E), Power Excel User, PLC, Automation, Ngee Ann Polytechnic, Singapore, 2007
• Risk Assessment, Risk Management, Association of Singapore Marine Institute, Singapore, 2006
• Computer aided Engineering Drawing (Auto CAD), Ngee Ann Polytechnic, Singapore, 2006
• Advance English Pronunciation and Speech Course, Ngee Ann Polytechnic, Singapore, 2005
• National Trade Certificate 3 in Marine Mechanics, Institute of Technical Education (ITE), Singapore, 2005
• National Trade Certificate 2 in Marine Mechanics, Institute of Technical Education (ITE), Singapore, 2004
• Shipyard Safety Supervisor, Ministry of Manpower, Singapore (MOM), Singapore,2003
• Marine Riggers and Marine Signalmen, Association of Singapore Marine Institute, Singapore, 2002
• 3G Welding, Association of Singapore Marine Institute, Singapore (ASMI), 2001 10. Countries of Work
Experiences
Singapore, China, Bangladesh
11. Languages Speaking Reading Writing
English Good Good Good
Bengali Good Good Good
Hindi/Tamil Basis None None
Chinese/Malayu Basic None None
12. Employment Record
From (Year) To (Year) Employer Country Positions held July 2020 Till date
National Development
Engineer (NDE) Ltd.
Bangladesh DGM – Technical Operation &QHSE
July 2018 June 2020 SMEC-ACE Consultants Ltd. Bangladesh Construction Supervision Consultant/Specialist July 2016 June 2018 Sembcorp Marine Pte. Ltd. Singapore Senior Project Engineer (Construction & Commissioning) Jan 2014 June 2016 Keppel Offshore & Marine Ltd. Singapore Senior Mech & Piping Engineer (Engineering &Design) July 2009 Dec 2013 Keppel Offshore & Marine Ltd. Singapore Lead QA Engineer (Construction & Commissioning) Jan 2008 June 2009 Keppel Nantong Shipyard Ltd. China Engineer (Construction & Commissioning) Oct 2001 Dec 2007 Keppel Offshore & Marine Ltd. Singapore Asst. Engineer (Construction& Commissioning) 13. Work Undertaken that Best Illustrates Capability to Handle the Tasks Assigned Name of assignment or project:(i) Meghnaghat Combined-Cycle Power plants, (ii) Hazrat Shahjalal International Airport Expansion(iii) Chittagong to Dhaka Pipeline
Year: July 2020 to Present
Location: Various Locations
Client: Various Clients
Main project features: (i) This is a project to build a 718MW combined cycle power plant consisting of two gas turbines, one steam turbine, two heat recovery boilers and a substation. (ii) The expansion includes the construction of the third passenger terminal building known as Terminal 3, as well as a 5,900m VVIP complexes, 41,200m cargo building and multi-level car parking building with tunnel. The new international passenger terminal building will have a floor area of roughly 226,000m . inclusive, various water treatment, drainage system, power supply, rescue and fire-fighting facilities will also be built as part of the development. (Iii)The 246km-long cross country pipeline which started in Chittagong and ends in Dhaka consist of 237.71km 16-inch diameter pipeline from BPC's Chittagong tank terminal to Godnail tank terminal in Narayanganj via Feni, Cumilla, Chandpur and Munshiganj and8.29-km 10-inchdiameterpipeline from Godnail to Fatullah in Narayanganj to carry oil. There are nine stations across the entire pipeline and a new fuel depotset up in Barura upazila of Cumilla. Position held: DGM-Quality Health Safety Environment Activities performed: As a DGM-Technical Operation and QHSE in charge of following tasks but not limited to;
• Headed the team pertaining to Project/Factory Operation & QHSE related activities and compete the project without compromise quality & safety to assigned projects under Engineering, Procurement, Construction (EPC), Installation, Commissioning, Operation and Maintenance
• Identify Factory & Site service requirements and provide technical guidance for fabrication, erection, commissioning, operation &maintenance
• Study & design of mechanical modification at site & factory facilities, execute capital projects according to the work scope, schedule and budget
• Supervise inspection of vendor supply material/equipment upon arrival as per PO & DO and approved drawing (identification, dimension & quality), as well as provide direction of equipment installation, commissioning, operation & maintenance as per approved drawing & manual
• Ensure of equipment performance and advise repair/modification of equipment in accordance with approved/respective equipment manual
• Develop and implement strategies to improve project planning, cost, schedule, and quality as well as resolve project management problems
• Review, approved & Control Project Quality documents & procedure, Method of Statements and subsequent approval from Client/Consultant
• Identify Contract Quality requirements, review/approval of supplier/subcontractor ITP, other Quality Procedures(PQP, PQR, QAP, WQTR, WPS, PWHT, NDT, Hydro Test, Pressure Test etc.) and Lab Test (Tensile, Bend, Macro and Impact etc.) as well as Painting Procedure
• Responsible for Training and Certification of Welders and take the Welder Qualification Test, organize Post Weld Heat Treatment (PWHT)
• Ensure base metal specification and welding consumables. Verify correct application of welding procedure – welding surveillance. Ensure that only approved welding procedures are followed and welders are qualified as well as all relevant equipment at site are with valid calibration
• Monitor welder performance and repairs of welding, provide technical guidance for welding sequence and distortion control in accordance
• Ensure that employees are following scope of work, approved equipment/tools & safety instructions prior to work and during work at all time
• Witness, review and approved NDT (UT, RT, PT, MPT) reports and advise corrective action. Provide training to operate various equipments related to material quality test e.g. Universal Testing Machine (UTM), Spectrometer, Rock-well Hardness, Impact Tester, Ultrasonic, X-Ray etc.
• Oversee the project quality control & assurance activities as detailed such as; manage daily various types in house inspection, issue punch list and NCR & advise corrective action prior to final Site Acceptance Test (SAT) by Owner as per project specification, closed client NRC on time
• Review painting specification, ensure that only approved painting procedures are followed and all equipment at site are with valid calibration
• Supervise various inspection of surface preparation & painting WFT & DFT as per approved painting procedures and technical data-sheet
• Prepared design change notes, investigate damage, quality & safety incident, issued quality observation/incident report & improvement notes
• Attended and investigate warranty works (after sales service) pertaining to performance, quality and safety issues, advise corrective action, generated technical report& submitted to client & top management follow up until closed, presentation as a lesson learn
• Participated weekly/monthly management meeting, project meeting, production meeting, and quality meeting as well as attends kick-off quality meetings with Client, Vendor, Contractor and Sub-Contractor. Presentation Quality & HSE policies to clients prior to contact awarded
• Prepare weekly/monthly project progress and submit to management, organise Quality internal audits & facilitate external audits
• Support continuous improvement activities and statistical analysis. Establish & maintain the QMS requirement as per ISO 9001:2015. Name of assignment or project: Padma Multipurpose Bridge Project Year: July 2018 to June 2020
Location: Bangladesh
Client: Bangladesh Bridge Authority
Main project features: The project undertaking by the Bangladesh Bridge Authority and financed by Bangladesh Government. The Padma Multipurpose Bridge Project (PMBP) is approximately 40km south west from Dhaka comprise a new fixed crossing of the Padma River in Bangladesh. The PMBP are composed of mainly five contracts; (i) Main Bridge Construction, (ii) River Training Works, (iii) Mawa Approach Road & selected bridge-end facilities, (iv) Janjira approach road & selected bridge-end facilities, and (v) Service Areas-2. The Major and most important two contracts namely Contract Package No.1 for Main Bridge Construction (MB) and Contract Package No.2 for River Training Works (RTW). The Main Bridge Contract comprises into two main components; Two- level steel truss bridge across the Padma River with a total length of 6.15km, and 3.68Km of approach viaduct for road 3.148 km and rail line 0. 532km.comprising 41 spans of 150m each. It is founded on 42 piers comprising larger diameter 3m driven Steel Tubular Pile or Cased Bored concrete piles (inclined at 1H:6V) to minimum depth of 100~ 125m with cast in situ concrete pile, pile caps and piers as well as6.15 km long and 30-inches diameter natural gas pipeline on the bridge railway deck. Position held: Construction Supervision Consultant/Specialist Activities performed: As a Construction Supervision Consultant/Specialist in charge of following tasks but not limited to;
• Review/approve contractor’s ITP, other quality procedures, method of statement, quality assurance plan, shop drawings and NDT plan etc.
• Perform receiving inspection of individual equipment/members of truss spans and gas pipeline which were fabricated & shipped from China, review of truss/pipeline member’s identification & tractability, dimensional accuracy and non-conformity in accordance to approved drawing
• Review and witness of contractor’s WPS (Welding Procedure Specification) & WQT (Welder Qualification Test) to ensure the quality work
• Check welding consumables and base metal specification. Verify correct application of welding procedure – welding surveillance & supervise
• Ensure that only approved welding procedures are followed and welders are qualified as well as all equipment at site are with valid calibration
• Monitor welder performance and repairs of welding, provide technical guidance & advise for welding sequence and distortion control accordingly
• Ensure that contractors are following scope of work, approved equipment/tools & safety instructions prior to work and during work at all time
• Supervise and inspection all types of fit-up, fabrication, NDT, painting, mechanical test (PTP-Production Test Plate, Bend Test and Bolt Torque Tightening), assembly, erection activities of Steel Truss Span, Steel Tubular Pile, Railway Stinger & Natural Gas Pipeline to ensure the quality
• Ensure dimensional accuracy of node-chord assemblies, steel truss frames assemblies and 150-meter-long spans assemblies; and also ensure that contractor following & maintaining the correct camber values to each node point according to the approved shop drawings
• Check painting specification, ensure that only approved painting procedures are followed and all equipment at site are with valid calibration
• Attend various inspection of surface preparation & painting WFT & DFT as per approved painting procedures & painting technical data-sheet
• Review of final dossier of each 150-meter long Steel Truss Spans,125-meter long Steel Tubular Piles and 30-inches diameter natural gas pipeline; make sure that the concerned parties signed all documents before releasing for erection
• Coordinate with contractor’s/sub-contractor’s representative on a regular basis to resolve problems or issues arises during daily works
• Prepare weekly/monthly project progress and submit to management, due diligently perform any other tasks as assigned by PM/Team Leader. Name of assignment or project:Sleipnir (The world’s largest dual-fuel (LNG and MGO) semi-submersible crane vessel) Year: July 2016 to June 2018
Location: Singapore
Client: Heerema Offshore Services Pte Ltd, Netherland Main project features: IMO equipment Class 3, Lloyd's Register DP (AAA)Length 220 m (721 ft) Width 102 m (334 ft) Length over Work Deck 180 m
(590 ft) Beam over Work Deck 97.5 m (320 ft) Depth to Work Deck 49.5 m (162 ft) Draft range 12-32 m (39-104 ft) Lifting Capacity Two heavy-lift cranes, each with a lifting capacity of 10,000 tonnes (able to lift 20,000 tonnes when working in tandem) Crew Accommodations Up to 400 Helicopter Deck Diameter - 28 m Load Capacity – 15.6 tonnes Thrusters Forward end - Four (4) retractable, underwater demountable fixed pitch, variable speed azimuth thrusters of 5.5 MW each Aft end - Four (4) underwater demountable fixed pitch, variable speed azimuth thrusters of 5.5 MW each Mooring System 4 x 3 point mooring system, 3 1/8" wire ropes of 1,750m, minimum breaking strength 578 tonnes Stevpris Mk-6 anchors of 12 ton each Speed Cruising speed of 10 knots Engines 12 engines of 8MW each Fuel Dual-Fuel (Marine Gas Oil/Liquefied Natural Gas) Position held: Senior Project Engineer (Construction & Commissioning) Activities performed: As a Senior Project Engineer (Construction& Commissioning) my responsibilities are following but not limited to;
• Prepare overall schedule and manage the Project Execution Plan, control the cost budgeting and work within the specified schedule prepared
• Maintain contacts with Clients, Surveyors& Consultants with good working relationship, Conduct regular meetings with consultants, clients, surveyors, vendors and contractors, sub-contractors for smooth execution of project as per stipulated schedule
• Ensure that safety is in proper control, including the quality control on site. Prepare final accounts including settlement of claim, change orders
• Review method of construction for various trades& subsequent approval from client & surveyor, materials to be in accordance to specifications
• Close co-ordinate with Classification society with regard to Classification standards & certification (SOLAS, MARPOL, Load Line, Tonnage etc.)
• Lead negotiation with suppliers on settlements & disputes, managed high valued contracts with system supplier for the majority of procurement
• Managed procurement, engineering and construction teams in the execution of works on the major milestone in the project
• Lead design team and construction teams in planning and coordination work performed on integration in design and construction aspects
• Established good working relationship with suppliers and controlled supplier's scope of supply as well as schedules to avoid impact to quality
• Identify Contract Quality requirements, review/approval of supplier/subcontractor ITP, other Quality Procedures & Certification Dossiers
• Provide technical guidance for equipment and piping installation, testing and commissioning sequence and performance control accordingly
• Prepare weekly/monthly project progress and submit to management, attended project internal audits & facilitate external audits. Name of assignment or project: (i) Bhagwan Dryden (Dive/Offshore Support Vessel), (ii) MTD DLV 2000 (180M Pipe lay Vessel) Year: January 2014 to June 2016
Location: Singapore
Client: (i) Bhahwan Marine Pte Ltd, Australia, (ii) McDermott Hydro Marine Inc.USA. Main project features: (i)Classification: American Bureau of Shipping ABS A1, DSV Air, FFV 1, SPS, AMS, ACCU, DPS-2,, Offshore Support Vessel, ENVIRO, GP, RRDA, UWILD, CRC, certified to IMDG Code, Length Overall: 56.8 M, Beam: 16 M, Depth Moulded: 6.3 M, Design Draft: 3.3 M, GRT: 1475 T Dead Weight: 250 T.2 x CUMMINS QSK19, 400 ekW, CORVUS Battery System, 2 x Thrust Master TM 300 MLRT, (ii) Classification: American Bureau of Shipping (ABS), Flag Panama, Gross tonnage 45247 tons, Deadweight 16000 tons, Length 182 m, Breadth 38, m6 x Wartsila 12V32, ABB AMG 0900SM10 LSE, 5790 kW x 720 rpm, RRM UL 255 FP x Fixed Pitch Prop x 2800mm x 227rpm, ABB AMI 500L6L BAFTMM x 2000 kW x 1200 rpm, 2 x RRM UUC 455 FP x Fixed Pitch Prop x 4100mm x 157rpm, ABB AMI 710L6L VAFTMM x 5500 kW Position held: Senior Mech & Piping Engineer (Design & Engineering) Activities performed: As a Senior Mech & Piping Engineer (Design & Engineering), in charge of beneath mentioned works;
• Working within the project team on onshore/offshore feasibility, conceptual, pre-FEED, FEED, detailed design and EPC phase of the project
• Calculating & sizing various mechanical equipment, Piping, integrated system design, design/reviewed/approved of machinery layouts & GA’s
• Perform supporting calculation, fabrication drawing and construction sequence for piping, outfitting, various equipment seating/foundation
• Reviewed/approved technical & purchase specification for all type of piping & outfitting material, machinery & their supporting systems
• Reviewed/approved Ship System P&ID and PFD, construction standard, commissioning procedure, FAT/SAT procedure, sea trial procedure
• Answer technical quires raised by vendor, clients, surveyor and sub-contractor, solve on site design issues& prepare as build drawing
• Coordinate & liaise with the various local & international statutory authorities, ship owner, classification surveyors, vendors, contractors, sub- contractors & other discipline engineers to meet the design requirement as per contractual specification
• Attended weekly/monthly client meeting, management meeting, project meeting, production meeting, quality meeting & section meeting
• Attended sea trial and recorded all types of machinery operation data and make sure meet the requirement & specification, advise on correction action& guide commissioning teams. Headed the team of Engineers, Junior Engineers, draft-persons in completion of the assigned project
• Due diligently perform other tasks as assigned by Team Leader/Project Manager. Additionally, Compliance with following Classification Society & Statutory authorities Rules and Registration;
• IACS (International Association of Classification Societies) - ABS, LR, DNV-GL, BV and RS etc.
• Maritime Technical Standard - MARPOL 73/78 - International Convention for Prevention of Pollution from Ship etc.
• Codes and Standards - ISPS 2003, ITTC (International Towing Tank Conference) - Full Scale Maneuvering Trial Procedure etc.
• Maritime Safety Standard -SOLAS (International Convention for the Safety of Life at Sea), IMO Resolution, ILO Resolution etc.
• FFS 2007 (International Code for Fire Safety System), CSS 2003 (Code of Safe Practice for Cargo Stowage and Securing) etc.
• Quality Standard & Regulation - API, ASME, NACE, ASTM, CSWIP, NS, BS, UKS, DIN, NPT etc. ISO 9000 and ISO 14001 etc. Name of assignment or project: (i) Greatdrill Chitara (Jack Up), (ii) Yuri Koraghain (FPSO), (iii) CastorOne (World biggest Pipe Laying Vessel) Year: July 2009 to December 2013
Location: Singapore
Client: (i) Great ship Global Offshore Service, (ii) Lukoil Nizhevolzhsknef, (iii) Eni, Saipem Main project features: (ii) Class society: American Bureau of Shipping (ABS), Flag-India, 2988 t DWT,64m x 73m x 7.6m, 2 x CUMMINS QSK19, 400 ekW, CORVUS Battery System (ii) Class society: American Bureau of Shipping (ABS),Length Overall x Breadth Extreme: 132.8 x 32.4 m, Gross Tonnage: 20737, Flag: Russia, MAK 8MC20, 4 x 1080kw, (iii)Classification society: American Bureau of Shipping (ABS) - A1, Crane Service, Pipe Laying Service, E, AMS, ACCU, DPS-3, RRDA, EHS-P, UWILD, TCM, PMP+, CRC, Ice class A0, Ice class 1A, Helidk (SRF),Flag (Registration)- Bahamas, Gross Tonnage 102032, Deadweight (t) 32602, Length (m) 325, Beam (m) 39,Wartsila 12V38B, 8 x 8700KW x 600 rpm, 6 x Retractable Azimuth Thrusters x 5500 kW,3 x Tunnel Thrusters x 2500 kW, Position held: Lead QA/QC Engineer (Construction& Commissioning) Activities performed: As a Lead QA/QC Engineer (Construction& Commissioning) my responsibilities are following but not limited to;
• Headed the QA/QC team pertaining to project quality related activities of Structure, Piping, Outfitting, Mechanical & Electrical and competed the project within project quality control & assurance specification to assigned projects under construction, commissioning and operation
• Identify Contract Quality requirements, review/approval of supplier/subcontractor ITP, other Quality Procedures & Certification Dossiers
• Develop, review & Control Project Quality documents such as PQP, ITP, Other Quality Procedures (WPS, PQR, NDT, Air & Hydro Test, Pressure Test etc.), Painting/Coating Procedures, Method of Statements, SOP and subsequent approval from Client & Surveyors
• Participated weekly management meeting, project meeting, production meeting, quality meeting, daily safety coordinate meeting as well as attend kick-off quality meetings with Client, Surveyor, Vendor, Contractor and Sub-Contractor
• Verified and attended joint inspection vendor supply equipment/material upon arrival as per PO & DO, attended various types of FAT/SAT together with Owner & Class, issued internal NCR, follow up and closed client NRC on time
• Carry out the project quality control & assurance activities as detailed such as; attended daily various types in house inspection, issue punch list
& advise corrective action prior to final SAT by Owner & Class as per project specification
• Provide technical guidance for construction and commissioning sequence and monitor performance control in accordance with procedures
• Manage QRMS (Invite owner & class for inspections, generate daily inspection reports, update daily inspection status, incorporate punch items & NCR and monitor the status, administrative & completion of final dossier) as well as familiar with PIMS data base system
• Prepared design change notes, investigate damage & quality incident, issued quality observation/incident report & improvement notes
• Ensure that all standard operating procedures comply with specifications, quality standards, statutory and regulatory requirements.
• Attended and investigate warranty works pertaining to quality issue, advise corrective action, generated technical report witting & submitted to client & top management follow up until closed, presentation as a lesson learn
• Prepare weekly/monthly project progress and submit to management, attended Quality internal audits & facilitate external audits. Name of assignment or project: MV Sea Comanche (Anchor Handling Tug/Supply) under Keppel Nantong Shipyard, China Year: January 2008 to June 2009
Location: China
Client: GulfMark Offshore Inc, USA
Main project features: Class society: American Bureau of Shipping ABS A1, AMS, ACCU, DPS-2,, TCM, AH/Offshore Support & Towing Vessel, Fire Fighting Class 1, LOA 76 m Breadth 17 m Depth 7.6 m Draft 6.2 m GT 2943 T Deadweight 2700 T @ 6.2 m draft, MAK8MC20, 4 x 2650 Bhp c/w CPP (twin input single output), Speed-14.5 knots, Bollard pull-150T Position held: Engineer (Construction& Commissioning) Activities performed: As an Engineer my responsibilities are beneath mentioned but not limited to;
• Headed and led the Mechanical and Piping department to developed and improved, Coach and guide the junior engineers, technicians etc.
• Oversee project planning, manpower budgeting, controlling, executing, monitoring, safety matters, quality survey, inspection& documentation
• Attended weekly/monthly client meeting, management meeting, project meeting, production meeting, quality meeting & section meeting etc.
• Completed the machinery & piping fabrication, installation, mechanical completion, pre-commissioning, commissioning on time & within budget
• Completed construction& commissioning, attended sea trail & successfully delivered the project without compromised of Safety & Quality
• Prepare weekly/monthly project progress and submit to management, due diligently perform any other tasks as assigned by PM/Team Leader. Name of assignment or project: (I) Tyco Dependable (Cable Laying & Repair Vessel), (ii)Pacific Silver (Offshore Supply Ship), (iii) Toboy
(Multipurpose Ice Breaking Supply Vessel), (iv) MV Sea Cheyenne (Anchor Handling Tug/Supply Vessel) Year: October 2001 to December 2007
Location: Singapore
Client: (i) Tycom Reliance, USA (Ii) Pacific Richfield Marine Ltd, Singapore (Iii) Lukoil Kaliningradmorneft,Russia (Iv) GulfMark Offshore Inc, USA Main project features: (i) Classification society: American Bureau Of Shipping (ABS),Length 139.1 m Breadth 21.0 m Depth 7.8 m Gross tonnage 12184,7800 BERGEN, BERGEN, 5 x 2100 KVA, 3300V Diesel Gensets (ii) Class society: American Bureau Of Shipping (ABS), Length: 76 m Beam: 17 m Draught: 6.6 m Gross tonnage:3,228 tons, Wartsila 2 x 6000 Bhp, PTO/PTI, Bollard Pull-200T (iii)Classification society: Russian Maritime Register of Shipping (RS),Length: 81.6 m Beam: 18.5 m, Gross Tonnage 4406, Wartsila 9L32, 4 x 4250kW, Bollard pull-100T (iv) Classification society: American Bureau Of Shipping ABS A1, AMS, ACCU, DPS-2,, TCM, AH/Offshore Support & Towing Vessel, Fire Fighting Class 1,LOA 76 m Breadth 17 m Depth 7.6 m Draft 6.2 m GT 2943 T Deadweight 2700 T @ 6.2 m draft,MAK8MC20, 4 x 2650 Bhp c/w CPP (twin input single output), Speed-14.5 knots, Bollard pull-150T Position held: Asst.Engineer (Construction& Commissioning) Activities performed: As a Asst.Engineer in charge of following tasks for various specialized vessels under construction meet the project specification and quality standard;
• Oversee project planning, manpower budgeting, controlling, executing, monitoring, inventory, safety, quality, inspection& documentation etc.
• Supervise various shipboard Machinery and Piping storage, fabrication, preservation, installation, alignment, protection, mechanical completion, pre-commissioning, commissioning, testing, operation and maintenance in accordance to project speciation and classification requirement
• Coordinate as a front-line yard representative between the vendor, ship owner, classification surveyors, contractors and sub-contractors
• Attended all construction & commissioning inspection, responsible for completed the construction, commissioning, sea-trial as per specification
• Headed the team of construction/commissioning QC, officers, technicians, supervisors& subcontractors in completion of the assigned projects
• Prepare weekly/monthly project progress and submit to management, due diligently perform any other tasks as assigned by PM/Team Leader. Performed following equipment and their piping systems fabrication, installed, mechanical completion and commissioning;
• Main Engine & Generator, Auxiliary Engine & Generator, E Generator and their supporting equipment & systems, various switchboards etc.
• Boiler - Steam Boilers (Low, Medium & High), Exhaust Boiler, Economizers, Hot Water Boilers and their supporting equipment & systems etc.
• Cargo System-Various Cargo pumps (LNG, Heavy Fuel Oil, Marine Gas Oil ), Various Compressor (HP, IP & LP) & Heat Recovery System etc.
• Ship Marine Systems – HFO/MGO Supply & transfer Pump & System, FO & LO Purifier & Separator, FW and SW Cooling pump & System etc.
• Fire Fighting Systems - Fire Fighting Pump & Systems, Fire Protection, Detection & Alarm Systems, Water Mist Systems, Co2 System etc.
• HVAC - Main Air-Cons, Freezer Room & Chiller Room Air-Cons, Accommodation Air-Cons, Air-Con Ducting & Ventilation Systems etc. 14. Certification:
I, the undersigned, certify that to the best of my knowledge and belief, this CV correctly describes myself, my qualifications and my experiences. I understand that any willful misstatement described herein may lead to my disqualification or dismissal, if engaged. 07/03/2023
Signature Date: