Post Job Free
Sign in

Planning Engineer Project Manager

Location:
Maputo, Mozambique
Salary:
3,900 USD
Posted:
February 14, 2023

Contact this candidate

Resume:

ARMANDO LOPES

Planning Engineer

PROFILE

I have 13 years of experience in Civil

Engineering Projects which are 8 years

working Planning, Monitoring and

Control. I have experience in using MS

Projects 2016, Primavera P6, Excel and

Power Point Software. I have basic

Knowledge of the methodology’s

promotion by PMI (Project

Management Institute PMBOCK 6th

Edition

CONTACT

PHONE:

+258-**-**-**-***

+285-**-**-**-***

EMAIL:

***************@*****.***

HOBBIES

Academy and Music

BIBLIOGRAPHIC

REFERENCES

Yuyang_ CET/Project Manager

Cell: +258-**-***-****

Pravin Rugbar_ Kent, plc/ Project

Manager

Cell: 258-**-***-****

Acacio Nhamposse_ Kent plc/Planner

Cell: 258-**-***-****

Hugo Neves _ Mota Engil – Africa

Production Manager

EDUCATION

Higher Polytechnic Institute

Graduation in Civil Engineering

WORK EXPERIENCE

STATE GRID (China Electric Power Equipment and Technology Co., LTD) Planning Engineer

March–2022 _ Current

Employer: Intec (GOPA International Energy Consultants) Project: Design, Supply and installation of 400kV Air Insulated Substations (AIS) for Temane Transmission Project (TTP)

• Prepare & Issue planning package as per contractual terms & conditions and receiving approval from the Client within the stipulated period of the contract.

• Coordinate with the Project Manager, Site Manager, Site Engineers, Job Estimators, Engineers of various disciplines etc to acquire proper date and specifications for the schedule.

• Develop S Curve and Manpower histogram and check if these are achievable.

• Analyze Drawing, specifications & method statements of works for the preparation of activity networks/scheduling/ resources Planning and allocation.

• Assign duration, resources Manpower, Material and Equipment’s) and Budgeted cost for each activity based on their weight factor & quantity/volume of work. And identify long lead items required in the Project.

• Ensure that schedule is based on project execution strategy and schedule milestones are achievable.

• Develop databases for Engineering deliverables, Procurement deliverables, Construction activities for monitoring/analyzing tracking Progress.

• Review, analyze & refine sequence and logic of tasks/activities and highlight any critical activity needs particular attention.

• Resource Planning and Forecasting of projects & activities.

• Calculate & Manage Engineering productivity.

• Analyze schedule variance & plan remedy if there any negative variance.

• Revise the Project Plans & schedules (Re-planning and Reba lining) for variation orders/change orders/additional scope of works and Extension of Time.

• Prepare progress invoice

• Prepare weekly / monthly project reports

Kentz Engineers & Constructors, member of the Kent plc Planning Engineer

June-2021–March 2022

Employer: Vale (Implementation of Capital Projects, Vale Moatize Coal)

Project: Flotation & Filtration Phase 2 (Installation, Test Cold & Hot and Commissioning).

• Update Overall Project, Project Table %, S-curve, Productivity index per Discipline.

• Update SMEIP (Structure, Mechanical, Electrical and instrumental, Piping) Tracking Sheet.

• Update Schematic Presentation

• Prepare weekly project reports.

Mota-Engil Africa, Moçambique

Planning Engineer

February 2019 to June 2021

Employer: Vale (Implementation of Capital Projects, Vale Moatize Coal)

Project: Bridges and Viaducts/Deep and Shallow

foundations/Earthworks/Reinforced Earth Walls/Drainage.

• Initiate, prepare & develop Project plans & Schedules according to standards, contracts specifications and accepted Project Management practices.

• Develop major milestone activities & establish a well-defined work Breakdown structure, which includes all the scopes of work.

• Generate detail work Plan, critical activities /path, planned/Progress S-curve budget Histogram/Planned

distribution tables, Resource Histogram / Planned distribution tables etc.

• Collate date & other pertinent information of Project delay, if any, periodically by updating actual progress data.

• Develop action and recovery Plans to support project completion on time.

• Revise the Project Plans & schedules (Re-planning and reba lining) for variation orders/change orders/additional scope of works and Extension of Time.

• Ensure that schedule is updated and maintained valid throughout the duration of the project and that PM and team is aware of forward load and manpower availability. OAS Construction

Planning Technician

March 2013 to October 2014

Employer: Vale (Implementation of Capital Projects, Vale Moatize Coal)

Project: Port Construction Project

On-shore Civil Works Execution Project Porto de Nacala á Velha. Execution of Earthwork, Drainage, Implementation of Coal Storage Yard, 12 km of Stackers and Reclaimer Trails.

Construction of a car dumper, bridge and four underground passages

• Monitoring and Controlled Project activities

• Generated and updated daily, weekly Progress Report SKILLS

Primavera P6 70%

Excel 90%

Power Point 90%

MS Project 2016 90%



Contact this candidate