PERSONAL INFORMATION
Full Name: NGUYEN QUANG VINH
DOB: 10/10/1972
Gender: Male
Marital Status: Married
Nationality: Vietnamese
Languages: Vietnamese, English
Address: Hoang Quoc Viet Street, Phu My Ward, 7th Dist., HCMC
Current Salary & Expected Salary: Will be discussed to the interview
Notice period/Interview Availability: 2 weeks or negotiate
Contact: email: **********@*****.***; cell: +84 (0-913-***-***
EDUCATION
06/1996 DA NANG POLYTECHNIC UNIVERSITY/ENERGY SECTION
Bachelor in Heat Industry
TRAINING:
09/2017 Getting the training certificate for Installation/ and erection supervision for HVAC and Heat industry systems
05/2015 Getting the training certificate for General Project Management
2010 - 2011 To join in the training course for professional competition of tendering and QA/QC management training course
2006 HCMC POLYTECHNIC INSTITUTE
To participate in the Map-info (GIS) training course
2004 ASIAN PACIFIC INSTITUTE
To attend to the site supervision training course
2003 THERMO FLOW INC. (USA)
To join in the Advanced Gas Turbine (GT Pro.) and Steam Turbine Program (Steam Pro.) Developer’s system training course
1998 AOTS (JAPAN)
To participate in the training course for Crude Oil Firing
SKILLS / ASSESSMENTS
SUMMARY
Mr. Vinh is a senior leader/manager with experience in all phases of project implementation and construction management through site selection, feasibility study report, bidding document preparation, contract negotiation and site construction management for combined cycle power projects, coal fired power projects and oil fired power projects, etc up to hand over to the end-user;
He has also had managerial experience on every levels in construction/installation works for Oil Fired, Combined Cycle and Coal Fired Power Projects, etc….
He has over 20 years experience working with EVN and PVNs’ subsidiaries and has operated as a General Manager, Site Manager, Mechanical Leader, Senior Coordinator/ Mechanical Engineer/ Engineering Engineer.
He has over several years experience in wind power project development from beginning stage.
With one year working for DHIC as OEM General Manager, his duties covered the sale development works for equipment to serve the O&M works for the coal fired power plants; development the none-OEM works;
He has good relationship and connecting with key persons of MOIT, EVN, EVNGECO1, 2, 3; PVN and local and oversea companies who will develop LNG to Power projects in Vietnam, etc…for newly developing power projects, LNG terminals, developing of sale & marketing business.
ADDITIONAL SKILLS
Use some software expertly such as: Microsoft Excel, Word, Powerpoint, Autocad, etc. and technical software applying in designing the Combined Cycle Power Plant (GT-Pro) and Conventional Power Plant (Steam-Pro),
Good in teamwork and establish relationship.
SUMMARY OF EXPERIENCE
11/2019 – Present EPC SOLAR
Sale Manager (Southern Region)
10/2018 – 10/2019 Doosan Heavy Industries & Construction (DHIC)
General Manager
10/2013 – 08/2018 TPMB3 (OWNER’S REPRESENTATIVE)
Head of Mechanical Group and Deputy Site Manager
09/2012 – 09/2013 THAI SON GROUP (OWNER)
Deputy Project Manager
08/2010 – 08/2012 PTSC/ PTSC POWER
Mechanical Team Leader of Engineering Department
10/2007 – 07/2010 MARUBENI CORPORATION (JAPAN)
08/2009 – 07/2010: Warranty/ Liaison Engineer upto FAC of the Project
10/2007 – 07/2009: Site Engineer/ QA/QC Leader/ Coordinator upto PAC of the Project
09/2006 – 09/2007 POYRY LTD. AND PECC2 JOINT CONSULTANT (OWNER’S PMC)
Site Engineer/ Mechanical leader
10/1996 – 08/2006 POWER ENGINEERING CONSULTING COMPANY NO. 2 (EVN PECC2)
04/2005 – 08/2006: Site Manager/ Mechanical Leader
2000 – 2005: Designed Engineer/ Mechanical Leader for mechanical portion
2003 – 2006: Designed Engineer for mechanical portion
2001 – 2003: Engineering Manager/ Deputy Project Manager
1999 – 2001: Designed Engineer/Site Supervisor for combined cycle power projects
1996 – 1999: Designed Engineer for mechanical portion
PROFESSIONAL EXPERIENCE
11/2019 – Present EPC SOLAR
EPC Solar is an industry leader in clean energy fields
Sale Manager
Duties: As a developing manager for southern region and in charge for sale and development works for several solar power projects
10/2018 – 10/2019 DHIC
Doosan Heavy Industries & Construction is a leading EPC contractor offering a wide range of services ranging from the manufacturing of castings and forgings, power generation systems and desalination facilities to the construction of power plants.
General Manager
Duties: Coordinate with Clients in providing the OEM power services (boiler, turbine and its auxiliaries) for thermal power plants such as Mong Duong #1,#2 PP, Vinh Tan 4 & 4E PPs, etc…
10/2013 – 08/2018 TPMB3 (OWNER’S REPRESENTATIVE)
Lead of Mechanical Group and Deputy Site Manager
Duties:
Project: 60MW Wind Power Power Project – First stage (Scope of project: Owner)
Project location: Thanh Hai Commue, Thanh Phu District, Ben Tre Province
Client: EVN/ EVNGENCO1
Project Position: Lead of Mechanical Group
Duties and responsibilities:
oCoordinate with PECC4 Consultant for site selection and pre-FS and FS preparation;
Project: 2x622.5MW Duyen Hai 3 Coal Fired Power Project (Scope of project: Owner)
Project location: Mu U Hamlet, Dan Thanh Commue, Duyen Hai District, Tra Vinh Province
Client: EVN/ EVNGENCO1
Project Position: Lead of Mechanical Group and Acting Deputy Site Manager
Duties and responsibilities:
oCoordinate with PECC3-FITCHNER Joint Consultant for review and approval the engineering document and ITP/MS for each system;
oManagement and review and approval the submitted DWGs, Site ITPs, Site Work Method Staments, etc which is submitted by EPC Contractor and their sub-contractors;
oManagement and supervision the Site works of EPC Contractor and their Sub-Contractors for whole systems during construction, erection and commissioning of the captioned Project;
oInterface management for mechanical and others issues between engineering and others discipline in line project execution including Fire Fighting terminal points, HFO terminal points, Coal transfer tower terminal points connected with Sea Port Project; the auxiliary steam pipes connected to Duyen Hai 1’s auxiliary steam system and other terminal points;
oManagement the commissioning and start-up/reliability run and performance test of the 2 large boilers, turbines & its auxiliaries together with BOP system.
oConstruction management the Outstanding works, Punchlists and Warranty Defect Notice for the captioned Project during 2 years warranty periods;
oChair all site construction meetings with Consultant and EPC Consortium Contractors including their sub-contractors;
oAssigned as acting Deputy Construction Site Manager for the Project since April 2017;
Project: 1x680 MW Duyen Hai 3 Extension Coal Fired Power Project (Scope of project: Owner)
Project location: Mu U Hamlet, Dan Thanh Commue, Duyen Hai District, Tra Vinh Province
Client: EVN
Project Position: Lead of Mechanical Group
Duties and responsibilities:
oResponsible as Mechanical leader and in charge for Mechanical issues of FS Report, Bidding document preparation, Contract evaluation and negotiation for Duyen Hai 3 Extension Power Project;
oEvaluation of bidder’s proposals and negotiation with Sumitomo and its sub-Contractor;
oAssigned as Boiler system leader during contract negotiation with Sumitomo Corporation;
Project: 2x622.5MW Duyen Hai 1 Coal Fired Power Project (Scope of project: Owner)
Project location: Mu U Hamlet, Dan Thanh Commue, Duyen Hai District, Tra Vinh Province
Client: EVN/ EVNGENCO1
Project Position: Mechanical Engineer and Mechanical Leader
Duties and responsibilities:
oIn charge for Fire fighting work and coal handling system for engineering document review and site supervision for Duyen Hai 1 Power Project;
oInterface construction management for mechanical issues between engineering and others discipline in line project;
oIn charge to construction management of the NCR/SIs and outstanding works.
Project: 230MW Wind Power Project (Scope of project: Owner). First stage: 60MW; Second stage: 170MW;
Project location: Thanh Hai Commue, Thanh Phú District, Bến Tre Province
Client: EVN/ EVNGENCO1
Project Position: Mechanical Leader
Duties and responsibilities:
oIn charge in review of Pre- Feasibility Study Report and Feasibility Study Report prepared by PECC4;
oWorking as mechanical leader in implementation of the captioned project;
09/2012 – 09/2013 THAI SON GROUP (OWNER)
Main industry: Trading in real estate, land use rights of owner, owner or leased land
Deputy Project Manager
Duties:
Project: 6x110 MW Nhon Trach – Thai Son Coal Fired Power Project (Scope of project: Owner).
Project location: Nhon Trach District., Dong Nai Province
Client: Thai Son Group
Project Position: Deputy Project Manager
Duties and responsibilities:
oCoordinating with foreign consultant in site selection; Pre-FS preparation;
oOther businesses assigned by Manager of Investment Department;
08/2010 – 08/2012 PTSC POWER
Mechanical Team Leader of Engineering Department
Duties:
Project: 2x600MW Long Phu 1 Coal Fired Power Plant Project (Scope of project: EPC Contractor)
Project duration: 2010 - 2012
Project location: Thanh Duc Hamlet, Long Duc Commune, Long Phu District., Soc Trang Province
Client: Petro Vietnam (PVN)
Duties and responsibilities:
oIn charge for Mechanical issues of engineering dept. activities and detail engineering for Long Phu 1 Project;
oInterface management for mechanical issues between engineering and others discipline in line project execution including large Boilers and its auxiliaries; Steam turbines and its auxiliaries and BOP equipment for 2x600MW Coal Fired Power Plant Project during technical negotiation with oversea/main equipment contractors;
10/2007 – 07/2010 MARUBENI CORPORATION (JAPAN)
Range of business: lifestyle, ICT & real estate business, agri business, chemicals, energy, metals & mineral resources, power business, infrastructure project, aerospace & ship, finance & leasing business, construction.
Duties:
08/2009 – 07/2010: Warranty/ Liaison Engineer up to FAC of the Project
Working as Liaison Engineer/Leader (Warrantee period) for Marubeni Corporation as BOP Contractor for 450MW Nhon Trach 1 Combined Cycle Power Plant Project
10/2007 – 07/2009: Site Engineer/ QA/QC Leader/ Coordinator up to PAC of the Project
Working as Site Engineer & QA/QC Leader for Marubeni Corporation as BOP Contractor (EPC Consurtium) for 450MW Nhon Trach 1 Combined Cycle Power Plant Project;
Construction management and support local and foreign sub-contractors for civil works, material/equipment controls, installation and commissioning works.
Control the interfaces between civil, mechanical and electrical disciplines and interfaces between MC with Alstom and other Contractors.
09/2006 – 09/2007 POYRY LTD. AND PECC2 JOINT CONSULTANT (OWNER’S PMC)
Pöyry is an international consulting and engineering company.
PECC2 is one of the strong brands in the energy industry in Vietnam.
Site Engineer/ Mechanical leader
Duties:
Working as Site Construction Supervision Engineer/ Site Mechanical Leader (PECC2 side) for 750MW Ca Mau 1 CCPP Project upto the said plant is putting into commercial operation (PAC);
Review and approval the construction site document such as ITPs, Site Method Statement and HSE manual, etc…
Supervision of the start-up, trial run, performance test of the GTs Turbines and its HRSGs and their auxiliaries.
04/2005 – 08/2006 POWER ENGINEERING CONSULTING COMPANY NO. 2 (OWNER’S PMC)
PECC2’s main business is investigation, design, supervision and construction management of electric power projects as well as other industrial and civil utilities
Duties:
04/2005 – 08/2006: Site Construction Manager/ Mechanical Leader
Working as Thermo-Mechanical Leader (review drawing, document, site ITP, construction methods, site construction supervision) for 2x2.650MW Phu Quoc Diesel Power Station – Phase 2 upto the said plant handed over to End-User;
2000 – 2005: Designed Engineer/ Mechanical Leader for mechanical portion
Working as Thermo-Mechanical Leader in preparing the Feasibility Study Report (FS), Basic Design Report, Technical Design Report, Cost Estimation and Tender Document for Pha Lai Maintenance Service Center for Pha Lai Thermal Power Plants;
2003 – 2006: Designed Engineer for mechanical portion
Working as Mechanical Engineer in preparing the Master Plan and Cost Estimation for Nhon Trach Power Complex with capacity 2640MW in total;
2001 – 2003: Engineering Manager/ Deputy Project Manager
Working as Deputy Project Manager in preparing the Feasibility Study Report (FS), Basic Design Report, Technical Design Report, Cost Estimation and Tender Document for Oil to Gas Fuel Conversion for Thu Duc Power Plants Project with capacity 238MW in total;
1998 – 1999: Designed Engineer for mechanical portion
Working as Designed Engineer in preparing the Feasibility Study Report (FS), Basic Design Report, Detailed Design Report, Cost Estimation and Tender Document for 720MW Ca Mau Combined Cycle Power Plant Project;
1997 – 2001: Designed Engineer for mechanical portion
Working as Design Engineer in preparing the Pre-Feasibility Study Report (Pre-FS), Feasibility Study Report (FS), Basic Design Report, Technical Design Report, Cost Estimation and Tender Document for 600MW Nhon Trach Combined Cycle Power Plant Project;
1997 – 2004: Designed Engineer for mechanical portion
Working as Design Engineer in preparing the Pre-Feasibility Study Report (Pre-FS), Feasibility Study Report (FS), Basic Design Report, Technical Design Report, Master Plan, Cost Estimation, Tender Document and Site Supervision for 450MW Phu My 4 Combined Cycle Power Plant Project;
1999 – 2005: Designed Engineer for mechanical portion
Working as Designed Engineer in preparing the Pre-FS, FS, Basic Design Report, Technical Design Report, Cost Estimation, Tender Document for 2x300MW O Mon Thermal Power Plant – Phase 1 and O Mon Thermal Power Complex (1200MW);
1998 – 2001: Designed Engineer for mechanical portion
Working as Designed Engineer in preparing the Feasibility Study Report (FS) for 715MW Phu My 2-2 BOT Combined Cycle Power Plant Project;
1996 – 1998: Designed Engineer/ Site Supervisor
Working as Designed Engineer in preparing the Pre-Feasibility Study Report (Pre-FS), Feasibility Study Report (FS), Basic Design Report, Technical Design Report, Cost Estimation, Tender Document and Site Supervision for 300MW Phu My 2-1 Open Cycle Power Plant Project;
1996 – 1998: Designed Engineer for mechanical portion
Working as Designed Engineer in preparing the Feasibility Study Report (FS), Technical Design Report, Cost Estimation for Rehabilitation of S4 Unit (33MW) for Can Tho Power Plant Project;
The information contained in this document is highly confidential. We request that no communication be entered into with either present or past employers of the candidate, or the candidate themselves, without the express permission of HR1Vietnam Co., Ltd. Interviewing this candidate indicates acceptance of our standard terms & conditions of business. By utilizing the information in this document you agree to be bound these terms of business and any form of employment effected either directly to a 3rd party will incur a service fee as stated.