Summary. E&I engineer with 15+ year’s experience.

Expertise in ELectrical maintenance planning, Ms-Office & Ms-Project.

Good knowledge of handling project, start-ups & commissioning & sound

experience of working in Electrical Department, Operation & Maintenance of Power Generation,where involves E&I control of compressors,transformer,chillers,switchgears & LV / MV panels variable speed AC drives, Generators (Cummins, Wartsila, Jenbacher, Caterpiller and CATMAK).

Professional Experience.

BYCO Petroleum Pakistan Ltd.

Maintenance Lead Senior Officer (Electrical & Power Generation)

March 16, 2017 to Continue.

A renowned Oil refinary plant in Pakistan. Oil Refinery-01 35000 bpd and Oil Refinery-02 150000 bpd producing refining of crude oil into various saleable components including liquefield petroleum gas, light naphtha, heavy naphtha, high octane blending components, motor gasoline, kerosene, jet fuels, high speed diesel and furnace oil.

Job Description

Responsible for Refinary and Substation routine and emergency jobs execution & communicate & report to my Manager, through emails, presentation and meetings.

Successfully analyze the root causes of any failures and their elimination through proactive measures, which resulted in significant reduction in maintenance cost and down time loss.

Modification of existing maintenance work procedure to minimize maintenance faults & optimize operation.

Led the team of 16 no's electrical staff including Engineers, Trainee engineers, supervisors, riggers and helpers during the Shutdown of oil refinery 01 & turnarounds of oil refinery 02.

Involved in computerized maintenance management system (CMMS) introduction and successful implementation within software SAP.

Manage all daily and monthly routine & unscheduled maintenance activities through planning in SAP.

Responsible for issuing of job PTW and to record equipment history over.

Responsible for planning annual & monthly maintenance schedules.

Supervision of preventive / predictive maintenance of plant including overhauling of rotary equipments.

Have hands on experience of Operation and Maintenance of following major Electrical and Mechanical Instruments.

Induction Motors (LV and MV) Having Power Up To 400 Hp, Manufactured By

WEG(UK), ABB(USA), LOHER, MAC, GE etc.

Transformer.

Siemens 100 to 1600KVA etc.

Switchgears (LV and MV) Manufactured By

GE(USA), SCHNIEDER ELECTRIC(UK), ABB(USA), SIEMENS etc

Air circuit breaker.

Upto 4000A Make: Siemens, schneider electric etc.

Lucky Cement Pakistan Limited (Power Generation).

Senior Electrical Engineer (Power Generation)

December 2016, to March 2017.

A renowned cement plant in Pakistan, Lucky Cement strives to remain an efficient and low cost producer and is one of the pioneers to introduce and install Waste Heat Recovery and Refuse Derived Fuel (RDF) and Tyre Derived Fuel (TDF) Plants in Pakistan. It also has self-sufficient Captive power generation facility of 180 MW and supplies additionally generated electricity to support the National grid. Lucky Cement owns a fleet of Bulkers & Trailers, which gives added advantage in terms of logistics and efficient deliveries to all types of customers spread across the length and breadth of the countryl.

Job Description

Responsible for operation of (Wartsila GAS 20VSG34, CATMAK DF 16CM32C & G16CM34, Role Royce B35 40V16AG, B3540V20AG power generation smooth operation and Substation routine and emergency jobs execution & communicate & report to my Manager.

Successfully analyze the root causes of any failures and their elimination through proactive measures, which resulted in significant reduction in maintenance cost and down time loss.

Modification of existing maintenance work procedure to minimize maintenance faults & optimize operation.

Novatex (Pvt) Ltd.

Assistant Manager E&I. September 21, 2007 to December 28, 2016

A renowned petrochemical plant in Pakistan, which is the only 900 T/Day producing bottle grade pet chips (BGC) & 350 T/Day producing textile grade pet chips (TGC) in Pakistan

I joined Novatex as a Trainee Engineer E&I and progressively moved to Assistant Manager E&I.

Job Description

Responsible for routine and emergency jobs execution & communicate & report to my superiors, through emails, presentation and meetings.

Successfully analyze the root causes of any failures and their elimination through proactive measures, which resulted in significant reduction in maintenance cost and down time loss.

Modification of existing maintenance work procedure to minimize maintenance faults & optimize operation.

Involved in computerized maintenance management system (CMMS) introduction and successful implementation within house built software MOGAN.

Manage all daily and monthly routine & unscheduled maintenance activities through planning in MOGAN.

Responsible for issuing of job work permits and to record equipment history over MOGAN.

Responsible for planning annual & monthly maintenance schedules.

Supervision of preventive / predictive maintenance of plant including overhauling of rotary equipments.

Extensively used product catalogues and manuals for installation and commissioning of E&I equipments.

Work in electrical & instrument department, which involves operation and electrical & instrument control of generators, compressors, chillers, switchgears and LT panels, variable AC drives.

Very Good Experience of Various Instrument Calibration.

Flow Transmitter

Level Transmitter

Temperature Transmitter (sensing element PT-100)

Proximity Sensors.

Hart Communicator.

Successfully handle projects.

Erection of JENBACHER JGS-420 Gas Engines

First Major erection work. Commissioning of JGS-420. (3)Jenbacher Gas Engine in December 2009.

1.Worked with consultant (ORIENT POWER ENGINEERING) in erection, pre-commissioning and commissioning phases of JGS-420 Jenbacher Gas Engines.

2.Termination and Cable laying job of power and control cables according to design & drawing.

Erection of Heat Recovery System

Second Major erection work. Commissioning of Double Effect 260 Ton (2) Absorption chillers & (2) Heaters for HTM heating in January 2012.

1.Worked with consultant (ORIENT ENGINEERING) in erection, pre-commissioning and commissioning phases of double effect (2) absorption chillers.

2.Termination and Cable laying job of power and control cables according to design and drawing.

Erection of Heat Recovery System

Third Major erection work. Commissioning of Double Effect 400 Ton (1) Absorption chillers & (1) Heaters for HTM heating in April 2013.

1.These systems are design on Fatek PLC and also design Weintek HMI for operation and control of system.

2.Termination and Cable laying job of power and control cables according to design and drawing.

Erection of Coal Fire Oven

Fourth Major erection work. Commissioning of Coal Fire Oven / Heater 12000kw for HTM heating in January 2014.

1.Worked with consultant CEEF from china in erection, pre-commissioning and commissioning phases of 12000kw Coal Fire HTM Oven.

2.Termination and Cable laying job of power, control cables and instrumentation according to design and drawing.

Erection of JENBACHER JGS-320 Gas Engines

Fifth Major erection work. Commissioning of JGS-320. (2)Jenbacher Gas Engine in December 2014.

1.Worked with consultant (ORIENT POWER ENGINEERING) in erection, pre-commissioning and commissioning phases of JGS-320 Jenbacher Gas Engines.

2.Termination and Cable laying job of power and control cables according to design & drawing.

Erection of JENBACHER JGS-420 Used Gas Engines

Sixth Major erection work. Commissioning of JGS-420. (3)Jenbacher Used Gas Engine in December 2015 .

1.Worked with consultant (ORIENT POWER ENGINEERING) in erection, pre-commissioning and re-commissioning phases of JGS-420 Jenbacher Gas Engines.

2.Termination and Cable laying job of power and control cables according to design & drawing.

Erection of 600 (TON)SSP (Solid State Polymerization) Plant

Seventh Major erection work. Commissioning of 600 (TON) SSP PLANT in april 2016.

1.Worked with consultant (CPERION from Italy & CTIEI from China) in erection, pre-commissioning and commissioning phases of Plant.

2.Installation of power and control cable tray according to design & drawing.

3.Installation & placement of MCC,DISTRIBUTION panels.

4.Termination and Cable laying job of power and control cables according to design & drawing.

5.Instruments installation and cables laying for instruments and calibration with consultant engineers according to design & drawing.

Professional Qualification

1.Muhammad Ali Jinnah University,Karachi

Degree: MS in Electrical Engineering, 2021

Major sub: Robotics and Intelligent Control System

3.40 GPA.

2.Government College of Technology, Hyderabad

(Affiliated with Mehran University of Engineering and Technology)

Degree: B. Tech (Honrs), 2011

Technology: Electrical

3.15 GPA

3.Government College of Technology, Hyderabad

(Affiliated with Mehran University of Engineering and Technology)

Degree: B. Tech (Pass), 2007

Technology: Electrical

3.6 GPA

4.Government College of Technology, Hyderabad

(Affiliated with Sindh Board of Technical Education)

D. A. E. Electrical, 2002

1st Division

5.Technical Training Center, Latifabad Hyderabad

One Year Technical Training Certificate (Electrician), 2000

2nd Division

6.Skill development Council, Karachi

Auto Cad (2D & 3D), 2007

Academic Qualification

1.University of Sindh, Jamshoro

B. COM (Pass), 2004

2nd Division

2.B.I.S.E Hyderabad

HSC-II (Pre Engg :)

2nd Division

3.B.I.S.E Hyderabad

SSC-II (Gr: science)

1st Division

Personal. Father’s name: Muhammad Latif Khan

Caste: Pathan

Date of Birth: April 07, 1982

Sex: Male

CNIC No: 41304-2326007-1

Passport # QR4110072

Marital Status: Married

NTC Registration: PE.Tech/Electrical/00315



Contact this candidate