Career Goals:

I have 38 years of experience as a Project Field Engineer with a solid

Metallurgical engineering background. I have worked in the Middle East on world class projects all my life. Since I have migrated to the US recently, I would like to work in the US a Mechanical Field Project Engineer in areas that can benefit from experience in Process Piping, Oil Storage Tank (Fabrication/Maintenance / Repair), Hospital Equipment (Major Maintenance Work), Equipment (Fabrication/ Erection/Installation),Steel Structure Fabrication/Erection),Commissioning Plant (Sewerage Treatment Plant).

SKILLS & CAPABILITIES:

●Strong Negotiation and Communication skills.

●Quick Decision-making skills.

●Ability to Handle Multiple Tasks in High Pressure Environment.

●Goal Oriented Self Motivated and Committed to the Successful outcome of the Project.

CODES AND STANDARDS KNOWLEDGE:

●API-650

●API-653

PROFESSIONAL QUALIFICATION:

1982 N.E.D University of Engineering &Technology, Karachi.

B.E Metallurgy (1st Division)

PROFESSIONAL TRANING:

Fiber Glass Reinforced Time Settling Resin (RTR) Pipe Systems (Dammam KSA)

LECTURES:

I have delivered lectures on the following topics in below mentioned companies

1)ASIL (Allied Services Int. Ltd.) Karachi

2)Saudi ARAMCO (KSA)

a)Sewerage Treatment Plan

b)Erection / Installation / Process & Commissioning

3)DUTCO MACCONNEL DOWELL L.L.C (Dubai)

a)Metal Powder by Atomization Process

b)Preparation of Aluminum Powder through Atomization Process

PROFESSIONAL AWARDS:

*Pakistan Steel Mills Corporation.

*CPECC (China Petroleum Engineering Const. CORP. Intl.)

*KW&SB (Karachi Water & Sewerage Board)

*Ministry of Health (MOH) - Riyadh Medical Centre KSA

*SNC/ Lavalin (Saudi Aramco)

*SGS Gulf Ltd Industries services.

*Applus Velosi Pakistan (Pvt) Ltd.

PROFESSIONAL MEMBERSHIP:

Member of Pakistan Engineering Council (Registration No. Met/1167)

PROFESSIONAL EXPERIENCE:

Joint Engineering Services Pvt Ltd Project Manager Mar 2021 to June 2022

Project: Pakistan State Oil Keamari Terminals A,B,C & Oil Installation Area Keamari

Scope of Work: Rehabilitation of 15xnos of Bulk Storage Tanks & Replacement of 12’’& 8’’ dia Tanker Discharge Lines.

Job Responsibility:

●Project management includes execution of EPC project of rehabilitation of 15 nos. storage tanks & rehabilitation of 12’’dia 0.6km,8’dia 1.8km Tanker Discharge Lines at Keamari Terminals A,B,C & Oil pier 2,3 according to API 653 and API1104 respectively.

●Provide Technical support to PSO to ensure the integrity and reliability during the construction phase and pipeline connectivity to pace up with the Quality management system.

●Provide daily, on-site/in-field leadership, execution coordination of a multi-discipline team.

●Assisting & coordinating in Tender process, project costing, Purchase Orders (PO), BOQ, variation/change order requisition, Bill of material and estimation.

●Coordination with PSO head office Projects department and contractor for timely completion of technical projects and activities.

●Collaborate with project HSE leadership to develop appropriate Job Safety Analysis

●(JSA’s) for the mechanical activities.

A S Engineering Karachi Project Manager Jan 2020 Jan 2021

Client: F&B Terminal Keamari / Bulk Management Pvt.ltd Keamari/RCL Terminal Keamari & Karachi Grain Port Qasim

Project: Construction of Oil Storage Tanks & laying of associated pipe line.

Scope of Work:

Supervised the activities of new construction Tanks/repair of Tanks & laying of pipeline from Terminal to Jetty.

Petrochemical Engineering Consultant Asst. Manager QA/QC April 2019 Nov 2019

Client: PA Chem Global Pvt Ltd Lahore/ PPL.

Project:

Supervised the Inspection activities Performed for (Equipment's, Pumps & Ejectors) at Pathalic Anhydryde Plant in PAChem Global (Pvt.) Ltd.Lahore.

Supervised the Inspection activities of Well Head performed for " Adhi Field Compression Project" (Pakistan Petroleum Limited) in Gasco Yard Maymar, Karachi.

Etimaad Engineering PVT LTD. Project Manager Dec 2018 Mar 2019

Client: Byco Petroleum Pakistan.

Project:

Attending meeting as a Southern Project Manager on behalf of EPC- contractor with Clint for the following companies Projects for Shutdown

M/S Byco petroleum Pakistan

M/S Engro polymers & Chemicals

M/S Engro Daharki

Project:

Shutdown

Air Cooler / Hx / Towers / Vessels /Furnaces /Valves .

(Open, clean, repair and box-up). Painting – 6000 Sq meters (total 250 mic). Sand blasting – 3000 Sq meter. Scaffolding – 18000 rft. Relocation of Heavies End tank-110 meters. Relocation of pump with accessories 03-nos. Relocation filters with accessories 02-nos. Installations of fire hydrant 01-nos. Roof shade installations. Prepare pit. Teflon tiles use due to acid. Tie-ins total 14-nos.

Major Repair of Tank-PRL Korangi Project Manager Sept 2017 Feb, 2018

Project:

●Attending meeting weekly with Client regularly. To get approval with client by submitting Execution plan/Man power deployment / Method of Statement & HSC sample to prior work start etc.

●To execute work in such a way by completion of work in time without any losses. Scope: renewal of BP/AP Plates including Bitumen Pad/ renewal of shell course 03 nos /wind girder / Curb angle & Roof in all respect with quality of a work to save time.

Zishan Engineers (Pvt) Ltd Site Manager Mar,2017 Aug,2017

Client: Nashpa - OGDCL

Scope of Work: Execution of inspection LPG Recovery Plant.

Project:

●Attending regular meeting with Client & Contractor to settle down issues which affects the completion Project. To prepare Progress Project Report with special focus on up to date Project Status / delay & corrective action. Execution Supervision / Installation of above ground Storage Tank. Erection of Equipment / Power Generation Unit / Steel Structure Pipe Rack / Cable Tray. To supervise the proper Execution of Inspection according to approved Project Specification / ITP. Verification of Invoice of EPC Project.

Petrochemical Engineering Consultant Project Manager Nov 2016 Feb 2017

Client:Fatima Group(RCL Terminal – Oil Installation Area, Keamari)

Project:

●MIA – Mechanical integrity Assessment & NDT OF OIL STORAGE TANK.

●Tank preparation before Inspection (Mechanical Contractor).

●Exposed Projection Plate of each Tank.

●Cleaning / Scraping & Power Bush inside bottom Tank.

●Cutting Existing Coils & Sump Pipe Tank.

●Grinding Ohms, Clits & CST inside bottom Tank.

●Visual Inspection of Shell & Roof install Scaffolding stand inside Tank.

INSPECTION: (3rd Party)

M/s. Applus Velosi to carry out Inspection, as per Code API-653

●Visual Inspection

●UT Via Crawler

●UT thickness gauging

●MFL.

●VBT.

●DPT for Sump.

Petrochem Engineering Services. Sr. Mechanical Engr Jan 2016 May,2016

Client :Total Parco

.

Project: Preparation of Construction Schedule & Activities

Scope of Work:

●Preparation of technical and construction specifications of equipment and materials.

●Preparation of BOQs for tender documents (procurement / construction).

●Review and approval of vendor’s drawing

●Preparation of construction Schedule and supervise the construction activities.

Al-Bahr Al-Arabia (Sharjah UAE) Construction Manager Aug 2014 May 2015

Client: Arzoo International Terminal FAZ, Sharjah UAE.

Project:

EPC Project construction and commissioning of Petroleum storage facilities at Arzoo Intercalation Terminal FZE for Expansion of storage tanks, and Laying of Main Jetty Pipeline 03 no line each length 1500Mtr of dia 12”,8”,6” and product pipeline and fire water network.

Scope of Work:

●Ensure optimum of Maintenance / Projects activities at site location.

●Responsible to carrying out inspection and construction of Terminal equipment like Tanks (API-650), NDT testing for relevant codes as per API-650, Sand blasting and application of Painting, Vacuum box testing and checking as per standard code of API-650 .

●Responsible to check the performance of Welding / Hot work activities, routine maintenance of process equipment’s like Pipe lines and Mechanical structure etc.

●Responsible to check the bill quantities verified as per Purchased Order / physical inspection.

●To make sure the carried out the Project as per schedule.

●Prepare Quality Reports Dossier as per requirement of approved format.

Al-Rahim Trading Co Maintenance Manager Nov 2010 April 2013

Client: OIL INSTALLATION AREA KEAMARI KARACHI.

Project:

●Cold/ Hot Repair or Tanks as per Standard API -653.

●Monthly Preventive Maintenance Schedule of Tanks.

●Fabrication Roof Tank/ Travel Trolley for sand blasting purpose.

●Re-Routing of pipe line during discharging /loading for ocean vessel.

●Installation / Erection of Air link system / V.I Tank/ vaporizer of nitrogen system of Purging purpose.

Descon Engineering Ltd. Construction Manager Feb2010 Aug 2010

Client: BOSICOR OIL PAKISTAN LTD.

Project No: 1124

Scope of Work

●Fabrication of CS pipe / fitting spools / welding as per API standard.

●Sand blasting as per schedule 2.5.

●Erection of water tube boiler 6162 (BOPL).

●Rigging work of flash vessel tank / economizer / main stack / deaerators (HP and LP) and boiler block.

Achievement

●Peel test / Holiday test.

2. BHP Billiton Zamzama

Client :DADU SINDH

Project: No.1133

●During the execution of work on HDPE pipeline, supervise Butt Welding joints through fusion welding machines according to the weld-map.

Achievement:

Actual site situation 360 Nos. of Butt welding joints were found / performed on 1700 meter length.

Dutco9 McConnell Dowell (ME) QC Inspector Oct 2008 Jul 2009

Project: JEBLE ALI / TAWEELA – UAE

Scope of Work:

●Incoming Material Inspection for Aluminum Burs Bar.

●Inspection Fabrication Activities Stage Wise as per site Drawing/Specification.

●Check &verify all Documents.

●Fabrication of Aluminum Riser / Bottom ring etc.

●Welding copper TAG/ Aluminum with Carbon steel joints by MIG welding and at the zone of transition.

●Transition joint AL/CS focus by pyrometer to note temperature.

●DP test performed on transition joints.

At the time of alignment of equipment measurement in the Potron Cell according to the check list of the followings.

●Bottom Ring.

●Cathode Ring (Riser).

●Pot Shell.

●Super Structure.

●Regulates and overseas the compliance of work in accordance of SNC / LAVALIN Engineering procedure.

EASTERN TRADING AND CONTRACTING EST. ETE- GROUP Aug 2009- Jan 2010

Al Hasa Hofuf - Dammam KSA

Client Saudi Armco

Designation : RTR Inspector

Job Responsibility:

Implementation of piping layout and installation that would include Fiber glass reinforced Time Settling Resin (RTR) pipe / Steel pipe / PVC and UPVC pipe.

●Regulates and overseas the compliance of work in accordance with the requirement of ARAMCO Engineering P

●rocedures.

●Oversee the duties in the erection of steel structure for pipe support/cable tray support/crane scheduling/steel structure procurement. This responsibility would cover around 1000 tons of structural steel members.

Achievement:

●SEA Rehabilitation and upgrading of ARAMCO UTHMANIYAH WIPS.

●Project in line with KURAIS SOUTHERN WATER EXPANSION PROGRAM.

Osmani & Company Manager Co-Ordinator Feb 2006 Jul 2007

Client: KW & SB

Project:

Installation of Wind pump / R.O plant / Solar lights and incinerator. (Foreign Aided Project Development Wings KW&SB)

Achievement:

Upgrading of Water and Sewerage Treatment Plant.

Zahran Operation & Maintenance Co. Mechanical Engineer Aug 1999 Oct 2005

Client: MOH, (YAMAMAH HOSPITAL - K.S.A) Ministry of Health

Project:

Upgrading mechanical equipment like Elevator and Sewerage Treatment Plant.

Scope of Work:

●In charge of Mechanical workshop.

●To arrange preventive maintenance on weekly / fortnightly basis for the pumps / Elevators and Sewerage treatment Plant pumps / Screens / Incinerator / Kardex / Barriers etc.

●To arrange check-list/Preventive Maintenance Monthly/Quarterly for Cooling Tower/Water Circulation Pump/Air Handling Unit & Chiller.

●Approval of parts for Ministry of Health (MOH).

Achievement:

The most significant duty for my stay in this company that I was employed here for Six(6) years, and considering that these Hospital is consider as one of the biggest Hospital in Kingdom.

Marathon Construction Company (Pvt.) Ltd. Site Engineer Jan 1998 Jun1998

Client: Engro Chemicals Ltd, Dharki Sr Mechanical Engineer

Project:

●Erection / Insulation CO2 Compressor / Motors Coupling / Vessels and SS Pipelines.

China Petroleum Engg. Constr. Sr Mechanical Engineer Jan1995 Jan1998

Client: KW & SB Waste Water Treatment Plant cont. K2SAI.

Job Responsibility:

●Checking drawing and specifications. Estimations of quantities of Mechanical items to be utilize on Project, such as Ductile pipe / fitting / M.S Structure etc. Preparation shop drawing and getting approval from consultant.

●Installation of Serens / Pumps / dredger and associate equipment laying of D.I pipes (up to 100mm – 1200mm)

Achievement:

●Testing / Commissioning of Mechanical plants.

●During my tenure, I had the precious time of transacting from different position personnel, from client of contractors to international quality surveillance group SGS/Cotacna.

Pakistan Steel Mills Karachi Maintenance/ Executive Engineer Oct 1983 Nov 1992

Job Responsibility:

●I supervised the fabrication / machinery and welding of various parts, lining of reheating furnaces / convertor / tundishes and Ladles.

Dy. Production Manager / Assistant Executive

●I worked in PPC (Production Planning and Control Dept. I have acquired and great deal of experience and knowledge in production management Techniques and indenting material procedures.

●I had the experience of acquirement numerous management techniques in 9 years stay in this corporation and as a result of very dedication of the work, I was promoted as Executive Engineer / Managerial position.

Industech Asst. Engineer Jun 1982 Sep1983

Job Responsibilities:

●Inspection of material before fabrication.

●Inspection of fabrication activities as per drawing/project specification.

●Witness of hydro test & air blowing before install.

●As Production Engineer, I had the privilege several duties such as weekly production deadline / material procurement and Q/C handover.