Post Job Free

Resume

Sign in

Manager Project Oil Corporation

Location:
Kolkata, West Bengal, India
Posted:
August 28, 2022

Contact this candidate

Resume:

RESUME SUMMARY

Name: SAMIR BANERJEE Date of Birth : 1968-01-01

Mobile No: +91-798******* Functional Area : Project Execution(Piping) E .Mail ID:- adsb76@r.postjobfree.com Work Experience : 26 Years Qualification

Academic / Institute : Diploma (Mech)State Council) 1990 I.T EXPOSURE : MS office, Explore, Auto cad. Graduation / University : BE (Mechanical)NIET Delhi 1995 Extra Qualification : Certification On PMC. Detailed Resume

Professional Exposure: I have total 26 years of experience in Project execution,Out of that 13 years experience in Project Management to execute Job in smoothly manner and 4 years experience as a Lead Piping Engineer,To Co-ordinate with the Piping Design & Engineering Department and 9 year experience in Structural, piping fabrication and Mechanical work Like Static,Rotating Equipment, Procurement, Estimating, Hookup & Commissioning in the field of oil & Gas sector, Cross Country Piping, CGD Pipeline Projects & Refinery Job.

Also, I have strong communication & Team building skills, Overall responsibility for Execution & completion of the project within the stipulated time & budgeted cost

1. Org Name: Mideast Pipeline Product. D-913,New Friends Colony,New Delhi-110025 Post Held. RCM for India Bangladesh friendship HDD Pipeline project (25 Km for Seven River crossing) Duration: Join on 1st May 2022 5th August 2022.

2. Org Name: RESONANCE ENERGY PVT LTD.

Post Held. RCM as EPMC for MNGL/GAIL Project

Duration: 23/11/2018 to 30/04/2022

Project Handle :-

Executed for laying of 400km long CGD Pipeline(10”/6”/4”) 6.4 mm thickness 150/100 schedule networking system as per ASTM A106,API 5L 60/52 with 3 Layer External PE Coating In NASHIK at GA., Job involved for the Specification finalization, Work Procedure as per Engineering requirement as well as overall in-charge for construction activities

The job involved Erection of CNG Tank foundation, Pipeline Laying along with Fire fighting system & Modifications as per site requirements. Also involved anti corrosive Rapping & Coating,Pigging,flashing, Hydro testing, Nitrogen purging, TCP installation as well as Billing certification as per contractual requirements.

Executed for MDPE( 80/90,SDR 11)laying along with G1 3/4”,1”,2”) Pipe for interconnection and also installation of Service Regulator ( 25/50 SCMH – 4 Bar). Job involved Painting as per specification, Pressure testing and color coding.

3. Org Name: ESSAR PROJECT LTD. Through agency ( m/s Millicon ) Post Held. RCM as EPMC for LNG Bottling Plant (M/s IOCL) at Khargapur,West Bengal. Duration 06/06/2017 to 23/11/2018

Project Handle:-

Executed for laying of 160 km long CGD Pipeline networking system along with 120 TMTPA LPG bottling plant,involved in this project for finalizing the Specification & Engineering requirements and also Overall In charge for Construction activities like Land filling and Leveling,Boundary Wall & Approach Road,Tank Pad Construction also Equipment Erection.

Deputation for IOCL Panipat Refinery to Executed 30 days Shutdown Job at Hydrogen Unit, involved in this job for Modification of Piping, Pipe Rack, Deck extension, Nitrogen Purging, Hot Tapping, Loop Preparation and finally hand over the System within the Stipulated time as per Safety Norms. 4. Org Name: Nagarjuna Oil Corporation, Cuddalore at T.N. Post Held. Joined as Asst Manager & promoted As to Asst. General Manager (Project) Duration 7/06/2006 to 05/06/2017

Project Handle:-

Worked as AGM Project for Construction of Crude Distillation Unit (CUD)and also overall in charge for ISBL

& Off Site Piping during Refinery Construction Phase.

Executed the Ro-Ro jetty Construction for receiving the Oversize equipment, involve in managing Dredging, Breakwater also Off-Shore Jacket piping, Structural Walk Way for SPM as per HSE regulation.

To Lead the EPCM Piping department & Engineering Team as HOD ( Piping) for Preparing Piping Specification and MTO finalization during the Refinery Construction phase and also involved in Area Classification Drawing, Layout Concept and obtains input from other disciplines through “Want List” document.

Executed the entire Direct / Indirect workforce to complete the Refurbish, Revamping activities relating to Static Equipment & Piping Item Like Insulation removal, Retrieving of fitting & support from the Pipe Spool, Re-tooling of Flanges, internal Cleaning, Cross Thickness checking as per piping Specification. 5. Org Name: Reliance Petroleum Limited, Jamnagar

Post Held. Joined as Consultant and then Appointed as Dy Manager- Project. Duration 15/06/1998 to 15/05/2006

Project Handle:-

Worked as Consultant Engineer at Marine Tank Farm area & Off Site Piping as per ANSI / ASME B31.1 Like Carbon Steel 106 Gr.-B, A33 P11 & P22 from Construction to Commissioning during July 1998 to Jan 2000, involved in this project for Plan & Supervised all the Construction activity to ensure proper compliance with all Technical and safety aspect.

420 km 42"Gas pipeline Cross country Project with gas Compression Pumping & Metering facility 52M man-hours Shutdown Job :-

Worked as Dy. Manager Project for revamping the Crude Distillation of 28 days Shutdown Job during 2003, ensure to work permit system in the live area and also Tag/lock Out System.

Worked as Dy. Manager Project of Fluid catalyst Cracker Unit for Pre & Post Shutdown activities like Structural Rack Extension and Piping Net work system Laying in live Area for 32 days Shutdown job during 2005. 6. Org Name: Hindustan Construction Corporation, Mumbai Post Held. Manager- Project.

Duration From Nov 1997 to June 1998

Project Handle:-

Worked as Manager Project for laying 50 Km long Cross Country pipe line for LPG (SA 333 Gr. B )Gas distribution at Mumbai under The Mahanagar Gas LTD. Involved in this project erection, Modification & Material procurement as per site requirement. Also involved in anti corrosive rapping & coating (Out Side).

To co-ordinate all engineering & site activities during the project phase and also maintain of all operation record and compile reports which is submitted to Client’s representatives during monthly review meating. 7. Org Name: Duke Offshore Ltd. Mumbai

Post Held. Joined as Project Engineer & promoted to Dy. Manager Project . Duration From May 1995 to Nov 1997

Project Handle:-

Worked as Engineer for Annual Maintenance contract of all the fire fighting Sprinkler & Utility System of all the Unman platform under the South & North field Area at Bombay High of M/s ONGC.

Worked as Dy.Manager for Offshore Hook-up & Commissioning the Central Processing Platform at South Basin gas field Area at Bombay High & finally handover the project within the time,involved in this project Onshore Prefabrication and final Commissioning activity at Offshore in different type of materiel like Nace (C.S A-106 Gr- B) for Riser & S.S (ASTM-312) for permanent Well Fluid Flow Arms,Manifold installation,Flare installation & Deck extension,also involved for Nitrogen Purging,Gauging,Flooding,Pigging,Hydro-testing. Prime Duties:-

ENGINEERING:-

Monitor the issuance of engineering deliverable s,supervise the preparation of IFD's “Issued for Design” & IFC “Issue for Construction ” Documents encompassing the Support Standard Document & Plot Plan Isometrics drawing and other related documents.

Review the ITB (Invitation To Bid) documents submitted in the proposals stage, issue inquiry requisition, review techno- commercial vendor offers, prepare equipment, material, and man-hours estimates.

Review contract requirements for project execution, organize the preparation of the Technical Documents Register (TDR), identity requirements and scope of work, Review specification Process Data Sheet (PDS), Piping Material Specification

(PMS),Piping& Instrumentation Diagram(P & ID's),Plot Plans, General Arrangements (GA)Drawings,Review Philosophy. EXECUTION:-

Sequence wise listing the work and assign the job accordingly,also synchronizing the Construction activities for Commissioning the project within schedule & Make day-to day planning and preparing the periodical report forecasting the project trend to the management to ensure that they are aware of the site activities.

Verify and conceptualize the most optimum work route,identify a clear scope of work and quantify the total number of engineering deliverable s,Assign and distribute the manpower for the execution activities as per Projected Man- hours Chart.

Supervise all direct/indirect workforce and Co-ordinate all the activities of all the disciplines efficiently and in accordance with the construction requirement as per Quality and Cost standers.

To be aware of SHES details project concept & it communicated of all the supervisory staff,also ensure the Health & Safety requirements are adhered to of all time in accordance with laid down procedure and practically implemented as per schedule requirements.

Ensure that details interface between Engineering and Procurement deliverable s fit to a logical sequence that suit the commissioning and start- up requirements,Flange Management,Risk assessment and also resolved the contractual claims and finalize the accounts.

Date: 5th August 2022 ( SAMIR BANERJEE )



Contact this candidate