Profile 11.5 Years of experience (field / installation & project engineering along with project management) in offshore installation & inspection of the offshore platforms, submarine pipelines & cables, floating unit & subsea production system and other various subsea assets in the region of Arabian Sea, South East Asia and Persian Gulf.
Education 2010 – Sardar Vallabhbhai National Institute of Technology (NIT- Surat), India (MTech – Structural)
2008 – Andhra University (AU), India (BE - Civil) Qualifications
Master of Technology in Structural Engineering (CGPA – 7.61)
Bachelor of Civil Engineering (CGPA – 6.98)
Training/skills
Well versed experience with drafting software AutoCAD
Preliminary experience with design & analysis Software’s Staad–PRO & SACS
Microsoft Office Package
Languages spoken Native: Telugu & Hindi
Fluent: English
Work Experience
Dec 2019 – Dec 2021 Position – Project Manager (Subsea – ROV) Company – Fugro Peninsular Services Co. WLL
Location – Doha, Qatar.
Oct 2018 – Nov 2019 Position – Project Engineer (Subsea – Diving & ROV) Company – Fugro Survey (Middle East) Ltd.
Location – Abu Dhabi, UAE.
Oct 2014 – Sept 2018 Position – Project Methods Engineer / Sr. Field Engineer Company – Valentine Maritime Gulf LLC
Location – Abu Dhabi, UAE.
Apr 2013 – Sept 2014 Position – Project Engineer / Installation Engineer Company – Leighton Offshore Construction Pte. Ltd. Location – Singapore / Dubai UAE.
June 2010 – Mar 2013 Position – Field Engineer / Sr. Field Engineer Company – Swiber Offshore Construction Pte. Ltd.
Location – India / Singapore.
Fugro Peninsular Services Co. WLL
Project Manager
Responsible for managing offshore projects in Qatar for major Stakeholders such as Qatar Petroleum, Qatargas (North & South) Limited Company Ltd., Qatar Shell (QSGTL & QSSC) and North Oil Company along with EPC Contractors Saipem, Qcon & DOPET.
Coordination with other departments (Planning, Engineering, Operations, Commercial / Bidding / Estimation, Procurement, Subcontracts, QA/QC, and QHSSE). 2021 May – Client: Qatargas Limited Company Ltd. & Saipem 2021 December Project: EPCOL Pre-Engineering ROV Survey Vessel: Fugro Adventurer & Bourbon Enterprise
Client: Qatar Petroleum & DOPET
Project: Fast Rescue Craft, Boat Landings at NFA and Mooring Piles Installation at PS-3 Field.
JUB: Seafox Matsu (ROV Construction Support, Navigational and Surface / Subsea Positioning)
Client: North Oil Company
Project: AS-BD Geophysical & ROV Shallow Imaging Survey at Al-Shaheen Field.
Vessel: Bourbon Enterprise
Procedures (Operation Plan, Quality Plan, QHSE Plan, Emergency Response Plan, HIRA Document, Bridging Document, H2S Emergency Plan, Mobilization & Demonization Plan)
Mobilization, Offshore Support & Demobilization;
Invoicing;
Review of DPRs, Field reports & Final Data / Document Dossier Reports, Charts, Videos / Final Deliverables as per Contract. 2020 February –
2021 April
Client: Qatargas Limited Company Ltd., Qatar Shell (QSGTL)
& Qatar Shell (QSSC)
Project: ROV underwater Pipelines, Cables & Structures Inspection Projects; Navigational, Surface & Subsea Positioning, ROV and Sector Scan Support for Rig Moves & Vessels Mobilization, Offshore Support and Demobilization; Procedures; Invoicing; Review & Submission of DPRs, Field Reports, Final Data / Document Dossier Reports, Charts, Videos & Final Deliverables as per Contract. 2019 November – Client: Qatar Shell (QSGTL)
2020 January Project: ROV underwater Pipelines, Cables & Structures Inspection Vessel: FS-106 (Near Shore Boat) & DP2 Nor Spring
Mobilization, Offshore Support & Demobilization of the Vessel at RLIC, Hamad Port & FSME Jetty.
Procedures (Operations Plan, Quality Plan, QHSE Plan, ERP, HIRA, Bridging Document, H2S Emergency Plan & Mobilization
& Demobilization Plan) and review DPRs, Field & Final Reports. 2019 August –
2019 November
Client: Qatar Gas South / RasGas (Nearshore) & Qatar Gas South Structures / RasGas
Project: ROV underwater Pipelines, Cables & Structures Inspection (ROV Project)
Vessel: FS-106 (Nearshore Boat) & DP2 Nor Spring
Mobilization, Offshore Support & Demobilization of the Vessel at FSME / RSIC Jetty
Procedures (Operations Plan, Quality Plan, QHSE Plan, ERP, HIRA, Bridging Document, H2S Emergency Plan, Mobilization & Demonization Plan) and review DPRs, Field & Final Reports. 2019 August – Client: Qatar Gas North
2019 December Project: ROV underwater Pipelines & Cables Inspection
(ROV Project)
Vessel: DP2 Crest Argus 1
Mobilization, Offshore Support & Demobilization of the Vessel at FSME, RLIC & Hamad Jetty’s
Procedures (Operations Plan, Quality Plan, QHSE Plan, ERP, HIRA, Bridging Document, H2S Emergency Plan, Mobilization & Demonization Plan) and review DPRs, Field & Final Reports. Fugro Survey Middle East Ltd
Project Engineer
2019 July – 2019
September
Client: Qatar Engineering & Construction Company (QCon) / Qatargas Limited Company Ltd.
Project: Replacement of Subsea Compression & Shear Fenders of 4 x Boat landings & Install clamps for wooden Fenders
(Diving Project)
Vessel: DP2 Topaz Rayyan
Mobilization, Offshore Support & Demobilization of the Diving Spread at Mesaieed Qcon Jetty onboard DP2 Vessel
Procedures (Execution Plan, Method Statement, HIRA, Bridging Document, QHSE & ERP Plan)
Review of Field Reports, DPRs, Final reports, videos and other deliverables.
2019 March – Client: Dubai Petroleum Establishment – UAE & Technip FMC
2019 June Project: AQAM Development Project and Associated Pipelines
Vessel: DP2 DSV Lichtenstein
Subsea Smart / Hot Tapping into Live 10” GL
Pipeline
Subsea Smart Flange’s installation
Subsea Spools Installations
DBB Valve Protection Frame’s Installations
Sleeper Installations / Relocations
Free Span Corrections with Grout bags
Grouting Operations on AQA Jacket
Pre-commissioning Activities (FCGH,
dewatering & Nitrogen Purging) subsea to
subsea, riser top to subsea
Double Block & Bleed Valves cycling operations
at Subsea Tie-in locations
Existing Spools recovery
2018 October – Client: Dubai Petroleum Establishment – UAE & Technip FMC
2019 February Project: Rashid D Development Project and Associated Pipelines
Vessel: DP2 DSV Picasso
Subsea Rigid Risers & Clamps Installations on RA & RC Platforms
Subsea Spool’s Installations at RA, RC, RD & SST
(Subsea Tie-in) Locations
Sleeper Installations / Relocations
Free Span Corrections with Grout bags
Grouting Operations on RD Jacket
Pre-commissioning Activities (FCGH, dewatering & Nitrogen Purging) subsea to subsea, riser top to
subsea
Double Block & Bleed Valves cycling operations at Subsea Tie-in locations
Valentine Maritime Gulf LLC
Project Methods Engineer / Senior Field Engineer
2018 June – Project: Various Projects
2018 September
Technical tender preparation
(coordinate/prepare preliminary method
statements, technical clarifications, execution
plan, feasibility study, etc.)
Project as-built documentation compilation
Development of Detailed Installation procedures
development for Typical Offshore Installations
2018 February – Client: ONGCL / LTHE – India
2018 May Project: Daman Development Project Barge: DLB 1600
Installation of 5 No’s Sub-Sea Rigid Pipeline Segments (Sizes vary from 8” – 18” with total approx.. length 70 KM)
As-laid Survey
Client: ONGCL / LTHE – India
Project: BW Pipeline Replacement Project – IV (BWPRP-IV) Barge: DLB 1600
Installation of 2 No’s Sub-Sea Rigid Pipeline Segments (12”x 16 KM)
As-laid Survey
2017 March – Client: KNPC / KIPIC & HSS JV – Kuwait 2018 January Project: Al-Zour New Refinery Project (NRP)- Package 5 Barge: DLB 1600
Subsea Rigid Pipeline Installation
1 no. 10” x 18 km
4 nos. 30” x 18 km (2 nos. Piggyback with 2 nos. FOC each)
Shore pulling 1.5 km (All Pipelines)
Braces with Clamps Installation
Stalk-on Riser Installation (1 no. 10” & 4 nos. 30”)
Flange Riser Installation (1 no. 10” & 4 nos. 30”)
J-Tube Installation (2 nos. 10” J-Tubes for 4 nos. FOC’s)
Tie-in Spool Installation (1 no. 10” & 4 nos. 30”)
4 nos. FOC’s pulling though J-Tubes & termination
2 nos. Riser Protector Installation
As-laid Survey & Free Span Correction
FCG & Hydro-testing of all Pipelines & As-built Survey 2016 May –
2017 February
Client: ADOC (Japan) – UAE & Technicas Reunidas (TR) Project: HAIL Surface Facilities EPS Project
Barge: Regina 250
Subsea Rigid Pipeline Installation between Mubarraz & Hail Islands (6”, 8” & 18” x 9.5 km /each)
Shore pulling 1.5 km at Hail Island
Shore pulling 0.8 km at Mubarraz Island
Normal lay till mid-line tie-in location (from both islands)
Surface / Mid-line Tie-in of all the Pipelines
4” Composite Cable lay x 9.5 km with DP-2 DSV
Concrete / Pipeline Stabilization Mattress Installation Cable Stabilization Blocks, Free Span Correction & Buckle Mitigation Sleepers
Cable Stabilization Blocks, Free Span Correction & Buckle Mitigation Sleepers
Pre-commissioning Activities & As-built Survey
Client: ADMA & Petrofac
Project: SARB-3 Project
Approx. 200 KM Pipeline Segments
(12” – 48”)
2014 October –
2016 April
Client: ONGCL – India
Project: MHNRD-III PLP
Barges: Regina 250 & Kruez Supporter
Vessels: DP2 DSV Kreuz Installer & DP2 DSV Seamec 2
Installation of 19 No’s Sub-Sea Rigid Pipeline Segments
(Sizes from 6” – 20”) of total approx... length 170 KM
Umbilical Piggyback with 20” P/L and SSIV installation (Welded to 20” P/L while laying)
Laterals & Piggable Wye with Protection Cages Installation
Riser Protector’s & Boat Landing Installations
PLEM (Pile Driven) Installation
Riser’s, Sump Caisson & Fire Water Pump Demolition
Risers & Spools Installation
Free Span Correction & Crossings
Pre-commissioning Activities (FCG Dewatering &
Nitrogen Purging)
Leighton Offshore Construction Pte. Ltd
Project Engineer/ Installation Engineer
2013 October – Client: South Oil Company - Iraq
2014 September Project: Sealine Project (Phase-3)
Barge: DLB 1600; Vessel: DP2 HLV / DLV Oceanic 5000 Installation of:
Valve Station-1 (VS-1) Jacket & Boat Landing
Valve Station-1 (VS-1) Topside (Single Lift - MSF Deck, Module 1, Module 2, Module 3) 3250 MT
Valve Station-2 (VS-2) Substructure
Valve Station-2 (VS-2) Topside & VS-2 Boat landing
VS-1 to existing LQ Bridge Support Sub-Structure
VS-1 to existing LQ Bridge Support Topside
VS-1 to existing LQ Bridge
VS-2 to existing KAOOT Bridge
2013 April –
2013 September
Client: Shell Eastern Pte Ltd – Singapore
Project: Shell Bukom 48” Pipeline Repair Project
Barge: Leighton PLB Stealth
Vessel: DP2 DSV Altus Exertus
De-oiling of Existing SPM, PLEM, Hoses and 48” Pipeline (5.2 KM)
Removal & Transportation of Existing SPM, Old PLEM and Hoses
Removal of 50mtr of Existing pipeline for Midline Tie-in with New Pipeline Segment
Inspection of Existing Mooring Chains (in-situ)
Installation of new 48” pipeline (2.7 KM), FCG and Hydro testing
Installation of concrete mattress
Install Midline tie-in spool,
New PLEM (Gravity based) and tie-in spool with P/L
Re-installation of refurbished SBM, Subsea and Floating Hoses & Final leak test of SBM
Removal of Existing 2.7 KM 48” pipeline (Using DWCM) 2011 October –
2012 March
2012 April –
2013 March
Client: ONGCL – India
Project: B193 SS & PP PLP
Barge: Swiber PLB Concorde & Swiber PLB Conquest
Installation of 7 No’s Sub-Sea Rigid Pipeline Segments (Sizes from 12” – 24”) of total approx... length 90 KM with Rigid P/L (2” & 3”) Piggyback Pipelines
Riser Protector’s Installation
Client: ONGCL
Project: Cluster-7 PLP
Barge: Swiber DLB 1MAS 300
Installation of 16 No’s Sub-Sea Rigid Pipeline Segments (Sizes from 4” – 20”) of total approx... length 140 KM
Riser Protector’s Installation
PLEM (Pile Driven) Installation
Client: ONGCL & ESSAR - India
Project: D1 Development Project
Barge: Swiber DLB PJW 3000 & DP2 HLV Magnificent
Installation of D1-B Jacket & Topside
Installation of D1-C Jacket & Topside
Installation of D1-D Jacket & Topside
Installation of D1-B – Existing D1 Bridge
Installation of associated Riser Protectors & Boatlanding’s 2010 June –
2011 September
Client ONGCL - India
Project: MHNRD-II Project
Barge: PLB Swiber Conquest
Installation of 14 No’s Sub-Sea Rigid Pipeline Segments (Sizes from 6” – 16”) of total approx... length 75 KM
Client: Cairn Energy & ONGCL – India
Project: North Tapti Project
Barge: Accommodation Work Barge Swiber Victorious
Installation of 6 No’s 18” Stalk-On Risers with Pile Supports
Removal and Re-Installation of Riser Protectors
References
Paul Elliott (Senior Project Manager, Fugro);
*.*******@*****.***
Mark Impey (QHSSE Manager, Fugro);
*.*****@*****.***
Hemant Patil (Project Manager, Fugro);
*.*****@*****.***
Ghassan Joudeh (Senior Project Manager, Jacobs); *********@*****.***
Resham Lal (Senior Construction Manager, Subsea7); *********@*****.**.**
Ramesh Polnaya (Offshore CSR, ADNOC);
************@*****.**.**
A V Ramana Rao (Senior Project Manager, NPCC);
***********@*****.***
Vijay Verma (Senior Project Engineer, Technip FMC); ***********@*****.***