CURRICULUM VITAE
P.UTCHIMAHALI LAKSHMANAN
adpyog@r.postjobfree.com
Mobile : 950*******
Permanent Address
Tuticorin .
Tamil Nadu.
Pin Code – 628002.
Personal Data
Date of Birth : 30.09.1990
Sex : Male
Nationality : Indian
Marital Status : Married
Languages Known :
English, Tamil
Passport Details
Passport Number –
M1312603
Date of Issue- 19.08.2014
Date of Expiry- 18.08.2024
Objective
To work in a challenging environment in which my abilities can be fully utilized by the concern.
Personal Skills
Willing to learn, Ability to scope and work with people in groups, Friendly behavior.
Education
Diploma in Mechanical Engineering (Full Time) (Batch 2010) 69.29% (First Class with Distinction). samuel Polytechnic College, Tuticorin.
12th Standard (Batch 2008) 46.9 % S.A.V. higher
secondary School,Tuticorin
10th Standard (Batch 2006) 64 % S.A.V. higher
secondary School,Tuticorin.
Work Experiences : 9 Years
■ SITE 1
WARTSILA INDIA LTD 2x80 MW (VARIETYSERVICES)-
SESA STERLITE THERMALPOWER PLANT,
TUTICORIN
Period : May 2012 to Aug 2015
Department : Operation
Designation : Turbine Operator
■ SITE 2
M/S IND-BHARATH THERMAL POWER PLANT
3x63 MW TUTICORIN
C/O OEG INDIA PVT LTD
Period : Aug 2015 to Oct 2017
Department : Operation
Designation : Turbine Operator
■ SITE 3
M/S ABI TECHNO CHEM PVT LTD
TUTICORIN
Period : Oct 2017 to March 2018
Department : Operation
Designation : Boiler & Kiln Operator
■ SITE 4
M/S POWER SOURCE PHILIPINES ENERGY INC
1x20 MW
Barangay,kiwalan,Iligan city,Philipines
C/O POWER SOURCE OEG SERVICES INC
Period : March 2018 to June 2019
Department : Operation
Designation : Turbine Operator
■ SITE 5
M/S V V TITANIUM PIGMENTS PVT LTD
1x4.5 MW
C/O OEG INDIA PVT LTD
Period : Aug 2019 to Till date
Department : Operation
Designation : Turbine Dcs Operator
Involved in the vaious instrumentation scope of work. Attending routine Operation, Break-down & Shut-down maintenance of in all site. VV TITANIUM PIGMENTS PVT LTD
Plant Details:
Capacity Of Plant : 4.5MW (1 4.5) Thermal Power Plant Boiler Details:
Make Cheema boiler
Type of Boiler : AFBC
Capacity of Boiler : 60 TPH (63 kg/cm2)
Turbine Details:
Make : Triveni Industrial Engg,
Type of Turbine : Bleedcum,Extractioncum and condensating POWER SOURCE PHILIPINES ENERGY INC
Barangay,kiwalan,Iligan city,Philipines
Plant Details:
Capacity Of Plant : 25 MW Thermal Power Plant
Boiler Details:
Make WUXI HUAGUANG
Type of Boiler : CFBC
Capacity of Boiler : 110 TPH (117 kg/cm2)
Turbine Details:
Make : GUANGZHOU SKODA
Type of Turbine : 2HP, Deareator and 2LP
ABI TECHNO CHEM PVT LTD, TUTICORIN
Boiler Details:
Make THERMAX
Type of Boiler : WHBoiler
Capacity of Boiler : 3 TPH (10.5 kg/cm2)
:
:
IND-BHARATH THERMALPOWER PLANT, TUTICORIN
lant Details:
Capacity Of Plant : 63MW (3x63) Thermal Power Plant Boiler Details:
Make HANGZHOU
Type of Boiler : CFBC
Capacity of Boiler : 250 TPH (95 kg/cm2)
Turbine Details:
Make : HANGZHOU
Type of Turbine : 2HP, Deareator and 2LP
SESA STERLITE THERMALPOWER PLANT, TUTICORIN
Plant Details:
Capacity Of Plant : 80 MW (2x80) Thermal Power Plant Boiler Details:
Make BHEL
Type of Boiler : PULVERIZED
Capacity of Boiler : 320 TPH (95 kg/cm2)
Turbine Details:
Make : BHEL
Type of Turbine : 2HP, Deareator and 2 LP
RESPONSIBLITIES
The responsibility of operating the boiler, turbine, System in a day to basis and on a shift basis which includes safe start up and shutdown of plant.
Shift process review and manual event logging
Monitoring schedules and co-operation with maintenance department for day-to-day maintenance.
:
:
Follow up and implementation of safety shutdown of individual equipments on a planned basis and issuing of safety permit to work
Reporting any variance in the process parameters to the respective department and analyze the cause
Reasoning and implementing corrective measures if any Declaration
I hereby declare that all the information mentioned above is true to the best of my knowledge.