Post Job Free

Resume

Sign in

Electrical Engineer

Location:
MG Road Area, Puducherry, India
Posted:
January 18, 2022

Contact this candidate

Resume:

MURUGAN THILLAI JAYARAMAN

Mobile:

=+919****-***** / +919****-*****

adpycb@r.postjobfree.com

Position Applied : SENIOR ELECTRICAL ENGINEER

Availability : One Month

Date of Birth : 30th JULY1968

Nationality : Indian

Languages : English

PROFILE

Have more than Twenty PLUS (20+) years of Oil& Gas experience(14 YRS) these includes Construction & Commissioning /START UP Experience in executing are supervising work in India and Overseas in all aspects of Electrical & Instrument related to Onshore/ Offshore Oil and Gas Industries and Ship conversion industry (Marine). Have extensive experience in Erection, Installation, Pre-commissioning, Commissioning, Start-up and Operations of Gas and Oil processing platforms, Petrochemical export refinery,, FPSO, FSRU and Bulk carrier vessels and GTL (Gas to LIQUID PROJECT)

Have worked on HV – 33KV/11KV/6.6KV/3.3KV also worked on Electrical Distribution and installations /pre-commissioning with HT/LT transformer

Have worked as Construction/ Commissioning /Start up (E&I ) including of Maintenance

Have worked for Client & EPC Companies SAUDI ARAMCO /PETROBRAS Brazil, Sonangal- Angola, ENI services Italy, Saipem - Italy/Dubai, SHELL Qatar

Worked for morethan 14 years on offshore projects and onshore projects

QUALIFICATIONS

1991 Bachelor of Engineering (Electrical-&Electronic Engineering)

Computer Skills: Ms Word, Excel, Spreadsheet, Outlook Express, Internet, AutoCAD, Adobe

TRAININGS

Basic Sea survival coarse approved by OPITO –Abu Dhabi including Huet, Fire fighting, EBS & H2S –

SAUDI ARAMCO WORK PERMIT HOLDER

WORK EXPERIENCE

March 2014 to Till date Lead Electrical Engineer

Project : Al Wasit Project Hasbha & Arabiyah onshore & offshore facility – Saudi Arabia

Client : Saudi Aramco (Wasit Gas program)

Offshore : more than one year (Marjan and Hasbha / Arabiyah offshore )

Involving complete hook up activities of all the Hasbha and Arabiyah offshore well head platforms electrical activities including

cathodic protection

24 Volts batteries charger

13.8 Kv submarine umbilical composite cable installations and splicing

Involving and co-ordination of pre-comm activities

Complete earthing activities

Well head platforms lightings and helideck lightings

Get along with engineering for design issues to solve the problems arriving at site.

Participating in the preparation of all offshore commissioning activities related to the Electrical discipline in cooperation with sub - contractors and vendors.

Ensuring necessary HSE reviews are undertaken and identified actions completed. Monitor lockout & tag out procedure was followed by appointing trained personnel in the switchgear.

Coordinating and supervising the team executing the discipline work activities and assisting with relevant technical support as required, including mentoring

The commissioning and start-up test was performed in the presence of Contractor Representative and Vendors.

April 2012 to Dec 2013 Lead Electrical Engineer

Project : FSRU LNG Project (Dubai Dry-docks & Italy offshore)

Client : Offshore LNG Toscana- Italy

Offshore : Six Months

Supervise during the electrical discipline aspects of mechanical completion, commissioning & startup activities of HV/LV distribution (6.6Kv/460V), which includes HV/LV switchgears/MCC, HT/LT Transformer, AC/DC UPS, Navigation Aids, Lighting, VFD & process systems.

Commissioning power generations systems like 6.6 KV Steam generators/ 6.6 KV Diesel gensets using inductive and resistance combination load bank.

Get along with engineering for design issues to solve the problems arriving at site.

Participating in the preparation of all offshore commissioning activities related to the Electrical discipline in cooperation with contractors and vendors. This includes preparation of commissioning procedures & OTP; Check & Record sheets and detailed commissioning schedules.

Ensuring necessary HSE reviews are undertaken and identified actions completed. Monitor lockout & tag out procedure was followed by appointing trained personnel in the switchgear.

Coordinating and supervising the team executing the discipline work activities and assisting with relevant technical support as required, including mentoring and on the job training of junior personnel.

Participating in daily & weekly meetings within the commissioning team & preparing weekly status report to the nominated commissioning system engineers and to resolve any shortcomings.

Supervises commissioning services contractor’s personnel and vendors representatives.

Ensuring that relevant documentation is prepared and made ready for system hand over thereby checking the check sheets and record sheets to Production & Maintenance organization.

Contributing to Commissioning support for Start-up using the WINPCS methodology.

Participating in and assisting with the co-ordination of the Project’s performance test(s).

Ensuring that any outstanding actions for system hand over to commissioning are duly recorded and are effectively cleared as per the technical requirements.

Liaise with Contractors and Consultants to clear the punches issued during construction, commissioning and start up as per the standards and handover to operation team.

Commissioning and Start-Up activities:

-preparing the PTW according with Dubai Dry Dock requirements and rules

-preparing the Temporary LV Power Supply

Three Diesel Generators synchronized, parallel connection (two DG live, one DG in stand-by) connected to Main MV bus bar.

-preparing the daily technical and HSE meeting according with the planned activities

-preparing the necessary design documents (drawings, layout, electrical interconnection, data sheet)

-preparing the Test Sheets and OTP’s performing for followings equipment and systems:

1.

6.6 KV HV distribution boards including protection relay setting (AREVA . ABB VD4 breakers with primary and secondary injection).

Bus bar HV insulation tests (5 kV Megger), continuity and contacts quality (Low Resistance Ohmmeter / Ductor, torque value)

Secondary DC circuits test for each cabinet and energizing

Secondary injection for relays settings (Omicron Injection kit)

Primary injection for differential protection testing

Automatic Transfer Source (ATS) logic test

Testing of Intertrip / Interlock logical

DCS communication test (alarms, status)

2 LV distribution boards including protection relay setting (AREVA P127, P141, with primary and secondary injection).

Bus bar LV insulation tests (1 kV Megger), continuity and contacts quality (Low Resistance Ohmmeter / Ductor, torque value)

Secondary DC circuits test for each cabinet and energizing

Secondary injection for relays settings (Omicron Injection kit)

Energizing the LV Distribution Board from Temporary LV Power supply (2x1250 kVA Diesel Generators)

Automatic Transfer Source (ATS) logic test

Testing of Intertrip / Interlock logical

DCS communication test (alarms, status)

3 LV Variable Speed Drivers (VSD Schneider)

Crane Motor and Air Compressor Main Motor

4 Dual UPS systems (2x 120kVA; Chloride)

Battery bank load test (charging / discharging using load bank)

By-pass working test

Power transfer for maintenance test

DCS communication test (alarms, status)

5Emergency Diesel Generator

Power quality test (Voltage, current, frequency, harmonics)

Endurance test on the load banks

Starting dual battery bank tests

Auto / Man Synchronization with the main power

Power sheering test

Automatic Transfer Source (ATS) logic test

DCS communication test (alarms, status)

6Emergency LV Distribution Board

Bus bar insulation tests (1 kV Megger), continuity and contacts quality (Low Resistance Ohmmeter / Ductor, torque value)

Secondary DC circuits test for each cabinet and energizing

Secondary injection for relays settings (Omicron Injection kit)

Energizing the LV Distribution Board from Main Distribution board

Automatic Transfer Source (ATS) logic test with EDG

Testing of Intertrip / Interlock logical

DCS communication test (alarms, status)

7Dual Battery rectifier (110V DC; Chloride)

Battery bank load test (charging / discharging using load bank)

Power transfer for maintenance test

DCS communication test (alarms, status)

8MCC panels

Protection relays settings using secondary injection kit according with the design for motors, coolers, pumps

DCS communication test (alarms, status)

Phase rotation test (on the panels and field)

Power cables insulation, continuity, drop voltage tests

Motors vibration and temperature measurements

9Normal and emergency lighting

LV cables testing (insulation, continuity, connections)

Lighting fixtures checking

JB sealing and connection checking

Energisation and light level measurements

10Lightning and grounding

continuity and contacts quality (Low Resistance Ohmmeter / Ductor, torque value

11Trace heating system

LV Distribution Panel checking (leakage current protection test)

Insulation test

Energisation and temperature control checking

DCS communication test (alarms, status)

126 x 2 MVA transformers 6.6 kV / 460 V

Primary and secondary winding insulation test

Primary and secondary winding continuity and resistance

Marshaling box checking (oil temperature, oil level, gas pressure)

Oil breakdown voltage test (laboratory test)

Transformer ratio check

Energisation from Temporary Power Supply and OTP performing

13HV Motors

HV Power cables insulation, continuity,

Protection Areva relay setting

Phase rotation test (on the panels and field)

Motors vibration and temperature measurements

DCS communication test (alarms, status, control)

14DG Load Testing

Steam Turbine Generators 6.6 KV, 10 MW performance load test using load bank

Main Diesel Generator 6.6 KV, 3,3 MW performance load test using load bank

Steam Turbine Generators 6.6 KV, 3.3 MW performance load test using load bank

Load test with step of 25%,50%,75%,100% & 110%

Load rejection test from 100% to 50%to 0%

Load rejection test from 100% to 0%

Syncho Checks using load bank for two more generators

15PMS Test

Remote Synchronization between the two or more generators

Load Sharing test

Load Shedding test

Preferential shedding test

DG Auto start for back up test

Remote start and stop MV Motors

Remote start and stop LV Motors

Remote Open/close the MV breakers

Remote Open/close the LV breakers

Monitoring Active and reactive power

Earth fault monitoring of MV switch boards

Earth fault monitoring of LV switch boards

Monitoring UPS Systems

Monitoring of Nav Aids systems

The commissioning and start-up test was performed in the presence of Contractor Representative and Vendors.

Mar 2011 to Nov 2011 Senior Electrical Engineer

Project : FPSO AQUILA -II (Dubai Dry-docks & Italy offshore)

Client : ENI Services - Italy

Offshore : Four Months

Supervise/Perform the electrical discipline aspects of all installation, inspections, mechanical completion, commissioning & startup activities of HV/LV Power generation (11kV/460V) & distribution, and Offshore Oil & Gas Production at offshore Italy

Conversion done at Dubai Dry Dock

Ensuring all Electrical/Instrumentation work packs (mechanical completion Check sheets) and pre-commissioning/commissioning documentation & dossier is available from contractor in accordance with progress requirements.

Allocation of tasks for all the Electrical Engineers in reviewing and completion of the punch list items prior to the Pre-commissioning and Commissioning activities.

Coordinate with WinPCS team during the preparation of pre-commissioning & commissioning check sheets & record sheets.

Manage the commissioning activities of the electrical discipline as per the project schedule and execute the activities successfully.

Liaise with Contractors and Consultants during the commissioning of HV/LV switch gear & transformer, UPS, lighting, power distribution, F&G, PA/GA, alarm monitoring and grounding systems.

Participating in daily & weekly meetings within the commissioning team & preparing weekly status report to the nominated commissioning system engineers.

Ensuring that relevant documentation is prepared and made ready for system hand over to Production & Maintenance organization.

Perform tests for HV Switchgear, transformer, LV switchgear, UPS according to SMC methodology.

Developing the Nationals by sharing the practical Experiences and knowledge, involving nationals in critical jobs by proving the required trainings.

Monitor the Isolation/ De-isolation of switchgears with lockout & tag out procedure.

The electrical Commissioning activities:

-preparing the Temporary LV Power Supply

Two Diesel Generators, parallel connection ( one DG live, one DG in stand-by) connected to Main MV bus bar.

-preparing the daily technical and HSE meeting according with the planned activities

-preparing the necessary design documents (drawings, layout, electrical interconnection, data sheet)

- preparing the Test Sheets and OTP’s performing for followings equipment and systems:

1.HV Switchgear (IMESA -ITALY)

Bus bar HV insulation tests (5 kV Megger), continuity and contacts quality (Low Resistance Ohmmeter / Ductor, torque value)

Secondary DC circuits test for each cabinet and energizing

Secondary injection for relays settings (Megger Injection kit)

Testing of Intertrip / Interlock logical

DCS communication test (alarms, status)

2.HV / LV transformer

Primary and secondary winding insulation test

Primary and secondary winding continuity and resistance

Marshaling box checking (oil temperature, oil level, gas pressure)

Transformer ratio check

3.LV Switchgear (IMESA -ITALY)

Bus bar insulation tests (1 kV Megger), continuity and contacts quality (Low Resistance Ohmmeter / Ductor, torque value)

Secondary DC circuits test for each cabinet and energizing

Secondary injection for relays settings (Megger Injection kit)

Energizing the LV Distribution Board from Temporary Power Supply

Testing of Intertrip / Interlock logical

DCS communication test (alarms, status)

4.Lighting Transformer (dry type)

Primary and secondary winding insulation test

Primary and secondary winding continuity and resistance

Transformer ratio check

5.MCC testing and relay setting (Areva secondary injection)

Protection relays settings using secondary injection kit according with the design for motors, coolers, pumps

DCS communication test (alarms, status)

Phase rotation test (on the panels and field)

Power cables insulation, continuity, drop voltage tests

Motors vibration and temperature measurements

6. DC Charger for Emergency Lighting (Chloride)

Battery bank load test (charging / discharging using load bank)

DCS communication test (alarms, status)

7.UPS systems (120 kVA; CEG/ITALY)

Battery bank load test (charging / discharging using load bank)

By-pass working test

Power transfer for maintenance test

DCS communication test (alarms, status)

8.Normal Lighting Distribution Board and System

LV cables testing (insulation, continuity, connections)

Lighting fixtures checking

JB sealing and connection checking

Energisation and light level measurements

9.Emergency Lighting Distribution Board and System

LV cables testing (insulation, continuity, connections)

Lighting fixtures checking

JB sealing and connection checking

Energisation and light level measurements

10.Heat Tracing Distribution board and System

LV Distribution Panel checking (leakage current protection test)

Insulation test

Energisation and temperature control checking

DCS communication test (alarms, status)

11.Navigation System (SICE-ITALY)

Battery bank load test (charging / discharging using load bank)

Lighting fixture checking

Beacon radar checking

12.Lightning and grounding installation

continuity and contacts quality (Low Resistance Ohmmeter / Ductor, torque

13DG Load Testing

Steam Turbine Generators 6.6 KV, 10 MW performance load test using load bank

Two Main Diesel Generator 460 V, 1 MW performance load test using load bank

Load test with step of 25%,50%,75%,100% & 110%

Load rejection test from 100% to 50%to 0%

Load rejection test from 100% to 0%

14Syncho Checks using load bank for two more generators

The commissioning and start-up test was performed in the presence of Contractor Representative and Vendors.

Jan 2010 to Dec 2010 Shell GTL Projects – QATAR

Senior Electrical Engineer

Projects: GTL PROJECTS (Gas to Liquid)

Client : Shell – Qatar –Raslafan city –Qatar

Supervise during the electrical discipline aspects of mechanical completion, commissioning & startup activities of HV/LV distribution (33KV/ 6.6Kv/680V), which includes HV/LV switchgears/MCC, HT/LT Transformer, AC/DC UPS, Navigation Aids, Lighting, VFD & process systems.

Get along with engineering for design issues to solve the problems arriving at site.

Participating in the preparation of all offshore commissioning activities related to the Electrical discipline in cooperation with contractors and vendors. This includes preparation of commissioning procedures & OTP; Check & Record sheets and detailed commissioning schedules.

Ensuring necessary HSE reviews are undertaken and identified actions completed. Monitor lockout & tag out procedure was followed by appointing trained personnel in the switchgear.

Coordinating and supervising the team executing the discipline work activities and assisting with relevant technical support as required, including mentoring and on the job training of junior personnel.

Participating in daily & weekly meetings within the commissioning team & preparing weekly status report to the nominated commissioning system engineers and to resolve any shortcomings.

Supervises commissioning services contractor’s personnel and vendors representatives.

Ensuring that relevant documentation is prepared and made ready for system hand over thereby checking the check sheets and record sheets to Production & Maintenance organization.

Contributing to Commissioning support for Start-up using the WINPCS methodology.

Participating in and assisting with the co-ordination of the Project’s performance test(s).

Ensuring that any outstanding actions for system hand over to commissioning are duly recorded and are effectively cleared as per the technical requirements.

Liaise with Contractors and Consultants to clear the punches issued during construction, commissioning and start up as per the standards and handover to operation team.

standards and handover to operation team..

Jan 2008 to Dec 2009 Electrical Engineer

Project : FPSO GIMBOA (Dubai Dry-docks & Angola offshore)

Client : Sonangal- Angola

Offshore : Seven Months

Carry out Installation, Erection, Testing & Commissioning of Electrical & instrument systems and equipment.

Carry out execution of electrical commissioning activities on the LV/MV MCC/SWGR Power Management System and related equipment viz. (Protective relays)

Perform preventive maintenance activities on electrical systems involved in rig (offshore).

Attend break downs/system malfunctioning of 690 Volt Power generation & distribution (480/230/110v), Switch gears/MCC's, VFD's, drilling equipments includes National Oil well Mud pumps, Draworks & Top drive, HVAC and Utility systems.

Prepare Job Safety Analysis and adhere of electrical safety rules.

Supervise the assistant electricians for new installations onboard

Do inspection for third party equipments. Hookup cables and other electrical related issues of Client and report to Maintenance Supervisor/OIM

Sourcing of critical spares required for normal operation

Update AMOS system (PMS) and work accordingly.

Commissioning power generations systems like 6.6 KV Steam generators/ 6.6 KV Diesel gensets using inductive and resistance combination load bank.

16 x 2 MVA transformers 6.6 kV / 460 V

Primary and secondary winding insulation test

Primary and secondary winding continuity and resistance

Marshaling box checking (oil temperature, oil level, gas pressure)

Oil breakdown voltage test (laboratory test)

Transformer ratio check

Energisation from Temporary Power Supply and OTP performing

2 HV Motors

HV Power cables insulation, continuity,

Protection Areva relay setting

Phase rotation test (on the panels and field)

Motors vibration and temperature measurements

DCS communication test (alarms, status, control)

3DG Load Testing

Steam Turbine Generators 6.6 KV, 10 MW performance load test using load bank

Emergency Diesel Generator 460V, 450 KW performance load test using load bank

Load test with step of 25%,50%,75%,100% & 110%

Load rejection test from 100% to 50%to 0%

Load rejection test from 100% to 0%

Syncho Checks using load bank for two more generators

4PMS Test

Remote Synchronization between the two or more generators

Load Sharing test

Load Shedding test

Preferential shedding test

DG Auto start for back up test

Remote start and stop MV Motors

Remote start and stop LV Motors

Remote Open/close the MV breakers

Remote Open/close the LV breakers

Monitoring Active and reactive power

Earth fault monitoring of MV switch boards

Earth fault monitoring of LV switch boards

Monitoring UPS Systems

Monitoring of Nav Aids systems

The commissioning and start-up test was performed in the presence of Contractor Representative and Vendors.

Oct 2006 to Nov 2007 Electrical Engineer

Project : FPSO VITORIA-II (Dubai Dry-docks &Brazil offshore)

Client : Petrobras-Brazil

Offshore : 12 Months

Review of ITP and Commissioning test procedures and apply for electrical systems.

Ensuring that any outstanding actions for system hand over to commissioning are duly recorded and are effectively cleared as per the technical requirements.

Coordinate witness and perform trial run tests of Marine during construction of Cargo vessels at shipyard.

Start up and energization of generators, transformers and several motor control centers.

Perform hipot test for HV switchgears and verify the protection device parameters of starter.

Provide inspection status, defect list status, trial and progress status to all concerned.

Involved in Inspection and pre-commissioning of: Power Generation and Distribution systems; HVAC systems, UPS & Lighting systems; Fire/Gas system, Public Address system; & ESD and Utility systems.

Commissioning power generations systems like 11 KV Steam generators/ 11 KV Diesel gensets using inductive and resistance combination load bank.

1.

11 KV HV distribution boards including protection relay setting (AREVA . ABB VD4 breakers with primary and secondary injection).

Bus bar HV insulation tests (5 kV Megger), continuity and contacts quality (Low Resistance Ohmmeter / Ductor, torque value)

Secondary DC circuits test for each cabinet and energizing

Secondary injection for relays settings (Omicron Injection kit)

Primary injection for differential protection testing

Automatic Transfer Source (ATS) logic test

Testing of Intertrip / Interlock logical

DCS communication test (alarms, status)

2 LV distribution boards including protection relay setting (AREVA P127, P141, with primary and secondary injection).

Bus bar LV insulation tests (1 kV Megger), continuity and contacts quality (Low Resistance Ohmmeter / Ductor, torque value)

Secondary DC circuits test for each cabinet and energizing

Secondary injection for relays settings (Omicron Injection kit)

Energizing the LV Distribution Board from Temporary LV Power supply (2x1250 kVA Diesel Generators)

Automatic Transfer Source (ATS) logic test

Testing of Intertrip / Interlock logical

DCS communication test (alarms, status)

3 LV Variable Speed Drivers (VSD Schneider)

Crane Motor and Air Compressor Main Motor

4 Dual UPS systems (2x 60kVA; Chloride)

Battery bank load test (charging / discharging using load bank)

By-pass working test

Power transfer for maintenance test

DCS communication test (alarms, status)

5Emergency Diesel Generator

Power quality test (Voltage, current, frequency, harmonics)

Endurance test on the load banks

Starting dual battery bank tests

Auto / Man Synchronization with the main power

Power sheering test

Automatic Transfer Source (ATS) logic test

DCS communication test (alarms, status)

6Emergency LV Distribution Board

Bus bar insulation tests (1 kV Megger), continuity and contacts quality (Low Resistance Ohmmeter / Ductor, torque value)

Secondary DC circuits test for each cabinet and energizing

Secondary injection for relays settings (Omicron Injection kit)

Energizing the LV Distribution Board from Main Distribution board

Automatic Transfer Source (ATS) logic test with EDG

Testing of Intertrip / Interlock logical

DCS communication test (alarms, status)

7Dual Battery rectifier (110V DC; Chloride)

Battery bank load test (charging / discharging using load bank)

Power transfer for maintenance test

DCS communication test (alarms, status)

8MCC panels

Protection relays settings using secondary injection kit according with the design for motors, coolers, pumps

DCS communication test (alarms, status)

Phase rotation test (on the panels and field)

Power cables insulation, continuity, drop voltage tests

Motors vibration and temperature measurements

9Normal and emergency lighting

LV cables testing (insulation, continuity, connections)

Lighting fixtures checking

JB sealing and connection checking

Energisation and light level measurements

10Lightning and grounding

continuity and contacts quality (Low Resistance Ohmmeter / Ductor, torque value

11Trace heating system

LV Distribution Panel checking (leakage current protection test)

Insulation test

Energisation and temperature control checking

DCS communication test (alarms, status)

126 x 2 MVA transformers 6.6 kV / 460 V

Primary and secondary winding insulation test

Primary and secondary winding continuity and resistance

Marshaling box checking (oil temperature, oil level, gas pressure)

Oil breakdown voltage test (laboratory test)

Transformer ratio check

Energisation from Temporary Power Supply and OTP performing

13HV Motors

HV Power cables insulation, continuity,

Protection Areva relay setting

Phase rotation test (on the panels and field)

Motors vibration and temperature measurements

DCS communication test (alarms, status, control)

14DG Load Testing

Steam Turbine Generators 6.6 KV, 10 MW performance load test using load bank

SOLAR Turbine Generators 6.6 KV, 10 MW performance load test using load bank

Load test with step of 25%,50%,75%,100% & 110%

Load rejection test from 100% to 50%to 0%

Load rejection test from 100% to 0%

Syncho Checks using load bank for two more generators

15PMS Test

Remote Synchronization between the two or more generators

Load Sharing test

Load Shedding test

Preferential shedding test

DG Auto start for back up test

Remote start and stop MV Motors

Remote start and stop LV Motors

Remote Open/close the MV breakers

Remote Open/close the LV breakers

Monitoring Active and reactive power

Earth fault monitoring of MV switch boards

Earth fault monitoring of LV switch boards

The commissioning and start-up test was performed in the presence of Contractor Representative and Vendors.

2004 to 2006 ABB LIMITED – Bangaluru -India

Site Engineer

Projects : WIPRO SOFTWARE PARK -BANGALURU AND WOCKHARD HOSPITALS

Client : WIPRO / WOCKHARD

Department : Building Division and Building Automation Division

Lead a team for calibration, loop checking and pre-commissioning of power and instrument systems involved during the construction of vessels.

Attend FAT’s and check the performance of the system as per IEEE/IEC standard.

Commissioning of utility and HVAC systems.

Coordinate with clients and certifying agencies for daily inspection activities.

Test the I/O points for vessel monitoring systems.

Review the check sheets and confirm with the vendor data provided by the contractor.

Preparation of Test reports. Review of Schematic drawings & Cable schedule. Preparation of Testing and Commissioning activities Schedule. Preparation of work procedure for modification work. Preparation of as built drawings. Vendor co-ordinations Preparation of Job Safety Analysis (JSA) Co-ordination with clients and work force supervisors Preparation of work schedule and start-up co-ordinations Preparation of work permit and co-ordination of execution Total electrifications work including erection, testing and commissioning of Transformers, HT switchgears, LT switch gears, Diesel Gensets and 3000 A sand wich busduct and SCADA system

1995 to 2004 PETRON ENGINEERING CONSTRUCTION LIMITED –MUMBAI

Electrical Engineer

Client : ACC CEMENTS LIMITED/ MANALI PETROCHEMICALS LIMITED

Perform mechanical completion & commissioning activities for electrical & instrument equipments.

Coordinating and supervising the team executing the discipline work activities and assisting with relevant technical support as required, including mentoring and On the job training of junior personnel

Participating in and assisting with the co-ordination of the Project’s performance test

Do calibration and loop checking, megger testing of HV/LV power cables.

Perform megger test and measure the winding resistance for all electrical motors.

Assist vendor during commissioning of generators, MCC, UPS, F&G, PAGA and utility systems

Implement all activities in accordance with company safety procedures and manufacturer’s recommendations in hazardous and non hazardous area classification.

1994 to 1995 APPRENCESHIP TRANIEE-Office of the Chief Electrical Inspector to Government- CHENNAI/INDIA

Undergone training in the Government Electrical standards laboratory to calibrating the Rotating sub standard meters. KWH meters, RSSKVArh meters, Trivector meters, measuring instruments such as ammeters, voltmeters, tong testers, earth testers, insulation testers, and testing of motors, high voltage transformers, and high voltage cables.

1992 to 1993 ASSISTANCE



Contact this candidate