Name : Aamir Shahzad
Profession : Land Surveyor
Date of Birth : 04 April 1989
Permanent Address : Village kalas post office K.T.S dist/Teh Haripur
Years of Experience : 11 years
Nationality : Pakistani
Languages. : English,Arabic,Urdu
Mobile : +974-********
Email : ********.******@*****.***
Having exposure in Land Survey works including very good experience in Oil and Gas Plant, Petrochemical Plant, Building work, Main hole pipe line work, Electrical Substation works have an overall experience of 8+ years in Pakistan KSA & Qatar.
Academic
Session
Board/ University
S.S.C
2005
BISE Abbottabad
D.Com
2007
NWFP Board of Technical Education Peshawar
B.COM
2009
NWFP Board of Technical Education Peshawar
Land Surveying
2010
Ali Poly Technical college Haripur
Optic sense Trading & Contracting (QATAR) 15/02/18 to 01/05/2019.
Project: 01
Clint : KAHRAMAA
Main Contractor : National Contracting Company (NCC)
Design & Construct New Orbital Highway & Truck Road (P023-NOH3) New Orbital Highway Messaieed-Salwa Road.
Project: 02
Clint : KAHRAMAA
Main Contractor : National Contracting Company (NCC)
GTC 643E/2014-66kV / 120MVA CABLE LINE Umm Al Amad Super and Bu Garn SUBSTATION.
Project: 03
Clint : KAHRAMAA
Main Contractor : SIEMENS
GTC643D/2014: 66kV / 120MVA CABLE LINE Mehairja Super and Mehairja-1 SUBSTATION
Project: 04
Clint : KAHRAMAA
Main Contractor : SIEMENS
GTC 735C/2015: 66kV, 2000 Sqmm, 120 MVA Power Cables from New Terminal Compound to 66kV GIS at Umm Al Amad S/S
Projects: 05
Clint : KAHRAMAA
Main Contractor : SIEMENS
MONTAZAH NORTH S/S – OLD GHANIM S/S
Diversion of Existing 66kv 300Sqmm 40 MVA cable route from Existing 66kv GIS at Museum Road into 66kv GIS at Old Ghanim.
Projects: 06
Clint : KAHRAMAA
Main Contractor : SIEMENS
GTC/735C/2015-66/11kv AL WAAB SUBSTATION (UPGRADE)
Lilo of Existing 66kv 1000 Sq.mm 80 MVA Cable Circuit (AL WAAB SUPER-MEHAIRJA SUPER) TO AL WAAB S/S.
OMAR BIN ATEK FOR GENERAL CONT. EST. (KSA) (03 year)
Clint : ARAMCO
Main Contractor : SINOPEC CHINA
Jazzan Refinery and Terminal Project.
Product : GASOLINE DIESEL BENZENE.
Yanbu Petrochemical Plant.
Farabi Normal Paraffin and Derivative Complex (FYPC)
Responsibilities :
Structure foundation work.
Main hole work.
Pipe line work
Prepare survey report sheet and submit to client.
Maintain daily survey report and also inspection.
WASNA MANPOWER ISLAMABAD. (PAKISTAN) (03 Years)
Project 01:
Clint : Fazaia Government of Pakistan
Fazaia housing scheme
Building and plot layout,Mainhole,Pipeline,Road,Waterline,Gasline,Electric pole.
WORKING RESPONSIBALITIES
Develops work plans, methods and procedures to perform surveying tasks.
Collects and analyzes field data; performs complex survey and engineering computations.
Ensure adherence to safe work practices and proper use of traffic control measures during field work.
Arrange for regular spot check on work and records.
Maintain all instruments and instrument register as per Contract requirements.
Spot checks instruments in use to ensure that they are duly calibrated and in good proper adjustment.
Operate instrument
All kind of total station can operate.
Present using Stonex Total station & GPS Leica GS 08 Plus
YANBU PETROCHEMICAL PLANT
CURRICULAM VITAE
Key Qualifications:
EXPERIENCE