Keen to have a challenging and performance oriented career with an organization of distinction which recognizes my true potential and provides me sufficient avenues for professional growth in the field of Electrical Engineering/ Utility/Maintenance/Designing/Planning/Operation/Project Execution.

EXPERIENCE

M/S BESTPACK LIMITED TANZANIA

Working with M/S Bestpack Limited Tanzania. Since Oct 2020 to till date as Shift Manager Operation Department (Maintenance, Utility, Production and Project).

M/S MANJUSHREE TECHNOPACK LIMITED

Working with M/S Manjushree Technopack Limited Baddi. Since July 2016 to Sep 2020 as Engineer in Engineering Department (Maintenance, Utility and Project).

COMPANY PROFILE

Bestpack is a leading rigid plastics packaging convertor in East Africa. Established in 2005 in Tanzania – PET Packaging business started in 2005. Largest capacity in PET Performs, Bottle and Jars. Strong relationships with all leading FMCG and Food Companies. Bestpack is a subsiadiaries of Safepak Group Kenya.

Safepak having totaled 04 plants in East Africa 400 stock designs in various shapes and sizes for different industry verticals, we also help you design and customize your packaging solutions. With our inventively designed and exhaustive product range we are packing needs for almost everyone assortment includes Injection Molding, Injection Stretch Blow Molding, PET Performs and Compression Molding.

JOB RESPONSIBILITIES

Operation Excellence:-

Creation and implement best operation practices, strategy, policies, processes and procedures to aid and improve operational performance.

Operation and maintenance of ASB machines.

Oversee operational cost, risk and audit activities.

Develop productive, profitable and achievement oriented working environment.

Develop a system for scrap management.

Optimization of manpower as per production requirement.

Maintenance Activities & Documentation:-

Creation and implement best maintenance practices, strategy, policies, processes and procedures to aid and improve operational performance.

Develop a preventative maintenance schedule, ensure full preventative maintenance is carried out, plan for missed maintenance activities, and lead the team to deliver effectively.

Develop SOPs for operation & maintenance.

Ensuring Implementation of SOPs.

Prioritize the maintenance and repairs of company equipment and parts.

Ensure efficient repair schedules and review repair cost estimates.

Ensure proper operation & documentation of Utility Equipment’s & Machines such as Cooling Towers, Chillers, HP & LP Air Compressors, Electrical Equipment, 33/11 KV substation, 11/.433 KV substation etc.

Perform root cause analysis and resolve problems by 5 Y, fish bone and other tool.

Report on achievement of targets and identify any actions required.

Monitor the completion of tasks and ensure good performance and record on appropriate systems.

Prepared complete MIS report and presentation for the month activity.

Statutory Compliances and Audit:-

Update the list of statutory compliances and prepared schedule for its.

Audit and ensure compliance of the engineering data systems.

Successful audit completion such as ISO, FSSC, Sedex and customer audits.

Produce written reports and make presentations.

AMC /CMC Management, Vendor & Contractor Management:-

Ensure all CMC/AMC are done on times & schedule

Schedule both internal and external works maximizing planned down time and reducing unplanned downtime.

Coordinate work performed by outside vendors/contractors

Manage contractors on site to ensure they meet legal and company requirements.

Liaise and communicate with other departments, customers, suppliers and other service providers.

Spares Management & Budgets:-

Identification of Spares Required, Indenting and follow-up for procurement. Control and monitor inventory. Ensure availability of required spares.

Prepare the annual Maintenance budget and forecasts and all Capital Expenditure proposals as well as ensuring compliance with legal standards. Manage the budget from identification to completion of projects.

Power/Cost Saving:-

Identify the areas where power/Cost saving can be achieved & prepare detailed report showing cost benefit analysis.

Implement energy/general cost saving initiatives.

EHS:-

Adherence of 7 Safety Absolutes

1.Working on Height

2.Lockout Tag out

3.Machine Safe guarding

4.Confined Space Entry

5.Electrical Safety

6.Fire Safety

7.Mobile crane and EOT Crane Safety

Project:-

Project Planning.

Project mapping through Bar Chart, pert charts and other graphs.

Maintains project schedule by monitoring project progress, coordinating activities, and resolving problems.

Maintains project database.

Erection & commissioning of utilities such as Cooling Towers, Chilling Plant, Compressors, RO Plant, Machines, Fire hydrant etc.

Erection & Commissioning of Utility pipelines as per machines requirement.

Erection & Commissioning of Electrical panel.

Erection & Commissioning of Earth Pits, Cable tray, Cable Laying, Earth strip laying etc.

Erection & commissioning of transformer and DG Sets.

Prepare Daily project report and discuss with project manager.

Support Project Manager with mechanical project establishment and closeout.

Prepare BOQ and project executions.

Coordinate work performed by contractor.

Develop and review of complex mechanical project calculations.

Prepare reports and study existing technical information clearly and precisely to attain client requirements.

Guide project installation and commissioning on final load testing.

Bill checking & review as per BOQ & measurements.

EDUCATIONAL CREDENTIALS

Examination

Board/university

Year Start

End Year

Percentage

B. TECH in Electrical and Electronic Engineering

UTTARAKHAND TECHNICAL UNIVERSITY

2013

2016

71%

DIPLOMA in Electronics

UBTER

2010

2013

73%

S.S.C

UK BOARD

2009

2010

59%

H.S.C

UK BOARD

2007

2008

65%

Extra-Curricular Accolades:-

Best Documentation Award 2018.

Appreciation Letter during working on Covid Safety.

Participated in National Service Scheme activity.

PERSONAL INFORMATION

FATHERS NAME : MR. SANJAY KUMAR SAINI

DATE OF BIRTH : 03 JANUARY 1992

SEX : MALE

MARITIAL STATUS : UNMARRIED

KNOWN LANGUAGE : ENGLISH, HINDI

INTEREST : COOKING, READING.

DECLARTION

I consider myself familiar with ELECTRICAL ENGINEERING aspects. I am also confident of my ability to work in a team.

I hereby certify that the all information furnished above is true to best my knowledge.

Date: (ABHISHEK SAINI)

Place:

ABHISHEK SAINI

Contact: +91-892*******, 701-***-****

Email:adom3p@r.postjobfree.com

POSTAL ADDRESS

S/O- SANJAY KUMAR SAINI

VILL-PRATEETPUR, P.O-DHARMAWALA

DISTT.-DEHRADUN

UTTARAKHAND – 248142

INDIA