Specialist with 28+ years of experience in Process Control, automation, instrumentation, commissioning and Engineer lead in oil and gas production upstream, midstream and downstream. Collaborative problem solver, process improvement, maintenance, project management and training strengths to turnaround trouble operations. Expert in identifying root cause of issues and translating complex process into clear, understandable and actionable steps. Enthusiast leader who consistently meets commitments with integrity.

Skills

Engineering Commissioning and Startup Steam and gas turbine power generation Panel design SHA Standards EPC Projects PLC’s DCS’s (Honeywell Experion C-300 & S-300, Yokogawa, Delta V, PlantPax) Anti-surge systems tuning control loop New technologies Proactive and innovative Security Protection Systems ESD Systems Safety PLC Safety Instrumentation (H2S, Gas, Fire) HMI’s (factory talk, Wonderwere, Red lion - Crimson, Indusoft, Ignition, Experion Instruments Sizing Solar Cell Power System Maintenance

Work History

Intech Process Automation, Houston, TX 2018 - Present Control System Engineer - Programming & Supply of Control Panels

Designed, configured, programmed and commissioned the control system of 5 projects

Commissioned 10 projects, including PLC, HMI, third party communication and Scada

Upgraded one control system Steam turbine power generation

Upgraded one control system Gas turbine power generation and compressor

Configured, programmed and commissioned safety PLC and Honeywell S-300

Installed, configured and FAT for security protection system:

2 Senstar system (Fence Protection): Controller, Processor, Network Manager (Server) and Remote Supervision Workstation.

2 Access control system: Controller access M2150 and Server

2 CCTV system: NVR, fixed cameras and PTZ cameras Dresser – Rand (a Siemens Business), Houston, TX 2017 - 2018 Commissioning, control and instrumentation, Steam Turbo Generator - Control system Upgrade Work Location: YPFB Refinery-Bolivia

Reviewed and update the control logic, and created new operational strategy (operation modes) for 5MW steam turbo generator, to ensure the work performed is in accordance with Client Specifications / Contract Requirements, applicable Codes and Standards, budget and Government Regulations.

Supervised 30 project people

50 Electrical and control loops checked.

Configured and calibrated of the auxiliary’s devices: Woodward over speed, 3300 Bentley Nevada vibration and temperature, Frequency to 4 – 20 mA converter, vibration monitoring and analysis system and combination generator control module (CGCM) and instrumentation.

5 Control loop PID’s tuned.

Configured and programmed HMI Indusoft

Douglas G. Avendano P.

adoknf@r.postjobfree.com • Katy, TX 77494 • 661-***-**** https://www.linkedin.com/in/douglas-g-avendaño-p-90742219/

Configured operation modes: VAR, AVR, PF, Droop, CCC HPI – LLC, Houston TX 2014 - 2017

Senior Control Engineer, Gas Turbo Compressor and Generator – Control System Upgrade Work Location: Houston USA,

Argentina

Gas Turbo Compressor – Control System Upgrade:

Leaded all phases of the engineering; Feed, detail engineering, construction phases, commissioning and startup, providing input into the planning and execution of projects, including milestones, schedule and budget with client, during weekly status meeting. The work was performed is in accordance with relevant Client Specifications / Contract Requirements, applicable Codes and Standards, Government Regulations.

Supervised 20 project people

Sized anti-surge control valve, cables and more than 50 Instruments (transmitters and RTD)

Defined construction and 10 tuned control loop.

Developed Control Narrative and Cause and effect diagram.

Installed the ESD control system.

PLC designed, selected, configured and programmed.

Configured and programmed HMI Wonderwere

Gas Turbo Generator – Control System Upgrade:

Leaded all phases of the engineering; Feed, detail engineering, construction phases, commissioning and startup, providing input into the planning and execution of projects, including milestones, schedule and budget with client, during weekly status meeting. The work was performed is in accordance with relevant Client Specifications / Contract Requirements, applicable Codes and Standards, Government Regulations.

Supervised 15 project people

Sized conduits, cables, 2 MCC, 1 switchgear, Transformer and 20 instruments

Defined construction and 10 tuned control loop.

Developed Control Narrative and Cause and effect diagram. Processes y Business Integrals C.A., Bakersfield, CA 2013 Control and Instrumentation, AERA New Oil Treatment Plant Designed, development, implemented and installed Control systems for process control, supervision and ESD

Calculated and defined all Instruments (400) to Processes Supervisor and control.

Defined and construction 1000 control loop.

Developed Control Narrative and Cause and effect diagram.

Designed, development, implemented and installed of Scada and Turbine control systems

.

DRESSER RAND, Houston, TX 2003 - 2012

Field installation Manager, Project: Offshore Oil Production Platform - Automatization Work Location: Mexico- Houston

Douglas G. Avendano P.

adoknf@r.postjobfree.com • Katy, TX 77494 • 661-***-**** https://www.linkedin.com/in/douglas-g-avendaño-p-90742219/ Leaded all phases of the engineering; Feed, detail engineering, construction, commissioning and startup phases, provide input into the planning and execution of projects. Responsible for installation one of the largest companies’ engineering projects with an approximate budget of $30MM per year, SCADA and Turbine control systems. Project includes: platform, transfer pumps, FWKO, Heater Theater, Clarifier Tank, flow lines, casing gas system, power distribution system and associated utilities.

ESD systems.

Video and communications (Programming Cisco Router)

Designed and Installed of Fire, H2S and gas detection and extinguisher systems (CO2 & FM- 200), ESD systems.

Sized and defined all Instruments to Processes Supervisor and control. Education

Master, Development Manager, IESA (Business School), Caracas, Venezuela BA, Electronic Engineering, Polytechnic University – Barquisimeto, Venezuela Certificates

Process Automation – Certificate, Siemens Company – Pennsylvania SAP Human resources – Maintenance, Ciudad Ojeda, Venezuela ISO9002 Certificate, PDVSA, Ciudad Ojeda, Venezuela