NAGESH KARTHI PROJECT QUALITY MANAGER

Tell: +919********* Email : ado4z9@r.postjobfree.com

Name : NAGESH KARTHI

Nationality : Indian

Present Discipline : Project Quality Manager

Professional Qualification : CSWIP 3.1, Lead Auditor (ISO 9001:2015)

ASNT LEVEL II (RT, UT, MPT, DPT & VT)

ASNT Level 2- RTFI CERTIFICATION

Qualification : BE in Mechanical Engineering from

PSNA Anna University

Languages Known : English, Tamil & Hindi

Total Experience : 15+Years

CAREER SUMMARY:

Over 15 years of rich Piping experience in the various phase of EPC contracts construction jobs, fabrication, erection in the field of QA/QC and inspection associated with Refinery and Oil & Gas sectors, Cryogenic services, Power plants, Steel Plant etc..

Managing the Quality Team, for executing the Project as per Contract requirement in line with site team for the Quality Work.

Managing project Inspections which includes Pre-Inspection meetings, Quality Audit, Piping and liquefied Natural Gas (LNG),Sour and Non Sour Pipe line welding Inspection & NDT Inspection, Flange Management for high pressure rating lines, capable of handling of all NDT Inspection, Pressure Testing of Piping Above Ground / Underground pipe line,Piping & Valves Testing, Heavy structures, Stacks(chimneys),Pressure-Vessels and Boilers, Painting and Coating activities, Re-instatement, Equipment installation, GRP,GRE,GRVE and HDPE pipe works, Preservation & Final alignment Inspection. Having good experience of Painting to plan and complete all painting inspection as per client requirement, Holiday detection etc. and having working knowledge of API 1104, ASME CODES, API 510/653/570, AWS,DEP,ASTM

DETAILED PROFFESSIONAL EXPERIENCE:

CURRENT EMPLOYER: M/s Towell Engineering. Co. LLC – Muscat, OMAN (AVAILABLE IN KUWAIT OPERATIONS)

(Sep 2015 – Aug 2020)

Project Word:

Sl. No.

Projects

Year

Client

01

Al Zour refinery Project EPC

Feb 2018- present

EPC Contractor: HSS JV

Client – KIPIC

02

Liwa Plastics Industrial Complex

Sep 2017-Feb 2018

EPC Contractor: Tecnimont

Client – Orpic

03

Sohar Refinery Industrial Complex

Sep 2015 - Sep 2017

Client : Daelim Petrofac (DPJV)

Owner – Orpic

Project 1

Project Name: Al Zour refinery Project EPC

EPC Contractor: HSS JV

Client – KIPIC

Duties & Responsibilities - (Al Zour refinery Project EPC) (Handling: Piping,Pipeline sour and LNG Welding NDT,GRE/GRVE and structures):-

Preparation of Project quality presentations and produce in,project kick off meeting.

Get approval for Inspection Test Plan, Project Quality Plan, Project KPIs,Project Audit Plan, NDT Plan (Structural & Piping), Quality Control Procedures (Structural & Piping, LNG Pipelines, Equipment’s), Hydro test Procedure & Test Pack as per Client Specification & Applicable Standard Codes.

Attending Quality review and Project review meetings and prepare MOM to close the issues.

Understanding Issued Drawings (ISO, GA & P&ID’s) and scope of work. Discussion with Quality Control / Inspection team, Welding Engineer, GRE/GRVE Inspector, NDT Department for requirement as per Standard code & Client Specification.

Interacting with Client on QA/QC related issue (PQP, ITP’s/QCP’s, WPS/PQR, NDE Procedures, Mechanical Testing Procedure, Hydrostatic procedure as per Inspection & Testing Plan, Inspection Methodology & Criticality Rating of Each Items

Preparing WPS, PQR, GRE/GRVE QCP and review of GRE/GRVE vendor procedures .

Ensuring Training & Qualifying, welders and welding operators to start of new projects.

Verification of isometric drawing with respect to P&ID status. Ensure that master, control copies are controlled by team or not.

Ensuring the Daily piping, pipeline, Vessel and structural welding inspection carried out by welding inspectors according to the stage inspections according to the ITP phase.

Verification of inspection coverage and NDE coverage to clear the line for further testing. And ensure the repair percentage as per KPI.

Monitoring the inspection notifications and close outs, keep record to control the rejection and cancellation notification as per KPI

Planning, Supporting for Preparation of package and co-ordination with hydro test team to clear the pressure testing .

Supervision of flow Pipeline welding small to large diameter activities in Sour and LNG services, Bonding Activities to Ensure that the all activities are performed to the specific ITP’s & standards / Client specification

Ensure Line walk and clearing the punch

Check the hydro testing line,welding and NDT coverage,Supports.

Ensure the quality reports of hydro testing LNG pipe lines .

Check and clear the LNG, Sour underground pipeline painting and coating reports.

Check the Pressure gauge calibration, water test report and other equipment reports for Hydro testing.

Releasing test packages for Hydro test.

Responsible for reporting non-conformances if any and in Consultation with QC Engineer shall raise a NCR if required. Extra vigilance is required that no underground piping is buried under backfill prior to inspection and subsequent release.

Managing and coordinating the Reviewing and approve of QCP, PQP,MS,PQR,WPS,PQR procedures from sub-con.

Review DEP, Project specifications, company procedures, quality manuals, and scope of work to perform the required inspection.

Ensuring the GRE /GRVE daily Bonding activities and inspection progress.

Cross verifying the progress and updating data base for Laminators List

Ensuring with inspectors weather Preparing Inspection test record for GRE/GRVE line with ITP

Review of Qualification of Bonders or Bonding Operators laminators’ qualification as per ASTM D1599

Cross verifying the laminator and bonder ID cards and qualifications

Monitoring the Bonding surface temperature, humidity is as per vendor requirements

Monitoring GRE lamination process, ensure the method of process for lamination joints

Monitoring the GRE bevel end joint preparation method before lamination.

Ensure the Selection suitable lamination method and recipe according to the size and pressure rating system as per the lamination procedure.

Ensuring qc inspector will Check the mix ratio of resin and hardener, type of glass, resin and catalyst etc. The mixing ratio shall be as per product data sheet guidelines

Ensuring the lamination layers and required layers achieved.

Ensuring the team Conducting 100% visual inspection and ensuring no defects.

Monitor the heat blanket operation according the instruction given in lamination procedure.

Shall ensure throughout monitoring and surveillance that all GRE Works are executed in accordance with the Project specifications and are inspected accordingly.

Ensure throughout surveillance, that the storage conditions for GRE material are being maintained as per manufacturers' recommendations by the respective in-charge personnel.

Ensure and maintain the project team following the project plan, Project spec, company procedures and ASME international standards.

Conducting department meeting, prepare minutes.

Duties in Painting and coating to monitor the inspection activities;-

Ensuring with coating inspector Climate reading tables and temperature readings should be noted every 2hours humidity, wet bulb, dry bulb. Temperature measuring equipment should be available for that.

Monitoring the Painting system number should be as per our approved spec according to the line system and fluid

Confirming with painting inspectors that Paint coat surface should be cleaned as per our project spec, by compressed air ect.. it should be free from mud dust sand, grease .or other oil substances.

Cross verifying DFT,WFT, Holiday detectors should have calibrated and issued to the coating and painting inspectors

Surveillance and review of coating inspector Report preparation and ensuring the updated form is in use for reporting.

Project 2

Project Name: Liwa Plastics Industrial Complex

EPC Contractor: Tecnimont

Client – Orpic

Duties& Responsibilities - (Liwa Plastics Industrial Complex) (Handling: Cross country under groung Pipelines,Piping,HDPE,GRP and structures):-

Preparation & getting approval of Inspection Test Plan, Project Quality Plan, Project Audit Plan, NDT Plan (Structural,Cross Country Pipeline & Piping), Quality Control Procedures (Structural & Piping, LNG Pipeline and Equipment’s), Hydro test Procedure & Test Pack as per Client Specification & Applicable Standard Codes.

Understanding Issued Drawings (ISO, GA & P&ID’s) and scope of work. Discussion with Quality Control / Inspection team, Welding Engineer, GRP Inspector, NDT Department for requirement as per Standard code & Client Specification.

Interacting with Client on QA/QC related issue (PQP, ITP’s/QCP’s, WPS/PQR, NDE Procedures, Mechanical Testing Procedure, Hydrostatic procedure as per Inspection & Testing Plan, Inspection Methodology & Criticality Rating of Each Items

Supervision of flow line welding activities to Ensure that the all activities are performed to the specific ITP’s & standards / Client specification

Ensuring Training &Qualifying welders and welding operators, HDPE fusion operators and GRP laminators’ prior to start of new projects.

Ensuring the Daily welding inspection carried out by welding inspectors

Monitor the stage inspections according to the ITP phase.

Verification of inspection coverage and NDE coverage to clear the line for further testing.

Planning, Supporting for Preparation of package and co-ordination with hydro test team to clear the pressure testing .

Ensuring qc inspector will Check the mix ratio of resin and hardener, type of glass, resin and catalyst etc. The mixing ratio shall be as per product data sheet guidelines

Referring ISO 14692 -2002 Glass-reinforced plastics (GRP) piping (Part 1-2-3-4) for Barcoll Hardness Test Conformance.

Ensure throughout surveillance, that the storage conditions for GRE material are being maintained as per manufacturers' recommendations by the respective in-charge personnel.

Responsible for reporting non-conformances if any and in Consultation with QC Engineer shall raise a NCR if required. Extra vigilance is required that no underground piping is buried under backfill prior to inspection and subsequent release.

Managing and coordinating the Reviewing and approve ofQCP,PQP,MS,PQR,WPS,PQR procedures from sub-con.

Review DEP, Project specifications, company procedures, quality manuals, and scope of work to perform the required inspection.

Ensure and maintain the project team following the project plan, Project spec, company procedures and ASME international standards.

Conducting department meeting, prepare minutes.

Project 3

Project Name: Sohar Refinery Industrial Complex

EPC Contractor: Petrofac/Deilim DPJV

Client – Orpic

Duties & Responsibilities :Verification of Progress in Welding Piping and Pipelines, GRP Bonding, NDE and Painting activities

Planning, Supporting for Preparation of package and co-ordination with hydro test team to clear the pressure testing .

Ensure Welders are qualified, Man power, list as per the applicable code, a register is maintained to monitor their Ensure WPS/ PQR are prepared established approved as per the applicable code.

Ensuring the GRP daily Bonding activities and inspection progress.

Referring ISO 14692 -2002 Glass-reinforced plastics (GRP) piping (Part 1-2-3-4) for Barcoll Hardness Test Conformance.

Ensure the piping, pipeline & pipe fitting materials pressure ratings and materials are handled stored and preserved as per approved procedures. Ensure the issue receives the materials, checking of high pressure rating flanges of LNG line and trace abilities are maintained.

Coordinate with Customer Ensure and Supply the approved vendor list for Electrodes/filler wires and other consumables blasting and Paint Materials.

Status reporting and conduct team meetings to clear the Welding and NDT assessments as per project procedure and monitoring Non-Destructive Examinations and Radiographic Film interpretation. Discuss with team members and resolve problems.

Discuss with team to Re-solve the issues and Non confirming products.

Checking validate calibration certificate of equipment’s

Co-coordinating and confirming Preparation of documents and releasing test packages for Hydro test.

Supporting in Arrangements Witnessing Hydrostatic, Pneumatic pressure test.

Ensuring Coating Works QC Set-up meets as follows painting and coating procedures and application method of statements tracking

Follow up with painting and coating inspector for the activities are line with project requirements.

PREVIOUS EXPERIENCE: ABF Engineering (Qa/Qc Manager) - India

(Oct 2014 – Aug 2015)

Project Name: NPGCL –NABINAGAR, BPCL -KOCHI, JBF- MANGALORE

Client – BPCL, NPGCL, JBF

Sl. No.

Company

Year

Client

01

ABF ENGINEERING INTERNATIONAL PVT .LTD.

Project Name: NPGCL –NABINAGAR, BPCL -KOCHI, JBF- MANGALORE

Client – BPCL, NPGCL, JBF

Oct 2014 to Aug 2015

BHEL,L&T,THYSSEN KRUPP AND THERMAX

Duties in Project Progress (Handling: Pressure Vessels, Boilers, Ducts,chimney, Piping,Pipe liens and structures):-

Ensure Welders are qualified, Man power, list as per the applicable code, a register is maintained to monitor their Ensure WPS/ PQR are prepared established approved as per the applicable code. Verification of isometric drawing with respect to P&ID status. Ensure that master, control copies are controlled by team or not.

Verifying Local and International suppliers Incoming Raw material inspection and reviewing MTC Status and Maintain the Guide.

Ensuring the Inspection of incoming materials.(Structures,flanges, pipes plates ect. )

Preparation of weld maps and welding books.

Inspection of Pressure vessels, dimensions and fitments,cross verifying with the drawings

Coordinating and Check NDT coverage according to the requirements.

Structural fabrication inspections and mock ups to ensure the requirements.

Supports for Preparation of final dossier and dispatch

PREVIOUS EXPERIENCE: Samsung Engg Co. Ltd. UAE

(Feb 2013 – Oct 2014)

QA/QC Lead

Project Name: IRAQ WEST QURNA FIELD 2NDPHASE AND TAKREER CBDC Abu Dhabi

Sl. No.

Projects

Year

Client

01

SAMSUNG ENGG CO.LTD UAE

Iraq west qurna field 2nd phase

CBDC abu dhabi

Feb 2013 to Oct 2014

LUKOIL,TAKREER

Duties in Project Progress in Welding, NDE, Painting,Static equipment:-

Approving the WPS and PQR of Sub contractors.

Ensure the piping, sour and LNG under gound pipeline & pipe fitting materials are handled stored and preserved as per approved procedures. Ensure the issue receives the materials and trace abilities are maintained.

Ensure Welding Activities of small to large Piping and Pipeline

Inspecting High pressure ratings of fitting and materials using in Pipe and Pipelines in Sour,LNG projects

Planning, Supporting for Preparation of package and co-ordination with hydro test team to clear the pressure testing .

Ensuring the GRP daily Bonding activities and inspection progress.

Referring ISO 14692 -2002 Glass-reinforced plastics (GRP) piping (Part 1-2-3-4) for Barcoll Hardness Test Conformance.

Cross verifying all GRP GRE activities with inspectors.

Status reporting and conduct team meetings to clear the Welding and NDT assessments as per project procedure and monitoring Non-Destructive Examinations and Radiographic Film interpretation. Discuss with team members and resolve problems.

Discuss with team to Re-solve the issues and Non confirming products.

Coordinate with Clients and 3rd party agencies like (IRS,BVIL, ABS,DNV GL and TUV)

Managing project deliverables in line with the project plan.

Resolving cross-functional issues at project level.

Monitoring project QA/QC progress and performance.

Ensuring and make status of Inspection is being carried out according to the sub-con offer any clarifications as required.

Releasing of materials after review of final documents for next process.

PREVIOUS EXPERIENCE: Power Tech LLC Oman

(Aug 2012 – Feb 2013)

Senior QA/QC Engg.

Project Name: Gathering plant pipe lines nimar ph2 .MEDCO Energy, Oman

Client – MEDCO

Sl. No.

Projects

Year

Client

01

POWER TECH BOGS LLC, OMAN

Project Name: Nimr gathering pipe line expansion ph2

Aug 2012 TO Feb’2013

MEDCO

Duties in Project Progress in Welding, NDE, Painting,Static equipment:-

Preparation of WPS and PQR

Qualifying the Welder and HDPE fusion operator

Quality procedure preparation and getting approval

Pipeline welding and NDE inspection

NDT witnessing and reports review

RTFI review according to the acceptance criteria.

HDPE fusion and HDPE pulling into the pipelines

Preparing the Hydro testing packages and get reviewed by client.

Witnessing the Hydro testing and Chart recorder monitoring.

Checking and maintaining the Calibration status.

Ensure the piping & pipe fitting materials inspections

Monitoring project QA/QC progress and performance.

Preparing all inspection reports and get client clearance and signed

File the complete set of inspection documents and maintaining

PREVIOUS EXPERIENCE: KBR-KSA

(July2009 – June 2012)

QA/QC Engg.

Project Name: Saudi Kayan project,jubail 1

Client – SABIC

Sl. No.

Company

Year

Client

01

KBR, SAUDI

Project Name: SAUDI KAYAN PROJECT JUBAIL 1

July’ 2009 TO June’ 2012

SABIC

Duties in Project Progress in Welding:-

Daily welding inspection

Daily preparation of welding inspection reports

NDT witnessing

Hydro test package preparation and Line walk

Punch list preparation and punch point clearance

Understanding the WPS-PQR / AFC drawings / Specification.

Awareness of applicable Standards & Codes required for Welding & NDT, Material Testing.

Review of Inspection and Test Plan, Welding Procedures, Material Verification.

Witnessing for Welder Qualification, co-ordination with client during welder qualification.

Responsible for Welders performance evaluations / Welder Renewal .

Responsible for Fit-up/Visual Inspection.

Responsible for continuously monitoring welding activities.

Responsible for preparation for welding inspection record & shall conduct visual Inspection to client on daily basis.

Responsible for arranging team clearing visual inspection defect & NDT repair if any

Responsible for preservation & proper usage of material, welding consumables.

Shall monitor baking oven, holding ovens regularly.

Ensure that the welders are qualified to the applicable WPSs.

Check and record welding parameters and verify compliance with approved WPS.

Reports to QA/QC Engineer & Manager

PREVIOUS EXPERIENCE: GB ENGINEERING SERVICES PVT LTD India

(May2006 – May 2009)

QA/QC Inspector.

Project Name: PIPING ANDmechanical inspector

Client – CVCL

Sl. No.

Projects

Year

Client

01

GB ENGINEERING SERVICES PVT LTD

May 2006 to May 2009

CVCL

BHEL

Duties in Project Progress in Welding:-

Daily fit up and welding inspection

Daily preparation of welding inspection reports

Dimension checking of piping

NDT requesting and clearing the reports

Review of iso-metric drawing and verifying with the pipe fabrications

Hydro testing at shop and release the pipe to site

Final documents preparation and clearance

QMS Audit responsibilities: -

Documents & Records Control shall be maintained as documented Quality System described in ISO 9001:2015 in up to date latest editions.

Review and digesting the latest changes in latest editions and implementation.

Audit documents and records maintenance.

Ensuring the requirements of ISO QMS and fulfilling the requirements.

Audit findings follow up and monitor the measures.

Preparing for internal and external audits.

Maintaining documents for ISO certification and recertification process for organization.

Preparing Audit checklist, Agenda Conducting internal Audits for improvements and preparing for certifications.

Conducting External Audit for Vendors for assessment and vendor approval.

Keep & maintain a library of company spec, procedures, international standards, codes etc as Client applicable spec & standards, API 1104, ASME CODES, API 510/653/570, AWS etc.