CURRICULUM VITAE

KIRAN NATH

+965-******** / 99331384

*****.******@*****.***

PLANNING ENGINEER (PMP®)

OBJECTIVE

To Purpose a challenging career in the field of Project Planning and scheduling this provides adequate opportunity for utilizing my knowledge, skill and experience. A Certified Project Management Professional (PMP) specialized in project planning and scheduling the project with Primavera & MS Office Projects.

Seeking for the challenging role in a quality environment, my knowledge can be shared and developed. Looking for a good opportunity where I can improve my ability, quality, and project management skill. I was trained well and prepared to move with increased responsibility, and look forward the challenges of Oil and Gas / Refinery, & Petrochemical Industries

I will use my proven track record as a Planning Engineer to gear up and contribute to the growth of the company with dedication and add value to the company. PROFILE SUMMARY

Over 11 years of work experience (EPCC) in Project Planning and Control Engineer for Oil and Gas type of EPCC projects (Inc.…Civil, Marine (Offshore), Mechanical, Electrical, & Instrumentation, and Commissioning related works)

Presently associated with M/S. Gas and Oil Field Services Co. in Kuwait as a Planning engineer.

Support to develop and maintains the various Levels of integrated Engineering and EPCC schedules/cost control programs.

Responsibility for providing direction and control of planning function, supporting to site execution when necessary.

Supporting to preparation of planning packages

Prepares monthly status reports for the projects to keep the client and company’s management informed of construction progress and status of costs and schedule as related to budgets and previous forecasts.

Delay analysis of subcontractor’s schedule to review the progress and report to the management.

Prepares the Project Organization Chart, Project Management Consultant/Third Party inspection Services, Manpower allocation Chart and Mobilization / Demobilization plan for Design and Construction Projects

Involves in the preparation of the EPC Base line schedule for Oil & Gas Projects including Progress Measurement System, Resources Loading, ‘’S” curves, Bar Charts, Histogram etc. using PRIMAVERA P6 V7.0 software in accordance with contractual scope of work and project duration by considering the QA/QC, HSE Standards, rules and regulations of Client.

Updating the CPMS and preparation of Meeting Materials for Weekly Construction Meeting to the Client

Monitors the actual site construction progress of Sub Contractors daily and ensure the reports accurately reflect the actual performance and productivity.

Preparing progress percentage calculation systems, earned man-hours, productivity & Trend analysis.

Progress measurement using S-Curves.

Preparing executive Progress Summary Report, Presentation to the Top Management on Project status for periodical review.

Involved in Shutdown related works.

Support for Pre-commissioning activities to follow-up the progress in a certain way like, system and sub-system wise

Page 2 of 7

EMPLOYMENT DETAILS

GAS AND OIL FIELD SERVICES CO. K.S.C.C, Kuwait

TECNICAS REUNIDAS (TR), KNPC GT5 Project – Kuwait

DAELIM INDUSTRIAL Co., Ltd., KNPC SHFP Project, Kuwait

DAELIM INDUSTRIAL Co., Ltd, KNPC FCC Revamp Project, Kuwait

DAELIM INDUSTRIAL Co., Ltd, KNPC GT-4 Project, Kuwait

TECH SHARP Engineers (P) Ltd, BPCL CEMP-Phase-II, India

PROJECTES HANDLED:

Desalter Package EPF-50 facility, KOC

Installation of Alternative Auto vent Floater For TK-34-407 & TK-34-414 at MAA Refinery

Gas Train-5 (GT-5) at MAA Refinery, Kuwait

Sulphur Handling Facilities & Revamp Project (SHFP) at MAA Refinery, Kuwait

FCC (Fluid Catalytic Cracking) & Revamp Project at MAA Refinery, Kuwait

Gas Train-4 (GT-4) at MAA Refinery, Kuwait

Capacity Expansion cum Modernization Project – Phase-II, Kerala, India

SHUTDOWN RESPONSIBILIES

Preparation of Shutdown Micro schedule in terms of Hourly / Shift basis based on Operation windows.

Assign resources to the activities to prepare Mobilization plan

Prepare progress measurement system based on the resources assigned.

Reschedule the plan if any unforeseen events happened.

Follow up Engineering and procurement related with the Pre-shutdown and Shutdown requirement.

Update Tie-in Readiness Traffic checklist to confirm the readiness.

Follow up the progress regularly and update daily report and issue to client / operation teams.

Daily update the progress to analyze deviation in the schedule and inform to the Shutdown team for improvement.

CIMS (Construction Production Control Management System) CIMS is a Construction Production Control Management System (E-data base) that covers whole project cycle documentation & data records update like,

- Construction Piping Fabrication/ Erection, Equipment Erection, Steel Structure Erection

- Quality documentation (NDE reports, status, etc.)

- Work Progress / Work plan / Test packages / Commissioning / Turnover, etc.

- Welder Qualification details and WPS info

- All kind of above related scanned QA/QC Certificates duly signed by Client. Education, Skill & Certifications

Bachelor’s Degree in Mechanical Engineering

PMP (Project Management Professional) – Certified

Primavera P6 8.2.0

Software Known

- MS Office package

Page 3 of 7

- Construction Database application

- AutoCAD

Experience: (11 yrs.)

Project 6:

Presently working as a Planning Engineer with M/S Gas and Oil Field Services Co. K.S.C.C, Kuwait from May-2021 for KOC Desalter Project and Auto vent Floater Line Project in Mina Al-Ahmadi Refinery, Kuwait Project Description: -

Projects Name : KOC Desalter Project & KNPC Auto Vent Floater Line Project Client : KOC & KNPC

Location : KOC North Kuwait / KNPC MAA Refinery

The scope of the project includes engineering, procurement, construction, pre- commissioning and the necessary services for the commissioning and performance test of the Facilities. Responsibilities:

Update the overall Schedule based on the Approved Baseline schedule and review, compare the subcontractor schedule along with client schedule.

Overall system summary status report preparation

Updates Engineering Progress from the EDDR log on weekly basis.

Priority system status report preparation and monitoring

Prepare Manpower analysis based on current work front availability both client & Subcontractor.

Preparation of disciplines Quantity “S” Curves for the remaining works from production Controls application system

Review Subcontractor Quantity “S” curves based on subcontract agreement and highlight to the management about variance report.

Preparation of Monthly, Weekly progress updates for Clients / Internal report

Preparation of Layouts by area / Discipline to higher management for ongoing activities

Preparation of Client certification for different disciplines from the supporting production Control documents on Monthly basis

Supporting for the preparation of documents related to unpredictable events.

Supporting for the preparation of Vendor mobilization plan

Reviewing and finalizing of subcontractor’s invoices Project 5:

Worked as a Planning Engineer with TR (Tecnicas Reunidas) from Jan 2018 to April 2021 for Gas Train- 5th (GT-5) Project, Mina Al-Ahmadi Refinery, Kuwait Project Name : Fifth Gas Train (GT-5)

Client : KNPC (Kuwait National Petroleum Corporation) PMC : WOODS Group

The scope of the project includes engineering, procurement, construction, pre- commissioning and the necessary services for the commissioning and performance test of the Facilities. Facilities: Pre-treatment facility, Fractionation column, Gas treatment unit, Natural gas liquid (NGL) recovery unit, Refrigeration unit, Sour water stripper, Water treatment unit, Offsite and Utilities Responsibilities:

Update the overall Schedule based on the Approved Baseline schedule and review, compare the subcontractor schedule along with client schedule.

Supporting for the preparation of Vendor mobilization plan Page 4 of 7

Overall system summary status report preparation

Updates Engineering Progress from the EDDR log on weekly basis.

Priority system status report preparation and monitoring

Prepare Manpower analysis based on current work front availability both client & Subcontractor.

Preparation of disciplines Quantity “S” Curves for the remaining works from production Controls application system

Review Subcontractor Quantity “S” curves based on subcontract agreement and highlight to the management about variance report.

Preparation of Monthly, Weekly progress updates for KNPC / Internal report

Preparation of Layouts by area / Discipline to higher management for ongoing activities

Preparation of Client certification for different disciplines from the supporting production Control documents on Monthly basis

Handling project overall site reparation works.

Preparation of Process and Utilities Tie-in Schedule inter-connecting with Existing plants from the Execution windows based on Operational shutdown plan for Piping, Electrical, Instrumentation, Hot tap. Update the Tie-in readiness checklist on weekly basis.

Site progress photography report preparation for monthly/weekly basis

Supporting for Claim related documentation works.

Supporting for the preparation of documents related to unpredictable events.

Supporting for the preparation of Vendor mobilization plan Project 4:

Worked as a Project Planning Scheduler in DAELIM Industrial Corporation from Dec 2015 to Jan 2018 for Sulphur Handling Facilities & Revamp Project (SHFP), Kuwait Project Description: -

Project Name : Sulphur Handling Facilities & Revamp Project (SHFP) Client : KNPC (Kuwait National petroleum Corporation) Location : Mina-Al-Ahmadi Refinery, KNPC

Scope of Work: The new part consists of the following: Four new Liquid Sulphur Storage Tanks & Liquid Sulphur Feed Pumps, Five additional Granulator units and integration with the existing units, New belt Conveyor system and Longitudinal Storage Hall, New Stacking & Reclaimer machine, New belt conveyor system to the new ship loader, New independent Solid Sulphur Pier & New Ship Loader (Off-Shore work), Dust suppression system to avoid dust emissions in the plant and port, State of the art Instrumentation, communication, safety, fire detection & firefighting systems

Responsibilities:

Update the overall Schedule based on the Approved Baseline schedule and review, compare the subcontractor schedule along with client schedule.

Responsible for Daily / Weekly / Monthly reports generation including ‘S’-curves for client & Management review.

Monitoring and update the day-to-day site activities, manpower and equipment’s utilization for Construction activities.

Responsible for make the advance Weekly working plan for client review

Analysis of Subcontractors Weekly and Monthly Reports and co-ordinate to project manager regarding delayed items

Reporting Site Manager & Project Control Manager

Attending Meeting with Client on weekly basis

Coordinating with Subcontractors

Identifying the area of concern and critical path of the project to ensure Project completion. Page 5 of 7

Co-ordination with different departments in project to smooth flow of project

Inspecting field sites to observe and evaluate site conditions and to collect field survey data and measurements.

Industrial photography for Presenting the Site the progress to the Management and the Client

Preparing for the non-productive working hours details for claiming purpose

Evaluation & Processing of Subcontractors Monthly Invoice.

Dealing with Subcontractors regarding pending issues and clarifying with the management

Analyzing the KPIs delay in weekly basis to inform to the responsible team and management Project 3:

Project Description: -

Worked as a Project Planning Scheduler in DAELIM Industrial Corporation from Nov 2014 to Dec 2015 for FCC & Revamp Project, Kuwait

Project Name : FCC (Fluid Catalytic Cracking) & Revamp Project Client : KNPC

PMC : AMEC Foster Wheeler

Scope of Work:

The scope of the company was to build facilities to treat Phenol acid water and cooling tower to supply cooling water to FCC and construct acid water treatment facilities. The major activities for revamping is the replacement of existing Reactor with Regenerator and also Modification for equipment as per new facility, piping tie in work for utility and process line also been done. Responsibilities:

Update the overall Schedule based on the Approved Baseline schedule and review, compare the subcontractor schedule along with client schedule

Responsible for Daily / Weekly / Monthly reports generation including ‘S’-curves for client & Management review.

Monitoring and update the day-to-day site activities, manpower and equipment’s utilization for Construction activities.

Responsible for make the advance Weekly working plan for client review

Analysis of Subcontractors Weekly and Monthly Reports and co-ordinate to project manager regarding delayed items

Reporting Site Manager & Project Control Manager

Attending Meeting with Client on weekly basis

Coordinating with Subcontractors

Identifying the area of concern and critical path of the project to ensure Project completion.

Co-ordination with different departments in project to smooth flow of project

Inspecting field sites to observe and evaluate site conditions and to collect field survey data and measurements.

Industrial photography for Presenting the Site the progress to the Management and the Client

Preparing for the non-productive working hours details for claiming purpose

Evaluation & Processing of Subcontractors Monthly Invoice.

Dealing with Subcontractors regarding pending issues and clarifying with the management

Analyzing the KPIs delay in weekly basis to inform to the responsible team and management Project 2:

Worked as Project CIMS Controller and Planning Scheduler in DAELIM Industrial Corporation from Feb 2012 to Nov 2014 for LPG Train # 4th Project, Kuwait Project Description: -

Page 6 of 7

Project Name : Fourth Gas Train (LPG Train-4, GT-4) Client : KNPC (Kuwait National petroleum Corporation) PMC : AMEC

Scope of Work : EPC LSTK (E,P,C, Precomm, Comm/Startup & Performance Testing Assistance) The scope of the project includes engineering, procurement, construction, pre- commissioning and the necessary services for the commissioning and performance test of the Facilities. Facilities: Pre-treatment facility, Fractionation column, Gas treatment unit, Natural gas liquid (NGL) recovery unit, Refrigeration unit, Sour water stripper, Water treatment unit, Offsite and Utilities Responsibilities:

Responsible for Daily / Weekly / Monthly reports generation including ‘S’-curves for client & Management review.

Monitoring and update the day-to-day site activities, manpower and equipment’s utilization for Construction activities.

Analysis of Subcontractors Weekly and Monthly Reports and co-ordinate to project manager regarding delayed items

Reporting Site Manager & Project Control Manager

Coordinating with Subcontractors

Co-ordination with different departments in project to smooth flow of project

Inspecting field sites to observe and evaluate site conditions and to collect field survey data and measurements

Industrial photography for Presenting the Site the progress to the Management and the Client

Evaluation & Processing of Subcontractors Monthly Invoice.

Dealing with Subcontractors regarding pending issues and clarifying with the management

Analyzing the KPIs delay in weekly basis to inform to the responsible team and management

Updating all related to Piping production and QC documents for monthly payment process Project 1:

Worked as a Planning Asst. in Tech-Sharp Engineers Pvt. Ltd. from Aug 2010 to January 2012 for CEMP PHASE- II (VGO/HDS) at M/S Bharat Petroleum Corporation Limited, Cochin Refinery, Kerala. Project Description: -

Project Name : Capacity Expansion cum Modernization Project – Phase-II Client : BPCL (Bharat Petroleum Corporation Limited) Contractor : Tech-Sharp Engineering (P) Ltd.

Location : COCHIN REFINERY, Kerala, India

Summary: Phase-II of the Capacity Expansion cum Modernization Project (CEMP) envisages to set up facilities for producing auto-fuels complying with Euro-III / IV quality specifications and to increase the refining capacity from 7.5 MMPTA to 9.5 MMPTA. Revamp of CDU-II for capacity expansion by 2.0 MMTPA. Responsibilities:

Supporting to prepare for Daily / Weekly / Monthly reports generation including ‘S’-curves review.

Supporting for monitoring and update the day-to-day site activities, manpower and equipment’s utilization for Construction activities.

Supporting for Inspecting field sites to observe and evaluate site conditions and to collect field survey data and measurements.

Supporting for Field photography for Presenting the Site the progress to the Management and the Client

Supporting for evaluating Subcontractors Monthly Invoice.

Analyzing the KPIs delay in weekly basis to inform to the Senior planner

Supporting to update all related to Piping production and QC documents for monthly payment process

Supporting for invoice to Client for the progress achieved. Page 7 of 7

Personal Info:

Name : Kiran Nath

Date of Birth : 04-March-1988

Gender : Male

Marital Status : Married

Languages Known : English, Hindi, Tamil & Malayalam Mobile Number : +965-******** / 94732353

Local Address : Al-Mangaf, Kuwait

Nationality : INDIAN

Civil ID No : 288********* (Article -18, Transferrable) Passport Expiry : 20-03-2027

Driving License : Valid Kuwait Driving License (LMV) Declaration

I hereby declare that the above particulars are true to best of my knowledge and I assure you that I will work in right earnest.

Place: Kuwait (Kiran Nath)